Majority
Headnote
1. Building Contract — Time to Complete Building — Interference byThis action was brought to recover a balance due upon a building contract. The defendants, by their answer, denied that anything was due, and set up, by way of de
In the consideration of this appeal, it will not be necessary to examine in detail the voluminous evidence which was offered before the referee upon the trial of this case. It is claimed upon the part of the appellants that the referee erred in finding that the defendants interfered with the plaintiff, and prevented the completion of his contract, by refusing to permit the plaintiff to transfer certain iron shutters from the easterly wall of the old building to the easterly wall of the new building, and to connect the two buildings by doors, for the reason that the provision of the contract was that this work was to be done at the convenience of the owners. But this convenience of the owners, if they are to hold the contract- or to the time limit of the contract, must refer to some suitable time within the term of the contract. They cannot wait until after the time for the completion of the work has expired, as they did in the case at bar, and then claim that the contractor is not excused from his default in completing his work in time. In the case at bar, the contractor wanted to remove the shutters within the time limited by the contract, and he was requested to leave them there until a considerable time after the contract should have been completed. This delay, clearly, was through no fault of his; and, when it was agreed to, it extended the time for the performance of the contract.
It is further urged that the referee erred in finding that the defendants prevented the plaintiff from completing his contract on September 20th, by demanding and receiving, for the convenience of other contractors, the exclusive use of the elevator shafts. But, if the referee did err in this respect, it does not in any manner affect the other two points upon which the referee based his decision. By the uncontradicted acts of the defendants,—by their requests, established beyond peradventure,—the plaintiff refrained from .doing those things which were necessary to complete his contract within the time limit. This being the case, how is it possible to hold him for a fixed sum, as liquidated damages for noncompliance? But it may be said, and was urged upon the argument, that although this may be the condition of affairs, yet still these requests and acts of the defendants were not responsible for the whole of the delay, and that, therefore, there should be some apportionment of the delay. But in their contract these defendants were careful explicitly, and with precision, to define the rights of the parties. They provided that the $250 a day was not to be a penalty, but liquidated damages. There was to be no question about it. If the plaintiff delayed he was to pay $250 a day as long as the delay continued. , This was to be liquidated damages, and not a penalty. The plaintiff being under this strict obligation, how can he be held to it when, by the very request of the defendants, he refrained from so completing his contract as to bring himself within the limit fixed by such contract? If the specified day has passed, and has passed because of the acts of the defendants, who is to determine for how much of the delay the plaintiff must pay $250 a day,—this precise, fixed, liquidated damage? It is manifest that, when the plaintiff allowed the contract day to go by, at the request of the defendants, he can only be made responsible for neglect, and cannot be held under the contract. The plaintiff being absolved from the obligation of completing the building on the 20th of September by the express action of the defendants, such obligation could not be renewed, except by express contract. The plaintiff could not know when he would be held to be in default, under such circumstances; and where, by the terms of the contract, liquidated, damages are to be .sustained after a given day, the plaintiff is entitled to know with precision when he is laboring under