Majority
Headnote
1. Municipal Corporations—Public Improvements—Liens—Statutes—Repeal.This action was brought to determine the rights of various parties to money due under a contract made and entered into on June 24, 1897, between David F. Gibbs and the city of New York, through the board of education, for the building of a school house. The total amount of the contract was $124,164, of which there has been paid $93,600, leaving in the hands of the comptroller the sum of $30,564, which is the subject of this controversy. The contractor testified that the .claim of the Eleventh Ward Bank was for money borrowed to. use for pay rolls and to pay bills; that he (the contractor) was obliged to borrow some money to carry on the business, and money was used to the extent of $7,500—which was the consideration named in the assignment to the bank—in carrying on the work; that the money was obtained from the bank at different times, but the full amount of $7,500 had been advanced when the assignment was executed; that at that date there was due on the contract more than $7,500 in addition to sufficient money to pay the prior liens which had been filed against the fund. In other words, it clearly appears that the assignment executed to the bank was for a good and valuable consideration, and that, when made, there was owing by the city on the contract sufficient to pay the $7,500, in addition to enough to pay the prior lienors.
The main question presented on'this appeal is as to the priority of the claim of the Eleventh Ward Bank over subsequent lienors,— whether the assignment by the contractor, Gibbs, to the bank of a part of the fund due or to grow due is postponed in time of payment to liens subsequently filed. The subsidiary questions relate to the validity of the liens, exception being taken to some of them on the
Although there were some minor amendments, extending the scope- or declaratory of the intention of the consolidation act, none of them needs consideration till we come to the general lien law of 1897 (Laws 1897, c. 418), which is a general statute upon the' subject of mechanics’ liens, and to chapter 419 of the Laws of 1897, amending the-Code of Civil Procedure, both of which went into effect on September-1, 1897. This act of 1897 has a provision (Laws 1897, c. 418, § 5) relating to liens under contracts for public improvements, which, at first blush, might be regarded as affecting the consolidation act. When, however, we appeal to that rule of construction that a special and local statute providing for a particular case or class of cases is-not repealed by subsequent statute, general in its form, provisions,, and applications, unless the intent to repeal or alter is manifest, although the terms of the general act are broad enough to indicate-cases embraced in the general law (McKenna v. Edmundstone, 91 N. Y. 231 ), it becomes evident that the consolidation act was not repealed, for we fail to find in the general act any intent to supersede-its provisions. This view is strengthened by the act passed in 1899 (Laws 1899, c. 195), which expressly repeals the sections of the consolidation act and acts amendatory thereof (relating to mechanics’" liens on account of public improvements in the city of New York), which expresses the legislative construction that those sections of the
The consolidation act provides for the filing of a lien, and there is nothing in its terms which would prevent the contractor from assigning any portion of the moneys due or to grow due thereunder to one to whom he is indebted, or who, on the faith of the contract, advances money. Nor is there any good reason, in the absence of an ■express inhibition, why the contractor, who may have proceeded in part with his work, and who is prevented from going ahead by lack •of funds, should not have the right to obtain money by way of loan, which may be used for the benefit of the work, and pledge the moneys due and to grow due under the contract by means of an assignment for the repayment thereof. We can see no distinction between the rights of a contractor who does work for, the city, in this respect, and one who enters into a private contract. There is nothing in the consolidation act, any more than in the general lien law, which expressly gives a preference to a lien over an assignment. If one does work, or advances money to aid the work, there is nothing in the law to compel him to file a lien in preference to taking an assignment. There are many decisions which, following the case of Lauer v. Dunn, 115 N. Y. 405 , 22 N. E. 270 , recognize in contracts made between private parties the right of a contractor to make an assignment, and the priority of such an assignment over liens subsequently filed. See Fortunato v. Patten, 147 N. Y. 277 , 41 N. E. 572 ; McCorkle v. Herrman, 117 N. Y. 297 , 22 N. E. 948 ; Stevens v. Ogden, 130 N. Y. 182 , 29 N. E. 229 ; Beardsley v. Cook, 143 N. Y. 143 , 38 N. E. 109 . These cases uphold the rule enunciated in Lauer v. Dunn, supra, which is well summarized in Bates v. Bank, supra, as follows:
“In the absence of anything to the contrary in the contract, and before any •notice is filed, the contractor may assign to his 'creditor, in payment of his •debt, the whole or any portion of the moneys due or to become due under the contract, and the assignee acquires a preference over a subsequent lienor.”
That this rule is equally applicable to contracts made with a municipal corporation is supported by the case of Hackett v. Campbell, 10 App. Div. 523 , 42 N. Y. Supp. 47 , affirmed in 159 N. Y. 537 , 53 N. E. 1125 , without opinion. There the question involved a provision of a contract between the board of education of the city of Yonkers and a contractor to the effect that no assignment of any portion of the amount due upon the contract should be made without the consent first had in writing of the committee of the board of education. During the progress of the work, numerous assignments having been :made by the contractor, and paid, this was deemed to constitute a
This determination renders it unnecessary to discuss any of the other questions urged by the appellant as to the invalidity of the subsequent liens, for the reason that the bank, the appellant here, is not concerned with them.
Judgment reversed, and new trial ordered; costs to appellant, payable out of the fund, to abide event.
VAN BRUNT, P. J., and RUMSEY and PATTERSON, JJ., concur.
I am unable to concur in the reversal of this judgment. The assignment under which the appellant claims was executed by one David F. Gibbs, and grants, assigns, and conveys “unto the Eleventh Ward Bank, New York City, $7,500 of the moneys due and to become due for and on contract No. 77 of 1897, made and entered into by and between the board of education of the city of. New York, and through its committee, on buildings, and myself as principal, and Thos. Bailey and Geo. A. Haggerty as sureties, on June 24th, 1897, for erecting an annex building to Grammar School No. 2; * * * to have and to hold the same unto the said the Eleventh Ward Bank, N. Y., its successors and assigns, forever, to and for the use of said Eleventh Ward Bank.” This assignment was dated October 29, 1898. It does not appear that there was then any money due to the assignor under his contract with the city, and this assignment was, therefore, simply a transfer of $7,500 of the money that the assignor, as contractor, would be entitled at a future time to receive from the city under the contract. The assignor created the Eleventh Ward Bank his attorney to receive from the city the sum of $7,500 when that sum became due to the contractor from the city, and simply .transferred to the assignee the right of the assignor to receive that sum of money out of the moneys which the city subsequently became under a legal obligation to pay to him. No specific payment is assigned. The assignee was substituted for the assignor in his right to obtain from the city this sum of money under the contract; and this right was subject to all of the obligations or liabilities of the assignor created prior to that time, either by transfers or agreements of his own, or by operation of law, which would tend to affect the obligation of the city to pay to him any sum of money upon the completion of his contract. If the assignment had been a transfer of all the money which was to grow due to the contractor upon the final completion of his contract, it does not seem to me that such an assignment would result in a transfer of the money when it should become due, so as to render inoperative the statute passed for the protection of mechanics and laborers who had furnished labor or material for the completion of a contract of a municipal corporation; and the assignment of the portion of the money which became due could have no greater effect.
I do not concur with Mr. Justice O’BRIEN in his conclusion that the provisions of the general lien law of 1897 are not applicable to the city of New York. The provisions of the act are sufficiently broad to include that city, and there is nothing in the act that would show
“In all contracts for work done by or for the corporation, the head of the department having charge thereof shall cause to be inserted a provision that the payment of the last installment due in pursuance thereof shall be retained until such head of department shall have satisfactory evidence that all persons who have done work or furnished materials under any such contract, and who may have given written notice to such head of department any time within ten days after the completion of said work, that any balance for such work or materials is still due and unpaid, have been fully paid or secured such balance. And if any person so having done work or furnished materials and given such notice as aforesaid shall furnish satisfactory evidence to the department that money is due to him by the contractor under such contract, such head of department shall retain such last installment, or such portion thereof as may be necessary, until such liability shall be discharged or secured.”
In considering this ordinance, the court say:
“We think the purpose of the ordinance was to secure to persons furnishing labor and materials to contractors with the city some of the advantages which the lien laws of the state give to mechanics and material men, and this result was sought to be accomplished by making the city a trustee of the unpaid balance due upon the contracts with it for the benefit of such persons. * * * The ordinance, and the clauses inserted in the contract in pursuance thereof, were intended for the benefit of the laborers and material men dealing with the contractor, and they should not be so construed as to make them illusory, misleading, and nugatory.”
This same ordinance was again before the court in the case of Bank v. Winant, 123 N. Y. 266 , 25 N. E. 263 , where the court say:
“But here we have a case where the plaintiff appears to have advanced moneys to the contractor to perform a contract undertaken by him, and to have taken as its security for repayment an assignment of the moneys which were or might become due by virtue of the contract. As I understand the import of such language, it is that the assignee should be entitled to be paid whatever moneys and whenever the contractor could legally demand to be paid by the city under the contract. So that, unless the city could legally refuse to pay a claimant under the contractor, the plaintiff is not in any position to object to the payment. Its whole concern is that it recovers the net amount which is earned by the performance of the contract. As to claims against the contractor by those employed in the work under him, I do not see why the city is not authorized to pay any such of which it has notice.”
It certainly seems to irte that by the provisions of the consolidation act and the mechanic’s lien law, before cited, the legislature sought to accomplish just what the common council did in passing the ordinance referred to in the cases just cited; and to hold that a contractor, by simply transferring to another the moneys which are to grow due under the contract, could make such assignment, superior to the right of those to whom the statute gives a lien for the labor or materials actually furnished in completing the contract, would be
Cases cited
- Merchants & Traders' National Bank v. Mayor of New York 97 N. Y. 355 p. 60
- Mechanics & Traders' National Bank v. Winant 123 N. Y. 265 p. 60
- Bates v. Salt Springs National Bank 157 N. Y. 322 p. 60, p. 61
- McKenna v. Edmundstone 91 N. Y. 231 p. 60
- Lauer v. Dunn 115 N. Y. 405 p. 61
- Fortunato v. Patten 147 N. Y. 277 p. 61
- McCorkle v. Herrman 117 N. Y. 297 p. 61
- Stevens v. Ogden 130 N. Y. 182 p. 61
- Beardsley v. Cook 143 N. Y. 143 p. 61
- Hackett v. Campbell 10 App. Div. 523 p. 61
- Hackett v. Campbell 159 N. Y. 537 p. 61