Majority
Headnote
Alteratión op Instruments—Adding Signature—Release op Sureties.When the bond on which plaintiff sought to maintain the action came into the hands of Mr. Doubleday, president of the principal obligor therein, it was a completely executed instrument. Those named therein, and who by its terms were bound by it had affixed their signatures thereto. But Mr. Doubleday evidently signed his name thereto with intent to become an additional surety. Under the original arrangement between the plaintiff- and the Electrical-Supply & Construction Company, he was to become such. It has been held that one executing an instrument signed by others, who-
“No alteration of a writing before execution, which includes delivery, affects its character or value as an instrument of evidence. Alterations before delivery are presumed to be made with mutual consent. The very act of delivering and receiving the writing implies so much. This is the doctrine of the common law. ‘The period after which alterations not mutual are fatal is that of the final delivery of the document.’ * ::: * Weaver and his co-obligors, who signed this bond, and left it with the principal therein to deliver to the plaintiffs, thereby constituted the latter their agent for that purpose. Belloni v. Freeborn, 63 N. Y. 389 . Before the delivery was made, this alteration took place. It consisted of an attestation, which, for aught that appeared, was authorized and genuine. So far as the plaintiffs are concerned, it was the act of Weaver and his co-sureties acting through the agent and co-obligor, Owens, prior to the delivery to them of the writing.”
See, also, Nash v. Fugate, 34 Am. Rep. 780 ; Cutler v. Roberts, 29 Am. Rep. 371 -377.
“Upon the point made by the appellees, that the signature of James Nash was obtained to the bond after their testator had signed it, we are of opinion that it did not avoid the bond, if done before its delivery to the governor. Before its delivery, Ryan could have procured as many names as he chose to his bond.”
When the appellant affixed his signature to the bond in question, as a surety, and sent it to his principal, the paper was not completed. It was to be executed by the corporation and by his brother, and delivered to the plaintiff. We see no reason to doubt that the principal obligor, to whom the appellant had forwarded the unexecuted paper for completion and delivery, had power to obtain an additional surety thereto.
Under the evidence in the case, the court was justified in determining that there was no valid extension of the time of the payment of ■the account of the plaintiff against the Electrical Supply & Construction Company, by which the defendant was discharged from liability.
We find no rulings of the trial judge that should lead us to grant a new trial. The judgment should be affirmed, with costs. All concur.
Cases cited
- Ex parte Fulton 7 Cow. 484 p. 384
- Perkins v. Goodman 21 Barb. 218 p. 384
- Thomas v. Gumaer 7 Wend. 43 p. 384
- McCaughey v. Smith 27 N. Y. 39 p. 384
- Mersman v. Werges 112 U. S. 139 p. 385
- Brownell v. Winnie 29 N. Y. 400 p. 385
- Casoni v. Jerome 58 N. Y. 315 p. 385
- Town of Solon v. Williamsburgh Savings Bank 114 N. Y. 122 p. 385