Majority
Headnote
-Building Contract— Construction—Eights oe Contractor.The contract here, like the one in Phelan v. Mayor, etc., 119 N. Y. 86 , 23 N. E. 175 , provides that the time during which the work of completion may be delayed by acts of the city shall be determined by the commissioner of public works. Such provision proved fatal to the plaintiff in that case, but is not controlling here, for the contract sued on contains other provisions more germane to this controversy, to wit:
(1) “In case said building shall not be completed within five hundred working days, as aforesaid, the architect in charge of said building shall certify, in writing, what portion of said excess of time, if any, is chargeable,to the party of the second part [the plaintiff]; and such certificate, when approved by the commissioner of public works, shall be final and conclusive in respect to the responsibility for any such delay." (2) “Whenever, in the opinion of the said architect; the party of the second part shall have completely performed the contract on 1ns part, the said architect shall certify the same, in writing, to the commissioner of public works; whereupon the parties of- the first part will, on the expiration of thirty days after such completion and the delivery of said certificate, pay, and they hereby bind themselves and their successors to pay, to the said party of the second part, in cash, the' whole amount of money accruing to the said party of the second part under this contract.”
The contract discriminates between delays caused by acts of the city and other delays, for the commissioner of public works is to determine the extent of the first, while the decision respecting other delays is to be made by the architect, and is to be conclusive. To give any other construction to the contract would be to enforce one provision beyond its proper scope, and to withhold from the others any practical meaning or force. The commissioner undertook to go beyond his authority by holding that the plaintiff was guilty of 49 days’ delay, for which he withheld from the contract price of $161,000 the sum of $4,900 (being at the stipulated rate of $100 per day), without any certificate from the architect, and contrary to the terms of the contract. Indeed, the architect certified that the plaintiff had in all things performed his contract, and had become entitled to the final payment, and this certificate is conclusive on the subject. Zimmerman v. Lutheran Church, 11 Misc. Rep. 49 , 31 N. Y. Supp. 845 ; Iron Works v. Rouss (Super. N. Y.) 15 N. Y. Supp. 137 , affirmed 133 N. Y. 538 , 30 N. E. 1148 ; Snaith v. Smith, 7 Misc. Rep. 37 , 27 N. Y. Supp. 379 ; Byron v. Low, 109 N. Y. 291 , 16 N. E. 45 ; Wyckoff v. Meyers, 44 N. Y. 143 ; and kindred cases.
The defendant claims that the commissioner was all-powerful under the contract, and that his determination concludes the plaintiff, without regard to what the architect certified. Such a construction would treat the architect as a nonentity, and render inoperative those carefully drawn provisions which prescribe his authority; and it is wholly unwarranted. The architect’s presence while the work was going on enabled him to determine from daily observation the causes and extent of the different delays upon the large building in course of construction, and to accurately decide upon whom the responsibility rested therefor. This is what the contract intended he should do, and is the reason why his decision thereon was agreed to be accepted as final, and effect must be given to the intention of the parties. The delays occasioned to the plaintiff were not attributed to acts of city officials or servants, respecting which the
Motion denied.
Cases cited
- Phelan v. Mayor of New York 119 N. Y. 86 p. 874
- Jackson Architectural Iron Works v. Rouss 133 N. Y. 538 p. 874
- Snaith v. Smith 7 Misc. Rep. 37 p. 874
- Byron v. Low 109 N. Y. 291 p. 874
- Wyckoff v. Meyers 44 N. Y. 143 p. 874
- Clark v. Devoe 124 N. Y. 120 p. 876
- Heryford v. Davis 102 U. S. 235 at 243, 244 p. 876