Majority
Headnote
1. Pleading—Complaint—Inconsistent Allegations.It is necessary to consider only the first and second causes of action set out in the complaint, as no proof was offered upon the trial to sustain the third cause of action. The plaintiff, under contracts with the city of New York, built a sewer in 96th street and another in 105th street. He claims that the city still owes him $380 on the first contract and $340 on the second. The city, on the other hand, insists that these amounts have been rightfully withheld, under a provision in each contract which authorized the defendants to deduct $20 a day as liquidated damages for the noncompletion of the work within a specified number of days. In the contract for the 96th street sewer this provision reads as follows:
“(B) The said party of the second part [the plaintiff] hereby further agrees that he will commence the aforesaid work on such day and at such place or places as the said commissioner [of public works] may designate, and progress therewith so as to complete the same in accordance with this agreement on or before the expiration of one hundred days thereafter, * * * and that in the computation of said time, expressed in days and parts of a day, during which the work, or any part or section thereof, has been delayed in consequence of the condition of the weather, or tides, or by any act or omission of the parties of the first part, all of which shall be determined by the said commissioner of public works, who shall certify to the same in writing, and also Sundays and holidays, on which no work is done, and days on which the prosecution of the whole work is suspended by order in writing by the said commissioner, shall be excluded. * * * And the said party of the second part further agrees that the said parties of the first part [meaning the defendants] shall be, and they are hereby, authorized to deduct and retain, out of the moneys which may be due or become due to the said party of the second part under this agreement, as damages for the noncompletion of the work aforesaid within the time hereinbefore stipulated for its completion, the sum of twenty dollars for each and every day the aggregate time of all the inspectors employed upon said work may exceed the said stipulated time for its completion.”
The only difference in clause E in the contract for the 105th street sewer was that it fixed 110 instead of 100 days as the period within which the work should be completed.
The plaintiff in the complaint alleged the full performance of
As to the latter objection, I think the allegation was proper, inasmuch as in a suit of this character it seems incumbent upon the plaintiff to show that the delay on account of which the money is withheld by the city has really been' caused by the city itself. Phelan v. Mayor, etc., 119 N. Y. 86 , 23 N. E. 175 . Nor can the receipts be deemed to establish an accord and satisfaction without ignoring other evidence in the case which the plaintiff was entitled to have considered. In regard to the contract for the 105th street sewer, there was before the court, not only the receipt dated on November 9, 1893, but also a general release from the plaintiff to the city, bearing the same date and specifically referring to the same work, but expressly excepting from its operation any legal claim which the plaintiff might have on account of the amount retained for “excess of inspection.” Taking this instrument and the contemporaneous receipt together, they seem to me to manifest an intent on the part of the plaintiff to keep out of the adjustment any settlement or admission of the city’s claim to liquidated damages on account of the noncompletion of the work in time. They preclude rather than support the idea of an accord and satisfaction. In respect to the work on the 96th street contract, there is no such release in the record; but the court received testimony from the plaintiff to the effect that, when he signed the receipt for that work, he obtained the consent of the representatives of the city that it should not affect his claim to be repaid the amount withheld on the ground that performance had been unduly delayed. With this evidence in the case, an accord and satisfaction had not been made out as matter of law.
After this proof was in the case, without having been objected to at all, I do not think it should have been stricken out as inadmissible under the pleadings; but, if necessary, the plaintiff should have been allowed to amend. In any event, the fact that such evidence exists and is available to the plaintiff precludes us from holding that he has no legal claim against the defendants enforceable in this action. It follows, therefore, that we should order a new trial. All concur.
Cases cited
- Fuller v. Kemp 138 N. Y. 231 p. 469
- Phelan v. Mayor of New York 119 N. Y. 86 p. 469
- Merrill v. Wakefield Rattan Co. 1 App. Div. 118 p. 470
- Bowery National Bank v. Mayor of New York 63 N. Y. 336 p. 470