Majority
Headnote
Breach op Contract—Performance by Plaintiff.This action was originally brought against the present defendant and her husband, James Ó. Pawson. After the submission of the case to the referee, James died, and a stipulation was entered by the parties continuing the action against the present defendant alone. The plaintiff is the mother of the present defendant. The complaint alleges that on April 1,1895, the plaintiff loaned
“That the plaintiff herein, on or about May 7, 1895, agreed with the defendants herein to give them the sum of two thousand ($2,000) dollars for the purpose of building a house, if they would furnish her board and two rooms therein during her natural life; that the defendants built said house and furnished the rooms as agreed, and at the time of the completion of said house were ready and willing to allow the plaintiff the use of said rooms, and to furnish her board in accordance with said agreement; that the plaintiff gave to the defendants the sum of seventeen hundred ($1,700) dollars on account of .the said two thousand ($2,000) dollars as agreed, but, although the defendants were ready and willing to perform the agreement on their part, the plaintiff refused to carry out the agreement on her part by not giving to the defendants the remaining sum of three hundred ($300) dollars in accordance with said agreement, thereby failing to keep her part of said agreement.”
He also found, as conclusion of law, that the plaintiff is not entitled to recover the sum of $1,700, or any part thereof, and that the defendants are entitled to judgment dismissing the complaint. Prom the judgment entered upon this report, the defendant appeals.
The only question which requires consideration is whether there was sufficient evidence upon which to base the referee’s findings of fact. Without analyzing the testimony, it is sufficient to say that the plaintiff’s contention is supported by her evidence alone, and that the defendant’s contention is supported by her own testimony and that of her husband, as well as that of the architect of the house.
The judgment should be modified so as to direct the dismissal of the complaint without prejudice to any action the plaintiff may hereafter bring upon the contract after she has advanced the remaining $300, or any action to compel the defendants to execute a bond and mortgage to her for the amount already advanced; and, as modified, the judgment should be affirmed, without costs of this appeal to either party. All concur.