Majority
Headnote
Contract—Performance—Waiver.The action was brought for the breach of a contract by the terms of which the plaintiff had been engaged to address a quantity of envelopes, it being alleged that the defendant refused to accept the plaintiff’s completion of the order after the greater part of the work had been performed, and that, while payment had been made for the actual services thus rendered, at the agreed rate, prospective profits upon the remainder of the order had been lost because of the defendant’s breach. The contract called for the completion of the work by December 5, 1895, and it is undisputed that the plaintiff did not complete by that time; but it is claimed that this default had been waived by the acceptance of the envelopes addressed after-wards, and also that the defendant’s representative had treated the contract as subsisting for two months thereafter. On the other hand, the defendant’s witness Dreyfus, the party with whom the whole transaction was had by the plaintiff, testified that the default in performance upon the 5th of December was not waived, since he had told the plaintiff’s agent, Chapman, that no more of the work would be accepted after that date, the envelopes being required for advertising-purposes before the Christmas holidays, and the observance of the date stated for performance being essential. He stated to Chapman, however, that he would receive the envelopes which were already addressed and on hand, but no more, and these envelopes were' accepted a few days afterwards. Further, he expressly denied that any conversations, such as testified to by Chapman touching a later recognition of the contract, had taken place. This testimony was credited by the justice, and amply supported the judgment rendered in favor of the defendant, since it was made to appear that time was of
Judgment affirmed, with costs. All concur.