Majority
Headnote
1. Executors—Building Contract—Liability of Estate.The defendants were named as executors and trustees under the will of Peter A. H. Jackson, deceased, which provided that the estate was to be held and managed by them for the benefit of his children, and they were directed “to pay and discharge, from time to time, all taxes and assessments” on the property, “and keep the same insured, and in good repair and condition, if damaged rebuilt, while held in trust by them.” In their agreement with the plaintiff, dated August 14, 1896, the defendants signed and executed it as “executors and .trustees under the last will and testament of Peter A. H. Jackson.” On the opening of the trial, and again on this appeal, it was insisted that the complaint did not state, and neither did the proofs establish, sufficient to constitute a cause of action against the defendants, as executors and trustees or in their representative capacity, but only against them as individuals. In support of this contention, we are referred by the appellants to a long line of authorities, in which it has been held “that a debt contracted by an executor or administrator as such, and for the benefit of the estate which he represents, only binds him individually, and does not bind the estate.” The reason for the rule is well stated in Van Slooten v. Dodge, 145 N. Y. 327 , 39 N. E. 950 : “An executor cannot subject the estate in his hands for administration to some new liability, either by his contract or by his wrongful act.” Even this general rule is subject to exceptions, where express authority is given by the will which requires expenditures to be made in the course of administration to preserve the estate. Willis v. Sharp, 113 N. Y. 586 , 21 N. E. 705 . The distinction between administrators or executors and trustees is important. Ordinarily, the only duties resting on an executor or administrator are to take possession, collect assets, pay debts, and retain the estate for distribution; all of which the statute assumes can be done in 18 months, except in ■ special cases, when a longer period is required. They have nothing to do with the real estate. The duties of trustees usually are more extensive, more onerous, more responsible, and cover a longer period, and to them, where real estate is the subject of the trust, are committed its care, preservation, and management. Their right and authority are therefore greater, and, in considering the power of representatives of an estate to make contracts and charge the trust estate, the distinction between an executor and trustee must always be kept in mind. With respect to trustees, “the general rule undoubtedly is that a trustee cannot charge the trust estate by his ex-ecutory contracts, unless authorized to do so by the terms of the instrument creating the. trust. Upon such contracts he is personally liable, and the remedy is against him personally. Bu.t there are exceptions to this general rule. When a trustee is authorized to
The real point, therefore, is, were the defendants authorized to make the contract? Undoubted power was given to them, under certain contingencies, to rebuild such building or buildings as would be, in their opinion,'beneficial to the estate; and it was within their right to determine when the damage was such as to make it proper to exercise their power to rebuild. That the original buildings were old and out of repair, and that the defendants deemed it wise and beneficial to rebuild, was made, to appear. Moreover, the answer did not deny such authority, though the amended answer may be said to have raised the question; but upon the stand Mr. Jackson, the trustee, stated that he understood he had a right to improve the property, and build on it, and to make the contract which he made. The power having been given to rebuild if necessary, and the trustees deeming the expenditure necessary for the protection and safety of the trust estate, and having by express agreement charged themselves in a representative capacity, they have made such expenditures a proper charge against the trust estate. Warren v. Bank, 28 App. Div. 19 , 51 N. Y. Supp. 27 .
This contract provided that the materials necessary should be furnished, and the work done, in accordance with the specifications, on or before November 1, 1896, in a good, workmanlike, and substantial manner, to the satisfaction and under the direction of the architect, certified by his writing or certificate. Bearing directly on the question of performance, besides the testimony of the plaintiff that all the work was completed in a satisfactory manner, we have the certificate of the architect, which it was stipulated should be given. The work also received the approval of the building department. A material defect shown was in the clogging of the pipes, but this was offset by the plaintiff’s statement that the pipes were clear when he left the job. Allegations in the answer as to uncompleted work do
Upon this question of authority, we have testimony tending to show that each item was expressly ordered or suggested. The architect says he ordered some, and we have letters covering other items included in the charge for extra work. This testimony was contradicted by the defendants, and the question was submitted to the jury. The appellants contend, however, that the receipt dated December 28th shows that it was accepted in full payment of all extra work done prior to that date, and they dispute alleged extra work done thereafter. This receipt was for the third payment in advance, by request, and purports by its terms to be a receipt also for extra work to date. Just when the extra work in the schedule annexed to the complaint was done is not clearly shown, although Some of the items are dated; and, as the amount of $.1,500 has-been credited to payment of the $15,300 on the contract work, it was necessary, for the purpose of an adjustment, that all items should be taken into consideration, and a balance obtained. So proceeding, it remains to inquire into the nature and amount of the claims for extra work.
The plaintiff testified that, in cases where extra charge was made, the figures were for the difference in price allowed for by the contract and the articles furnished and work done. Thus, with regard to “Fuller cocks,” we have a letter from the firm from which they were purchased, stating that $154 was the difference in price. So, also, with regard to the closets, it was stated that the Climax closet was a patented article, not known in the trade as “small washout closets,” as named in the specifications, and the item is for the difference in price. That there were substitutions of items for those in the specifications is evident. One-half instead of five-eighths inch pipe was furnished, and different iron riser pipes were put in, and changes were made in the bath tubs and sinks. The plaintiff testified that the necessity of making certain changes was called to the attention of the defendants, and that they assented to such changes, and agreed to receive, and did receive, therefor an allowance, where there was a difference in the cost or value. Both the architect and one of the defendants, Jackson, were present daily superintending the work, and they had the opportunity to object, had they seen fit, to any deviations or changes from the specifications. The conflict arising on these items was submitted to the jury, and the verdict shows that as to some they made deductions from the plaintiff’s claims. It would exceed the limits of an opinion to discuss each item, its cost, whether authorized, or whether included in the specifications. There was a sharp conflict on most of them, and just what ones were allowed and what ones rejected by the jury it is neither possible nor necessary to determine, and, unless there were errors in the charge, their verdict should not be disturbed.
An objection is taken to that part of the charge in which the ■court said that the jury might deduct the difference in value of any variations from the contract. What the judge undoubtedly had then
Another objection urged is to the refusal to charge that the plaintiff was not entitled to recover items (Fuller cocks instead of T-handle cocks, pipes for hot-water tank, and Climax closets) for alleged extra work performed, because such items were covered by the specifications. Whether such were intended by the specifications was not apparent, and upon each item there was, as already said, close and conflicting testimony. Thus, the specificatiohs speak of “cocks,” not Fuller cocks; and it was testified that ordinary T-handle cocks were intended, and that Fuller cocks were of greater cost. On the other hand, there was testimony that the Fuller cocks were no more expensive. A question of fact was thus presented for the jury, since Fuller cocks were not specifically mentioned in the specifications; they were ordered by special letter, and the firm from whom they were purchased said the cost would be greater. The same may be said with regard to the Climax closets. The specifications merely mention “small washout closets”; and it was testified to that the Climax closets were not known in the trade by that name, but were a patented article, and more expensive. Finally, as to the hot-water pipes, it was testified that the location was changed from that set forth in the specifications, requiring additional pipe and labor.
It is contended, further, that it was error for the court to grant an extra allowance and costs against the defendants, as executors and trustees, for the reason that the plaintiff recovered $100 less than the original claim, and failed to present proof of presentation of claim, or an offer to refer and refusal of the defendants. The provisions of the Code upon the subject of costs in actions against executors have no application to a .case like the present, wherein the claim or right of action is one against the trustees on a contract made by them after the death of their testator.
The judgment should be affirmed, with costs. All concur.
Cases cited
- Claim for a Ring of Van Slooten v. Dodge 145 N. Y. 327 p. 1046
- Willis v. Sharp 113 N. Y. 586 p. 1046