Becker v. National Prohibition Park Co.

23 N.Y.S. 380 Court N.Y. Gen. Term Decision date 1893-05-08 English

Delivered by BARNARD, P. J.

Contents

Majority

p. 380
(69 Hun, 55.)
BECKER v. NATIONAL PROHIBITION PARK CO.
(Supreme Court, General Term, Second Department.
May 8, 1893.)

Headnote

Building Contracts—Claims for Extra Work.
Where a person employed to construct sheds for a certain price is put to extra labor in laying the foundations through failure of the owner to properly grade the location, as he was required to do by the agreement, he may recover for such extra labor.
p. 381
Appeal from circuit court, Richmond county.
Action by Allen P. Becker against the National Prohibition Park Company to recover for work done under a contract, and also for extra work. Judgment was entered in favor of plaintiff, and defendant appeals.
Affirmed.
Argued'before BARNARD, P. J., and DYKMAN and PRATT, JJ.
Nichols & Bacon, (Alexander S. Bacon, of counsel,) for appellant.
W. J/ Powers, for respondent.

The defendant employed the plaintiff to furnish the materials except stone, and to do the work, for the erection of some 400 feet of sheds in Richmond county. It was admitted that the last installment, $565, was unpaid. The plaintiff seeks to recover this sum and $22.50 in addition for extra work. The answer avers that the materials were not good, and also that the work was not skillfully done, to the defendant’s damage of $250. The answer also avers a tender of the last installment of $565, which the plaintiff refuses to take. Upon the trial the principal issue was as to the extra work. The agreement bound the plaintiff to lay up the stone piers under the shed, and the defendant was to furnish the stone. The defendant was to do the grading. The plaintiff gave evidence tending to show that the defendant did not make an even grade or a good grade; that the piers were of irregular height, and made higher in some cases by reason of a greater excavation than was needed at particular points, and that the plaintiff was compelled to do the rest of the work to carry up these piers higher than the contract and specifications called for; that the defendant’s superintendent told the plaintiff to do the work, and that he must use small stones of the defendant, instead of one stone, as was designed, and not of uniform height. The defendant gave evidence tending to contradict plaintiff’s theory, and the case went to the jury under a charge from the court that if the $22.50 was made necessary by the improper grading of defendant, plaintiff was entitled to recover therefor. It was a pure question of fact, and the-finding of the jury should settle it. The fact being settled, the principle of law is sufficient to support the plaintiff’s claim. The defendant violated an independent contract, upon which the plaintiff’s contract rested. It was plaintiff’s duty to mitigate the damages, therefore, as much as he could, and to that end he furnished the work- to availability. He was thus entitled to recover for his extra expenditure. Kidd v. McCormick, 83 N. Y. 391 .

Judgment affirmed, with costs. All concur.