Majority
Headnote
1. Municipal Corporations—Contracts—Abandonment by Contractor.In November, 1888, Sullivan & Co., a firm of which the defendant Sullivan is the survivor, entered into a contract with the plaintiff for the construction of a sewer in the city of Amsterdam. The work was commenced by Sullivan & Co., and continued by them until April 5, 1889, when the plaintiff took possession and completed the work at a loss to the city, as the plaintiff claims, of about $1,300 over and above the contract price. This loss the
1. The .plaintiff took possession on the morning of April 5th. Up to this time there had been no failure on the part of the contractors to perform their contract. The work was going on as directed by the plaintiff’s engineer. The men of the contractors were at work on the 4th April, and they were on hand, ready to start, at 7 o’clock on the morning of the 5th, when the engineer of the plaintiff, by its direction, assumed control, and excluded the contractors from any further control or possession. There is evidence tending to show that the contractors had not become bankrupt or insolvent. The plaintiff,. however, seeks to justify its action by reason of what occurred the evening before between Sullivan and the commissioners. Sullivan was in charge of the work, his partner and the sureties living at Syracuse. The engineer had, a day or two before, made his estimate of the work done in March at about the sum of $300. Sullivan was dissatis
The plaintiff invokes the doctrine of equitable estoppel. Shapley v. Abbott, 42 N. Y. 447 . The claim is that when Sullivan said he would quit if the board would not allow his claim for extra work, the board, if it concluded not to allow the claim, could, without giving Sullivan any notice of its action on his claim, go on and take possession, although Sullivan at the time was in fact going on with the work, and had not abandoned it. There was some evidence that the board knew of his intention to go on until he could hear from his partner'-and bondsmen. The engineer, as he took possession, and before -he -did anything or the -board did anything to change its position, knew that there was in -fact no abandonment. The knowledge of the engineer as to the situation in fact when he took possession should be attributed to the board. It
2. The $60 was allowed for balance of extra work performed in February. The contractors presented to the ‘engineer a bill for extra work that month to the amount of $202. Of this the engineer allowed the sum of $142, and included it in the estimate for that month. Sullivan testifies that the engineer told him that he would allow the balance when a quantity of frozen earth was removed from the bank of the canal. It is not shown that this was ever done by the contractors, although there was plenty of time for the doing of it before they left. Besides, the item is allowed by the referee as for extra work done under the contract. By the contract the estimate of the engineer is final and conclusive, and a case is not made for going back of the estimates, within the rule laid down in Sweet v. Morrison, 116 N. Y. 39 , 34, 22 N. E. 276 . Corruption, bad faith, or misconduct on the part of the engineer, or palpable mistake appearing on the face of the estimate, is not shown. The item of $60 was, I think, improperly allowed.
3. The plaintiff claims that the finding of the referee as to the tools, implements, and machines is contrary to the evidence. We think not. The evidence was sufficient to justify the finding, and should not be disturbed.
4. The rulings as to the evidence in regard to the solvency of the contractors do not present any good ground for reversal of the judgment. It follows that, except as to the $60 above referred to, the judgment should be affirmed.
Judgment modified by deducting therefrom the sum of $60, and interest thereon from January 1, 1890, and, as modified, affirmed* with costs. All concur.