Majority
Headnote
Breach of Contract—Assignment for Creditors.On the 3d day of March, 1893, the Interstate Steamboat Company made a contract with the Cowles Engineering Company by which the Engineering Company agreed to build and deliver to the Interstate Company a steamboat, which was to be finished on or before August 22,' 1893. The boat was to be paid for by installments. The contract provided that if the Engineering Company should not complete the steamer on or before the 22d of August, 1893, it should forfeit to the Interstate Company the sum of $100 a day damages for each day’s delay. It was further agreed that, if the steamer should not be completed within two months after that time, the Interstate Company might accept or reject her upon completion, and, if it did then reject her, the Cowles Company should repay to the Interstate Company all sums which it had received under the agreement. To secure the
It is claimed by the defendants that under the contract the Cowles Engineering Company had until two months after the 22d of August, 1893, to complete the boat, and that as the Interstate Company took possession of her on the 9th of October, before that two months expired, it had put it out of the power of the Engineering Company to finish the boat, and therefore it was precluded from bringing this action against the sureties on the bond. It is claimed, on the contrary, by the plaintiff, that by the terms of the contract the boat was to have been completed on the 22d of August, 1893; that by the transfer of the title to the assignee for the benefit of creditors on the 30th
It is quite clear, we think, that the necessary result of the contract was that the boat was to be completed on the 22d of August, 1893. The agreement was that, if the Cowles Company should not complete the steamer on that day, it should forfeit $100 a day for each day’s delay. That provision of the contract necessarily carried with it an implication that the boat was to have been finished on August 22, 1893. It is quite true that by a subsequent provision of the contract the right to reject the boat for a failure to complete it did not come into existence for 60 days after the 22d of August, and the only penalty for the failure to complete during the 60 days was the forfeiture of ■1100 a day; but the requirement to complete the boat arises as a necessary inference from the imposition of a penalty for the failure to have it completed on the 22d of August, 1893. It may be true that after that time, and until the 22d of October, the Interstate Company would still have been bound to receive the boat, if it had been completed and tendered to it; but that obligation is a mere matter of grace extended to the Cowles Company by the subsequent terms of the contract, and was not strictly an extension of the time in which the boat should have been delivered. However that may be, it is conceded that the Cowles Company did not complete the boat at any time. On the 30th of August it transferred all its property to the assignee for the benefit of creditors. At that time it had the title to this boat, which, although made for the Interstate Company, and to be delivered to it when completed, had not yet become the property of that company; the boat, until it was finally paid for, being still the property of the manufacturer. Andrews v. Durant, 11 N. Y. 35 ; The Poconoket, 67 Fed. 262 ; Id., 17 C. C. A. 309 , 70 Fed. 640 ; Id., 168 U. S. 707 , 18 Sup. Ct.-. "When the title to the boat was trans-
ferred to its assignée for the benefit of creditors, the Cowles Company ceased to have any further interest in it, or right to interfere with it. So far as it was concerned, therefore, there was no power to complete it, because any interference with the boat after its transfer to Mr. Carter would have been a trespass. The case differs from the case of Hew England Iron Co. v. Gilbert El. R. Co., 91 N. Y. 153 . In that case the Hew England Iron Company had agreed to perform certain work for the defendant upon the defendant’s road, but had made an assignment for the benefit of creditors; reserving to itself, however, the right to perform this contract. In an action against the elevated railroad, arising out of the contract, the court held that, so long as the Hew England Iron Company still remained in existence, the mere fact that it had made an assignment for the benefit of creditors did not, as a matter of law, prevent its performance of an executory contract to do work and labor upon the elevated railroad. But that case
It is not very material to consider the powers of the assignee, Carter, in respect of the completion of the boat after he had taken possession of it. There is no claim that he made any effort to complete it, or had any intention of doing so. Indeed, he had no power to do so. His right to the property was controlled by his deed, and he could only take the properly for the purposes mentioned in the deed, and devote it to the use therein prescribed. All he could do was to sell the interest of the Cowles Company in the boat, and he could do nothing further with it. The result is that when the title to the boat had been transferred to Carter on the 36th of August, 1893, it was out of the power of anybody to complete it, and the Interstate Company was at liberty then to regard the contract as at an end. At that time there arose in behalf of the Interstate Company a cause of action against these sureties for the failure to complete the boat.
It was claimed on the trial that the subsequent taking of the boat by
For these reasons the judgment must be reversed, and a new trial ordered, with costs to the appellant to abide the event. All concur.
Cases cited
- Missouri, Kansas & Texas Railway Co. v. Fuller 168 U. S. 707 p. 480
- New England Iron Co. v. Gilbert (Metropolitan) Elevated Railroad 91 N. Y. 153 p. 480
- In re Carter 21 App. Div. 118 p. 481
- Woolner v. Hill 93 N. Y. 576 p. 481