Majority
Headnote
1. Mechanic’s Lien—Bond to Discharge Lien—Procedure.This is a common-law action upon a bond for §13,-000 given to discharge a mechanic’s lien upon real property in this city. The obligation was executed by the Wallis Iron Works, as principal, and two sureties, and the obligee is the clerk of the county of New York. The condition is “that if the said Wallis Iron Works, or its legal representatives, shall pay any judgment that may be rendered against said property in any proceeding to enforce the foregoing lien, then this obligation to be void; otherwise to remain in full force.” By a judgment rendered October 3, 1894, in an action against the principal on the bond, it was adjudged that the plaintiffs recover of the Wallis Iron Works the sum of §12,945.57, and that the plaintiffs had acquired a valid lien upon and against the premises. It is then declared that the judgment, as against the said premises, is in form only, and has been directed, and is so entered, for the purpose of enabling the plaintiffs to recover upon the bond. The judgment having been affirmed upon appeal, it must, at this branch of the court, be assumed that it was authorized, and that it properly adjudicated upon the subject-matter involved, notwithstanding the new mode of procedure established by the court of appeals. The bond was given, and judgment rendered, under the practice formerly prevailing, so that the only contingency within the contemplation of all the parties at the time of the contract, upon which the sureties were to be charged, has arisen. Story, Cont. § 6§6. The sureties now attack the form of the action, claiming- it should have been brought under the new mode of procedure, and the adjudications in the prior litigation ignored. In other words, the defendants now insist that the suit should have been brought in equity, as upon foreclosure, and all persons in interest should have' been made parties, as in foreclosure proceedings. Morton v. Tucker, 145 N. Y. 244 , 40 N.
With these technical objections overruled, the plaintiffs are entitled to judgment for $14,123, with costs.
Cases cited
- Morton v. Tucker 145 N. Y. 244 p. 93
- Goodwin v. Bunzl 102 N. Y. 224 p. 94
- Miller v. Youmans 13 Misc. Rep. 59 at 63, 34 p. 94
- Methodist Churches v. Barker 18 N. Y. 463 p. 94
- Jordan v. Volkenning 72 N. Y. 300 p. 94
- Mayor of New York v. Crawford 111 N. Y. 638 p. 94
- Heinlein v. Murphy 3 Misc. Rep. 47 p. 94
- Lyon v. Clark 8 N. Y. 148 p. 94
- Brainard v. Jones 18 N. Y. 35 p. 94