Majority
Headnote
Injuries from Defective Sidewalk—Notice to Foreman—Evidence of Repairs Made After Injury.This action, which was brought to recover damages for personal injuries sustained by the plaintiff in consequence of a defective sidewalk in the city of Rochester, has been twice tried. Upon the first trial the plaintiff was nonsuited upon the ground that notice of the defect complained of was not given to the city officials having charge of the streets and sidewalks within a reasonable time before the occurrence of the accident, as required by section 218 of the city charter. Thereafter a motion for a new trial was made and denied at general term ( 88 Hun, 613 , 34 N. Y. Supp. 1126 ), and from the judgment entered thereon an appeal was taken to the court of appeals, where it was held that notice of a defect in a sidewalk given to a foreman of sidewalks, clothed with general power to repair throughout a large district of the city, is notice to a city officer having charge of highways, within the meaning of the provision of the charter of the city of Rochester (Laws 1880, c. 14, § 218, amended by Laws 1890, c. 561), requiring notice “to the city officers having charge of the highways” of a defect in a sidewalk as a prerequisite to a right of action to recover damages for an injury caused thereby; and that inasmuch as there was ample proof of such notice, and ho question made as to the defective condition of the walk, the case was improperly withheld from the jury ( 159 N. Y. 20 , 53 N. E. 697 ). Upon the last trial the defendant did not deny the existence of the defect in the walk, but sought to escape liability therefor under the rule established by the court of appeals, by an attempt to prove that the authority of Moore, the foreman of repairs to sidewalks within the district wherein the walk in question was located, and the one to whom notice of its defective condition was given, did not extend to stone walks, which were repaired by contractors under the supervision of the executive board, but was restricted to the repair of wooden walks.
But it was expressly stated by the learned trial justice that it was received for no such purpose, but simply and solely as bearing upon the question of Moore’s authority. It is now insisted, however, that the. evidence was incompetent, even with this limitation attached to it, and, if it is to be regarded merely as evidence of an independent act or declaration with which the defendant is not connected, and for which it is in no wise responsible, it probably cannot be said that the defendant’s contention is unsupported by authoritative precedent. Clapper v. Town of Waterford, 131 N. Y. 382 , 30 N. E. 240 ; Terwilliger v. Town of Crawford, 40 App. Div. 253 , 59 N. Y. Supp. 64 . But, upon the other hand, if Moore’s acts, taken in connection with othei evidence which is concededly competent, tend to establish authority in him to perform those acts, we fail to see why they are not as binding upon tire defendant as though they had been performed in obe
Judgment and order affirmed, with costs. All concur.
Cases cited
- Sprague v. City of Rochester 159 N. Y. 20 at 53 p. 846
- Getty v. Town of Hamlin 127 N. Y. 636 p. 847
- Clapper v. Town of Waterford 131 N. Y. 382 p. 847
- Terwilliger v. Town of Crawford 40 App. Div. 253 p. 847
- Sewell v. City of Cohoes 75 N. Y. 45 p. 848