Majority
Headnote
1. Contracts—Destruction of Subject before Completion.When a builder agrees to erect and complete an entire house, if the house is destroyed by fire before completion, the builder can erect another; and, if he does not do so, he is guilty of a breach of his contract. Tompkins v. Dudley, 25 N. Y. 272 . But if a painter agrees to paint a certain house, and the house is destroyed before the painting is finished, it is impossible for him to complete his contract. If a new house should be erected, it would not be the house he had agreed to paint. Why should not the painter be paid for his part performance? It was no fault of his that full performance was impossible. Whelan v. Clock Co., 97 N. Y. 293 . But why shonld the owner pay? Because every stroke of the painter’s brush converted something of the painter’s labor and material into the property of the owner, and thus the fire destroyed the owner’s property, and not the painter’s. If the painter had been painting a boat which he had agreed to make and deliver to the vendee, and fire had destroyed it before delivery, the whole loss would have been his, and not the vendee’s, since title would not pass until delivery. An
In the case before us, the defendant owned the building, and the plaintiff was under a contract wdth him to do certain specified carpenter and joiner work therein, and to furnish the materials therefor, for a price fixed for the whole, to be paid, however, in installments as the work advanced. The plaintiff had performed a large part of the work as agreed, and had been paid several installments when the building was destroyed by fire without fault by either party. If the views above expressed are correct, then the plaintiff is excused from further performance, because it became impossible without fault of his own, and he is entitled to recover for all the labor and material which he added to the house, because his further performance is impossible, and therefore cannot be interposed as an obstacle to his recovery, and also because what he thus added became the defendant’s property, and thus the fire destroyed the defendant’s, and not the plaintiff’s, property.
The learned referee placed his decision in favor of the plaintiff upon Niblo v. Binsse, 40 N. Y. 476 , a case in its particulars almost identical with the one before us. The learned referee reluctantly yielded to the authority of that case, because of the similarity of its facts to this case, at the same time confessing that he could not harmonize it with the numerous cases which hold that, when performance of a contract depends upon the continued existence of its subject-matter or of some other essential, the law implies that the contract is based upon such continued existence; and, such existence ceasing, the obligation of the contract ceases, leaving each party without recourse to the other, on account of any breach of the contract. Dexter v. Norton, supra; Goldman v. Rosenberg, 116 N. Y. 78 , 22 N. E. 259 ; Lorillard v. Clyde, 142 N. Y. 456 , 37 N. E. 489 ; Stewart v. Stone, 127 N. Y. 500 , 28 N. E. 595 ; Taylor v. Caldwell, 3 Best. & S. 826, 113 E. C. L. 824. These cases simply denied the right of recovery of damages for breach of the contract. In Dexter v. Norton the plaintiff sought to recover the damages he sustained because the defendant did not deliver Mm
It follows that the judgment should be affirmed, unless the record shows some error ito the prejudice of the defendant. The measure of damages stated by the learned referee in his opinion is the. value of the labor and materials furnished and his proportionate profits to the time of the fire. He applied this rule by allowing the contractor the contract rates for his labor and material. This, yve think, was right. He, however, allowed the plaintiff |309.10 for materials which he had procured in order to place them in or upon the building, but which he had not actually placed at the time of the fire. These items we cannot allow, since they had not been added to the building, and therefore were not defendant’s property. Although the action is not upon the contract, the contract affords the best evidence between the parties as to the value of the labor and materials furnished. There are authorities to the effect that where the contractor is to be paid in installments, upon the completion of certain parts of the work, each installment becomes a debt as the particular portion specified is completed; and, as to the incompleted portion at the time of the fire, no recovery can be had, because the installment is not due. Richardson v. Shaw, 1 Mo. App. 234 ; Clark v. Collier, 100 Cal. 256 , 34 Pac. 677 ; Add. Cont. (9th Ed.) 809. If the action were upon the contract, this would be so; but, as it is not, the rule should not apply: The contract no longer binds the parties, or, if it does, its breach is excused, and therefore the breach is not available to defeat recovery for what has been done under it. Such, we think, is the sensible rule, and the one supported by the authorities in this state (Wolfe v. Howes, Whelan v. Ansonia Clock Co., and Niblo v. Binsse, supra); also, by the cases above cited from Massachusetts, Maryland, and Wisconsin.
The defendant’s exceptions to the admission of the plaintiff’s books containing accounts kept by Mm with the “Gross Hotel,”
We think the judgment should be modified by deducting $309.10 and the interest thereon, and, as so modified, be affirmed, with costs. All concur.
Cases cited
- Tompkins v. Dudley 25 N. Y. 272 p. 1099
- Whelan v. Ansonia Clock Co. 97 N. Y. 293 p. 1099
- Wolfe v. Howes 20 N. Y. 197 p. 1100, p. 1101
- Dexter v. Norton 47 N. Y. 62 p. 1100
- Kein v. Tupper 52 N. Y. 550 p. 1100
- Mason v. Lord 40 N. Y. 476 p. 1100
- Goldman v. Rosenberg 116 N. Y. 78 p. 1100
- Lorillard v. Clyde 142 N. Y. 456 p. 1100
- Stewart v. Stone 127 N. Y. 500 p. 1100
- Clark v. Collier 100 Cal. 256 p. 1102