Diehl v. Schmalacker

62 N.Y.S. 1080 Court N.Y. App. Term Decision date 1900-02-23 English

Contents

Majority

p. 1080
DIEHL v. SCHMALACKER.
(Supreme Court, Appellate Term.
February 23, 1900.)

Headnote

1. Contracts—Building Contract—Certificate of Architect—Waiter.
Failure of defendant to employ an architect to supervise the construction of his "building is a waiver of a stipulation in the contract that the work should be done agreeably to the plans and specifications, to the satisfaction of the architect, “to be testified by a writing or certificate under the hand of said architect.”
2. Same—Waiver of Defect in Performance.
Where the party for whom a building was being constructed saw, during the progress of the work, that all the specifications in the contract were not being complied with, and-paid all hut $100 of the contract price, and, after the completion of the work, promised to pay the balance as soon as he was able, he waived the defects in the construction of the building.
Appeal from municipal court, borough of the Bronx, Second district.
Action by John Diehl against Bernard Sckmalacker! Judgment for plaintiff, and defendant appeals.
Affirmed.
The following is the opinion of the court below (TIERNEY, J.):
This action was commenced in the late district court of the city of New York for the Tenth judicial district, which has been superseded by this court. It was originally tried before Mr. Justice MeCKEA and a jury, and resulted in a verdict for the plaintiff, but the judgment was. reversed on appeal and a new trial ordered. On such trial before me the case was submitted on the testimony taken on the previous trial, with the addition of new testimony of Michael J. Garvin. The action was brought for the balance claimed to be due on a written contract for the construction of the mason work of three buildings, which provided that this work should he done “agreeably to the plans and specifications made by Michael J. Garvin, to the satisfaction and under the direction of the said architect, to be testified by a writing or certificate under the hand of said architect.” On the’ former trial the architect was not called, and no explanation whatever was given for the failure of the plaintiff to produce a certificate, and the supreme court for that reason reversed the judgment. See opinion of MacLean, J., filed March 21, 1899. 57 N. Y. Supp. 244 . On the present trial the architect, Michael J. Garvin, was called, and testified that he was employed only to draw the plans and specifications; that he did not supervise the construction of the building, and had nothing to do with it after supplying the plans and specifications; that, if he were asked or required to furnish a certificate, he could not do so, because he had no supervision over the construction of the buildings. The defendant’s failure to employ Garvin, so as to make it possible for him to furnish a certificate, was a waiver by the defendant of the requirement of such certificate, and this further evidence meets the defect in the plaintiff’s case pointed out in the opinion of reversal.
Upon the trial there was also a contention as to certain defects in the construction of the work which the plaintiff had contracted to do. I think, however, that whatever departures there might have been from a strict performance of the contract were waived by the defendant, or accepted as a substantial compliance. He saw the work in progress, and had noticed these matters during the construction, and yet has voluntarily paid all but $100 of the $3,000 con tract .price, and, after the plaintiff had left the work entirely,' promised to pay the balance of $100, giving as an excuse for his inability to have done so before that he was short of money. Nine hundred dollars of the contract price was paid three months after plaintiff had left the work claiming to have finished.
Regarding the counterclaims interposed by the defendant, the only one that has any apparent basis is that for $25, which he says he paid for cleaning up the house. The evidence on this point does not establish to my satisfaction that this money was paid for work to he done by the plaintiff. It appeared
p. 1081
that, after the plaintiff left the work, carpenters came in and made considerable dirt. The plaintiff has established his cause of action, and judgment is given for the sum of §100.
Argued before BEEKMAN, P. J., and GIEGERICH and O’GrORMAN, JJ.
William Henry Knox, for appellant.
J. C. Julius Langbein, for respondent.

Judgment affirmed, with costs, on opinion of court below.