Majority
Headnote
1. Building Contracts—Breach—Quantum Meruit.The action is founded on an alleged breach of the contract by the defendant. The plaintiffs, by their complaint, charge: (1) That they, having nearly completed the work under the first or causeway contract, were, on or about June 29, 1895, prevented by the defendant from proceeding further in the fulfillment of it, and that the defendant had failed to make payments to which the plaintiffs were entitled. (2) That the plaintiffs had also nearly completed the work under the other or bridge contract when they, at the same time, were wrongfully prevented from proceeding fur
The alleged breach of the contracts on the part of the defendant mainly arises out of the fact that during the progress of the work, and on June 29, 1895, the defendant, by its president, addressed and sent to the plaintiffs a telegram, of which the following is a copy: “Your men quit work Thursday. Have instructed Smith to finish road under your contract.” The name subscribed to the telegram was “Geo. 0. Band,” who was such officer. Thomas D. Smith was the engineer who had been selected by the defendant. This was Saturday, and thereafter the plaintiffs did no more work upon the causeway job; but the defendant, on the 2d day of July, took charge of it, and proceeded with its completion. For that purpose, the men and tools theretofore in the service of the plaintiffs were employed by the defendant. This taking the possession of the work to finish it, the defendant alleges, was pursuant to the provision of the contract to the effect that, in case the plaintiffs failed to supply a sufficiency of materials or workmen, the defendant should have the power, on three days’ notice, to provide them, complete the work, and deduct the expense from the amount of the contract. The defendant also alleges that the expense of its accomplishment exceeded the amount of the contract price remaining unpaid to the plaintiffs. Whether or not the defendant' was, by any default of the plaintiffs,, justified in taking the work from them, under that provision of the contract, was a controverted question of fact, upon which it must be assumed that the jury found against the defendant; and, although they would have been fairly warranted in finding otherwise, we think the conclusion of the jury in that respect was permitted by the. evidence. It is true, the time specified in the contract for the completion of the.work had expired before the defendant took the control of it; and, if nothing chargeable to the defendant had intervened to permit the extension of the time of its performance by the plaintiffs, a different question would have been presented for consideration, since, in view of the purpose and contemplated use of the causeway, time may be deemed as of the essence of the contract. But after the making of the causeway contract, and early in August, 1894, the plaintiffs, in the expectation of proceeding at once with the work, were prepared with shanties, men, and implements on the ground to do so, but were denied the right to commence, by notice from the defendant that legal obstacles then prevented the beginning of the work, which, it seems, were occasioned by a failure of the defendant to obtain the right of way through the meadow in the town of Hempstead. This was not accomplished, so as to enable the plaintiffs to commence the work, before September 3d, when they entered upon its performance. The consequences of this interruption and delay were the expenses of the transportation of the unemployed workmen, and their wages, and the loss of a portion of the better season for the work, which it was more difficult to perform in the late autumn and winter in that place. It seems that in time of high
The jury were permitted by evidence to conclude that the defendant was not justified by lapse of time in taking the work from the plaintiffs. Following the conclusion of the jury that this was done by the defendant in violation of the contract, there arose, upon the evidence, questions of fact relating to the extent of the work which the plaintiffs had performed under the contract, including such as was denominated “extra work.” The trial proceeded, and the case was submitted to the jury, upon the theory that the plaintiffs were entitled to recover the amount of money expended by them upon the work, less the amount paid to them by the defendant thereon. Of course, the amount chargeable and expended under the contracts could not exceed the compensatory sums provided for by them; nor is it claimed that the expense incurred in the performance of the work specified in the contracts exceeded such sums; but, including the expenditures for extra work on the causeway, the evidence on the part of the plaintiffs tended to prove that they amounted to $15,-519.16, of which the sum of $4,660 was expended for what the plaintiffs’ evidence tended to prove was extra work. The plaintiffs received from the defendant, on account of their work on the causeway, $8,241.16. They also claim, and evidence on their part was given tending to prove, that the drawbridge was substantially completed by them prior to July 2, 1895, and that they had expended $1,300 in its construction; and, having received on account of that work $700, they claimed the right to the allowance of the further sum of $500, the residue of the contract price for the construction of the bridge, and the further sum of $72.40, for extra work. In addition to this, the plaintiffs claim by their evidence that the expenses incurred by them in consequence of the delay to which they were subjected, as before mentioned, in the outset, were $650, of which amount they were paid $340 by the defendant on that account. The matter of extra work which the nlaintiffs claimed to have performed was the subject of controversy by the evidence; and the evidence on the part of the defendant was to' the effect that the value of work done and materials furnished by the plaintiffs upon the causeway was only $9,448, and on the drawbridge $960, and that the defendant expended in completion of the causeway upward of $5,000 after taking possession of the work, and that the work to be done to complete the bridge and remedy the defects would cost $1,020. Of the sum so expended by the defendant upon the causeway, $3,600 were paid to Murray & Be Mott, who, in May, 1895, by contract made with the plaintiffs, agreed to put three inches of loam and three inches of gravel upon the roadway, for the sum of $3,600. This contract was
The court charged the jury that if they found from the evidence that the “plaintiffs were not in fault, but that they prosecuted the work with reasonable diligence, and that the defendant unwarrantably, and without cause, as contemplated by the contract, took possession of the work, and excluded the plaintiffs from it, then the plaintiffs are entitled to recover the amount actually expended by them uoon the work under the contract,” less the amounts which they had received under it. Exception to this charge was taken by the defendant’s counsel, who requested the court to charge that if the jury so found, and that the plaintiffs elected to rescind the contract, then the measure of damages claimed by them in the first cause of action was the actual value of what had been done under the contract, less payments made to them. This was declined by the court; and thereupon the defendant’s counsel excepted, and made the further request to charge that “such actual value is not determined by what the plaintiffs have paid therefor, but by the testimony of those competent to value work of the kind and character in question.” This was also declined, and exception taken. In such case the contractor may seek relief upon the quantum meruit for the work done, and such is a proper remedy. Clark v. Mayor, etc., 4 N. Y. 338 . The purpose of the remedy in such case is to enable him to obtain indemnity, by way of damages, for the loss legitimately suffered by him in consequence of the breach of the contract; and there would seem to be reason for the support of the rule which will permit him to prove as the basis of damages what he has fairly and reasonably expended in the performance of or under the contract. U. S. v. Behan, 110 U. S. 338 , 4 Sup. Ct. 81 ; Watts v. Board, 9 App. Div. 143 , 41 N. Y. Supp. 141 . This is a method of proving the value of the services and materials put into the work, and thus the expense of it, which in that sense may be deemed the value for the purposes of the remedy, and reimbursement of the party who has been wrongfully denied the right to complete the performance of his contract. In Kennedy v. McKone, 10 App. Div. 88 , 41 N. Y. Supp. 782 , cited by the defendant’s counsel, claim for the work done by the defendant to complete the performance of the contract was not founded upon any breach of the contract by the plaintiffs, but upon the election by the defendant to perform it for them, and at their expense. It was there simply proved that the defendant paid out a certain amount. And, in the opinion of the court, Mr. Justice Barrett said that the mere fact of payment, standing alone, was not sufficient evidence of value. In the present case, evidence was given on the part of the plaintiffs tending to prove that all the money claimed to have been expended by them actually went into the con
It is urged with some force that the jury would have been warranted in finding that the plaintiffs acquiesced in the taking from them of the control of the work, and proceeding with it by the defendant, in such sense as to relieve the latter from the charge of breach of contract; but, in the view taken of the evidence, that contention is not supported. The plaintiffs were not asked to surrender, nor can it be said that they consented to do so, otherwise than by force of the notice, peremptory in character, that defendant’s engineer had been instructed to finish the road, pursuant to which he did assume the control of the work. Neither resistance nor persistence to the contrary was necessary to nonassent. No view which can legitimately be given to the subsequent interview and communications had between the parties is deemed sufficient to have constituted a ratification by the plaintiffs of the action of the defendant, as taken pur-, suant to the contract.
The learned counsel for the defendant urges upon our attention the question arising upon the refusal of the court to charge that “if the jury find that up to June 29th was ample time to allow plaintiffs to finish the contract, and further find the work was not then completed, and plaintiffs at that time did not supply a sufficiency of materials or men, then, as the time when the work was to be finished was of the essence of the contract, the defendant was justified in doing what it did to complete the contract as soon as possible, to prevent as far as possible loss and damage to all concerned.” If the rights and obligations of the parties were dependent solely upon the written provision of the contract, there would be no answer to such proposition. But, as has been observed, the delay of about 20 days in the commencement of the work was chargeable to the defendant; and the consequence was a right of the plaintiffs to a reasonable extension of time for its completion, which, it appears by evidence, was recognized bv the defendant. The terms of the contract, in that, and no other, respect, were modified. In other words, the per
The question is raised whether or not the defendant was entitled to have allowed to it, against the plaintiffs’ claim, the amount paid by the defendant to Murray & De Mott, for the work done by them .under their contract made with the plaintiffs prior to June 29th. It is contended on the part of the defendant that it was, in any event, entitled to have such amount allowed in reduction of the plaintiffs’ claim, because the subcontract was made by them with the consent of the defendant, and Murray & De Mott were to receive payment directly from it. The contract, therefore, remained effectual, notwithstanding the termination of the connection of the plaintiffs with the work. As the work which Murray & De Mott undertook to perform was a portion of that within the contract between the plaintiffs and defendant, the payment to them was apparently upon the latter contract for work performed pursuant to it. But the defendant had terminated the relation of the plaintiffs to the work with knowledge of the existence and effect of the contract with Murray & De Mott; and assuming, as we do, upon the finding of the jury, that such termination by the defendant of its contract was wrongful, it .is not seen how the amount paid by the defendant to Murray & De Mott upon their contract could be made available as a counterclaim or set-off against the claim of the plaintiffs for work done by them under' the contract. The work done by Murray & De Mott was not, nor
In the view taken of the subject of the cause of action, and of the alleged defenses, counterclaims, and set-offs relating to the causeway or road, as distinguished from the bridge, there was no error to the prejudice of the defendant in the rulings of the court at the trial. The contract for the construction of the drawbridge was made subsequently to that for the causeway, and was distinct from it, and the relief sought, founded upon the alleged breach of the bridge contract, is made the subject of a separate and distinct cause of action in the complaint. It may be observed that the notice of June 29th, to the plaintiffs, was that Smith (engineer) was instructed to “finish the road” under the contract. It is insisted by the plaintiffs’ counsel that in the purpose and effect of this notice was included the bridge, as well as the causeway, because both were essentially united, and constituted parts of the same passageway. As the contracts were distinct from each other, the defendant was permitted to make the notice applicable to one of them only. It seems clear that the causeway was included in the term “road,” used in the telegraphic notice. As manifested by the manner of expression, the reference in it was to a single contract. The appearance, therefore, was consistent with a purpose to terminate the plaintiffs’ further performance of the causeway contract only; and such seems to have been the understanding of the matter. The engineer, Smith, testified that he “never at any time took charge of the bridge to complete the contract. We never touched the bridge. Mr. Simmons’ man, the foreman, was down there, at work at the bridge, after the 2d day of July. He was there for two weeks or more.” By letter to Mr. Rand, of date July 29, 1895, the plaintiff Simmons, in writing for and in the name of hi's firm, said: “I also desire to say that we have repeatedly called for our bridge contract left with your company, and without which we cannot put the bridge in working order, as it re
The claim of the nlaintiffs, founded upon the alleged breach of the "bridge contract, and submitted for consideration upon the evidence, .amounted to $572.40; Whether any or how much of it was allowed by the jury is not seen by the record, nor is it necessary to inquire in what manner they reached the conclusion represented by the verdict for $5,400. In the view thus taken of the case, the $170 .alleged as matter of defense to the plaintiffs’ second cause of ac- 1 tion, and found- to have been paid by the defendant to procure from the war department of the United States permission to construct the bridge over the inlet, requires no consideration, as that alleged cause of action is not supported by the evidence.
The judgment and order should be reversed, and a new trial granted, costs to abide the event, unless the plaintiffs stipulate to deduct -from the recovery of damages $572.40; and in that event the judgment should be so modified, and, as modified, affirmed. All concur.
Cases cited
- Clark v. Mayor of New York 4 N. Y. 338 p. 364
- United States v. Behan 110 U. S. 338 p. 364
- Watts v. Board of Education 9 App. Div. 143 p. 364
- Kennedy v. McKone 10 App. Div. 88 p. 364
- Lawson v. Hogan 93 N. Y. 39 at 44 p. 366
- Thomson v. Poor 147 N. Y. 402 p. 366
- Sinclair v. Tallmadge 35 Barb. 602 p. 366
- Wyckoff v. Taylor 13 App. Div. 240 p. 366
- Wright v. Reusens 133 N. Y. 298 at 307, 31 p. 367