Majority
Headnote
1. Contract—Provision for Termination—Notice.The first cause of action set forth in the complaint is founded upon an alleged breach by the defendant of a contract between the parties whereby it was agreed that the plaintiff should have the privilege of assorting the refuse dumped from the carts of the street-cleaning department at the dumping boards of the city, for the period of one year from June 12, 1892, for which the plaintiff undertook to furnish all the laborers necessary to trim the scows and boats of that department, and pay to the city $1,785 weekly in advance. The plaintiff entered upon the performance of the contract. The alleged breach is that on or about the 1st day of November, 1892, the defendant refused to allow the plaintiff to proceed further in its performance. The contract contains a provision to the effect that if, at any time before the expiration of such period, the commissioner of street cleaning shall deem it for the interest of the city so to do, for any other reason than the failure of the plaintiff to comply with the terms of the agreement, he shall have the power to terminate it upon giving at least 10 days’ notice in writing to him of such intention, and that, on the date and time specified in the notice, the plaintiff would discontinue the work, and the agreement absolutely terminate. In September, 1892, the health department, in apprehension of cholera, as a precautionary measure, required that assorting the refuse should be, and it was, suspended. In this the plaintiff acquiesced, and, pursuant to an arrangement with the defendant, he, by laborers furnished by him. did the work of trimming the scows at the dumping boards, without any assorting, at a stipulated price for the service, until about the 1st day of November, when he received from the commissioner of street cleaning a notice in writing that the contract for trimming scows had been awarded to a person named, and that the services of the plaintiff’s men in such work "would not be required after that date. This notice was not in the form of that contemplated by the
Tire plaintiff obtained by the judgment all the relief he sought by the second cause of action alleged in the complaint. There was no support in the evidence for any recovery upon the third cause of action, and as to that the complaint was properly dismissed. The dumping board at the foot of Forty-Sixth street, East river, was in no condition for use when the contract was made. It is said that it had been destroyed by fire. There was no provision in the contract for its reconstruction or repair. Nor was there any ambiguity in the terms of the contract, or anything which required evidence to explain or to complete or perfect any of its provisions. The import of the contract was that the plaintiff should have the privilege of assorting all the refuse which was dumped from the carts of the defendant, and as it was so dumped. It is not seen that any collateral promise made bv the commissioner of street cleaning to have that dumping board repaired for use could give any support to the plaintiff’s claim to a rebate because it was not fitted up and put into use. He had the full benefit of his contract while in its performance.
In the view taken of the case, there was no error in any ruling at-the trial other than the exclusion of evidence relating to the first cause of action alleged in the complaint, and for that the judgment appealed from should be reversed, and a new trial granted; costs to abide the event. All concur. •
Cases cited
- Crawford v. Millspaugh 13 Johns. 87 p. 145
- Buel v. Trustees of Lockport 3 N. Y. 197 p. 145
- Phyfe v. Eimer 45 N. Y. 102 p. 145
- Reynolds v. Robinson 110 N. Y. 654 p. 145
- Blewitt v. Boorum 142 N. Y. 357 p. 145