Majority
Headnote
1. Contracts—Delay in Performance—Liquidated Damages.The first objection urged by the defendant to the judgment recovered by the plaintiff is that the defendant should have been allowed $6,900, forfeited by the defendant under this provision of his contract with the city that his work “should be fully completed by or before May 1, 1888,” and that he would “forfeit and pay to the city the sum of $50 for each and every day after that date, May 1, 1888, that said work should remain uncompleted,” which sum was declared by the contract to be the damages which will result to the city from such delay, and are hereby liquidated at such sum, the same to be deducted from the amount otherwise due the plaintiff thereon. The referee found that the contract was substantially completed by May 1, 1888;
The defendant insists that by the terms of the contract the plaintiff should have been charged with $821.34, the amount paid by the defendant to one Murray for repairs upon the sewer within one year from its completion. We assume that under the contract this" item would be chargeable to the plaintiff if the defects occasioning these repairs were chargeable to his defective work, but would not be if chargeable, as claimed by the plaintiff, to the work of another contractor in subsequently making an intersection of a smaller sewer with this one. The issue was one of fact, and, upon the evidence, apparently of considerable difficulty. It might have been decided either way. We do not feel authorized to "disturb the finding of the referee upon it.
“When the contractor had performed his work according to his contract, he had no duty remaining to discharge, and then had a right to rely upon the implied obligation of the city to use with due diligence its own agencies to procure the means to satisfy his claims. It could not be supposed that he was not only to earn his compensation, but also to set in motion and to keep in operation the several agencies of the city government over whom he had no control, to place in the hands of the city the funds necessary to enable it to' pay its obligations. That was a power lodged in the hands of the city, and the clear intent of the contract was that it should exercise it diligently, for the purpose of raising the funds necessary to pay for the improvements. For an omission to do so it would become liable to pay such damages as the contractor might suffer by reason of its neglect of duty,”—citing Cumming v. Mayor, etc., 11 Paige, 596; Sage v. City of Brooklyn, 89 N. Y. 189 ; McCormack v. City of Brooklyn, 108 N. Y. 49 , 14 N. E. 808 .
Other cases recognize the like rule. Donnelly v. City of Brooklyn, 121 N. Y. 9 , 24 N. E. 17 ; Genet v. City of Brooklyn, 99 N. Y. 296 , 1 N. E. 777 ; Id., 94 N. Y. 645 ; Baldwin v. City of Oswego, 1 Abb. Dec. 62. People v. City of Syracuse, 144 N. Y. 63 , 38 N. E. 1006 , is cited by defendant as a later, and therefore a better, statement of the law. There the contract provided that no payment should be made “until the cost of the work shall have been assessed upon and collected from the taxpayers liable.” The proper assessment was made, but only about one-quarter of it collected. The effort to make further collections was suspended. The court held that the contractor was entitled to mandamus to compel the officers of the city having the matter in charge to proceed with their duties as required by. law. The court also remarked that no action was maintainable by the contractor against the city; citing Hunt v. City of Utica, 18 N. Y. 442 ; Lake v. Village of Williamsburgh, 4 Denio, 520 . In the Utica Case, as in the Syracuse Case, the warrant for the collection of the proper amounts was, when the action was commenced, outstanding in the hands of the collect-
The defendant further objects to the allowance of a small item ealléd “extra work.” This item was made necessary because the assistant engineer of the defendant mistakenly gave an insufficient depth for the excavation of the sewer trench, and the mistake, after the contractor had performed some work upon the wrong bottom, had to be corrected. Clearly, the contractor should not bear the burden of this extra expense. The mistake or oversight was the defendant’s, and the extra work had, ex necessitate, to be performed, which is a different thing from voluntarily departing from the charter. Mulholland v. Mayor, etc., 113 N. Y. 631 , 20 N. E. 856 . There are no other objections which require special notice.
The judgment should be affirmed, with costs.
PARKER, P. J., concurs. MERWXN and PUTNAM, JJ., concur in result.
Cases cited
- Little v. Banks 85 N. Y. 258 p. 95
- Colwell v. Lawrence 38 N. Y. 71 p. 95
- Kemp v. Knickerbocker Ice Co. 69 N. Y. 45 p. 95
- Noyes v. Phillips 60 N. Y. 408 p. 95
- Reilly v. City of Albany 112 N. Y. 30 p. 96
- Sage v. City of Brooklyn 89 N. Y. 189 p. 96
- McCormack v. City of Brooklyn 108 N. Y. 49 p. 96
- Donnelly v. City of Brooklyn 121 N. Y. 9 at 24 p. 96
- Genet v. City of Brooklyn 99 N. Y. 296 p. 96
- Genet v. City of Brooklyn 94 N. Y. 645 p. 96
- People ex rel. Ready v. Mayor of Syracuse 144 N. Y. 63 p. 96
- Hunt v. City of Utica 18 N. Y. 442 p. 96
- Mulholland v. Mayor of New York 113 N. Y. 631 p. 97