1. City—Public Work—Contractor—Unforeseen Obstacles—Damages.On the 24th of October, 1896, Mairs made a contract' with the city of New York to build and place a crib fender for the Pelham River Drawbridge in Pelham Bay Park. The work consisted of placing a crib fender in a branch of Pelham Bay, so that the ends
The plaintiff claims that the defendant was liable for the increased expense to "which the contractor was put because of this delay, for the reason that it had permitted the pipe of the water company to be located in the place where the fender was to be put, and that it was aware of its location, and failed either to remove the pipe, or to change the specifications in such a way that the contractor could go on with his work. The defendant, on the contrary, claims that the plaintiff, under the terms of the contract, took the risk of the existence of the pipe, and of any other obstruction or incumbrance upon the bottom of the stream, and that it was his duty to ascertain its existence, and, as he failed to do so, he cannot now hold the defendant liable for the damages which resulted.
The contract was made upon the usual estimates and specifications. The advertisement for estimates provided that the bidders must satisfy themselves, by personal examination of the location of the proposed work, as to the accuracy of the engineer’s estimate. It was provided in the specifications that the soundings shown on the plans had been made with thoroughness and care, and were believed to be correct, but that the contractor must satisfy himself of their accuracy, as the park department would not be responsible for any discrepancy between those shown on the plans and any others which might be made. The specifications further provided that:
“All loss or damage arising out of the nature of the work to be done under this agreement, or from any unforeseen obstructions or difficulties which may •be encountered in the prosecution of the same, * * * or from incumbrances on the line of the work, * * * shall be sustained by said contractor.”"
It appeared that on the 24th day of July, 1891, permission had been given by the park board to place this water pipe through Pelham Bay
There is nothing in the case of Horgan v. Mayor, etc., 160 N. Y. 516 , 55 N. E. 204 , that militates against this conclusion. In that case the plaintiff had agreed to clear and concrete the bottom of a park lake for the city of New York, and the contract contained provisions that the contractor should drain off all the water, and that he should furnish
By the contract the city was at liberty to charge Hairs with certain liquidated damages because of any unnecessary delay that might occur in doing the work. In the settlement with him, the city’s officers did’ not see fit to charge him for the delay while waiting for some arrange- - ment to be made about the pipe, but allowed him the 43 days during - which the delay continued. On that account it is said that the fact that they allowed him the 43 days operates as an admission on the - part of the city that it was responsible for that delay. But it cannot be said that, if the city saw fit to waive its right to charge liquidated: damages against him, that is any reason why it should be charged with; damáges for which it is not responsible.
For these reasons, the judgment should be reversed, and a new trial granted, with costs to the appellant to abide the event. All concur,. except PATTERSON, P. J., who dissents.