Majority
Headnote
1. Pleading—Evidence—Action on Contract.Hie action is brought to foreclose a mechanic’s lien. Upon the trial it appeared that the defendant Tallman contracted to do the carpenter work upon the interior of an addition to St. Mary’s Church, Beechwood. The said Tallman, in pursuance of his contract, contracted with the plaintiffs to furnish certain of the carpenter work and trimming. Under and in pursuance of this contract, the plaintiffs furnished doors, frames, paneling, and other material used in the building, in all of the value of about $1,347.47. There does not appear to have been any substantial dispute between the parties as to the value or contract price of the materials furnished by the plaintiffs. It is claimed, however, that the plaintiffs, as a part of their contract, agreed to do certain carving, for which the defendant Tallman has paid, and obligated himself to pay, the sum of $468.76. This sum he asserts should be deducted from the amount which the plaintiffs claim; also that there should be deducted from said claim the further sum of $200 for refitting the work which the plaintiffs delivered, and certain other small sums for cartage, etc. The main item in dispute is the carving. The complaint avers that the defendant Tallman contracted with the plaintiffs to furnish the interior woodwork and trimming for the said building, and further avers the performance of such contract. The defendant Tallman testified upon this subject: “I saw the panelwork after it was completed and in the church, and, aside from the carving, it was all completed according to the plans and specifications. That was done by the plaintiffs in this action.”. The court was justified, therefore, in finding that the plaintiffs performed their contract, unless the carving formed a part of it. It stands admitted that the defendant Tallman has paid the carving bill, or obligated himself to pay therefor, in the amount which he seeks to counterclaim; and, if it be within the contract, then the plaintiffs are compelled to suffer a deduction to that amount. Upon this subject there is some dispute in the testimony. It is admitted that the plans and specifications show that there was to be the interior carving which was done. It also appears that both Tallman and the plaintiffs understood but little about the carving which was required, and the architect of the building testified: “If they had never seen the carving, and never did any work for us, it would be necessary to ask us what kind of carving was contemplated.” It is therefore evident that, while the plans and specifications indicated what carving was to be done, yet, in order to have a fair understanding of its nature and extent, it was necessary that the plans and specifications should be
We think that this testimony, and much to which reference is not made, authorized the court to find either one of two propositions: That the plaintiffs by their contract never undertook to do the carving upon the Gothic panelwork, but were only to make the panels and do the carving about the door, and that the defendant Tallman left it with Blauvelt to determine the extent and character of the carving, and that Blauvelt’s estimate of the cost of that work was binding
So far as the question of allowance to the defendant Tallman for extra work is concerned, a question of fact was presented, and this court, under the evidence, is concluded thereby.
We find no error in the record prejudicial to the defendant Tallman, and therefore conclude that the judgment should be affirmed.
Judgment affirmed, with costs. All concur.