Majority
Headnote
Contracts—Waiver of Conditions.The plaintiff did not set out the contract in his complaint, but proved it on the trial, and sought to recover pursuant to the terms thereof. He was not bound, as a matter of pleading, to declare upon the contract, but might declare generally for the materials furnished and work performed, and on the trial the contract might be used to determine the rights of the parties. Hogan v. Laimbeer, 66 N. Y. 604 . It is not necessary to consider the question whether the $1,000 note was to be regarded as a payment on the contract or not, as the court held that the plaintiff had no right to recover or establish his lien for anything. There may well be a question whether, in fact, the note was delivered as- payment, or simply as additional security. That question can be considered and determined upon another trial, which we are inclined to order.
The only question to be determined now is whether the court was justified in dismissing the complaint, upon the ground that the architects’ certificate had not actually come into the plaintiff’s custody before the action was commenced. Before the action was commenced, the contract had concededly been complied with fully, so far-as the furnishing of the materials and the performing of the work were concerned. By the decision of the trial court, the plaintiff was defeated wholly in his action, because the architects’ certificate had. not been delivered to the plaintiff before he commenced his action. The contract did not provide, as the decision and the learned justice’s, opinion seem to imply, that the certificate should be furnished or produced to O’Neil before the payments became due. It merely provided that the work should be done to the satisfaction of the archi
The judgment appealed from should be reversed, and a new trial ordered, with costs of the appeal to the appellant to abide event. All concur.
Cases cited
- Higgins v. Newtown & Flushing Railroad 66 N. Y. 604 p. 213