Majority
Headnote
Mechanic’s Lien—Foreclosure—Plans and Specifications—Willful Noncompliance—Negligent Noncompliance—Dismissal of Complaint.This action was brought to foreclose a mechanic’s lien upon real property situate in the city of New York. In April, 1891, the plaintiffs and the defendant entered into a written contract by which the former agreed to erect upon land of the latter a stable, and to furnish all the materials and labor required in the work, which was to be done according to certain plans and specifications for an agreed price of $6,900; $1,900 thereof to be paid when the roof timbers were on, and the balance of $5,000 when the building was finished. It is alleged in the complaint that, after the contract was made, various alterations and modifications of and additions to the plans and specifications were made with the consent of
The only subjects involved in the appeal relate tó substantial performance of the work by the plaintiffs and the acceptance of the completed work by the defendant. The referee has found on those subjects against the plaintiffs. They now insist that no allowance should have been made by way of deduction, because of thé defendant’s acceptance of the work; that, if deductions should be allowed, then the referee was in error as to many of the items of allowance, and that, after making all proper allowances, he should have found that the plaintiffs substantially performed their contract as modified, altered, or added to. The evidence plainly shows that the plans and specifications for the work as originally projected were modified in some respects after the contract was signed, and before the 29th of June, 1891. The referee has found that the defendant accepted so much of the work as was done up to that date, but he also found, and was fully authorized to do so, that after the 29th of June, 1891, the plaintiffs failed to perform their contract as modified; and the evidence sustains his further finding that it would cost the defendant some $1,200 to supply the omissions and repair the defects in the work as it was left by the plaintiffs. The evidence is not sufficient to sustain a finding that the defendant specially promised to pay the plaintiffs the $5,000 as alleged in the complaint. The various details of the insufficiency in the performance of the contract are set out in full in the referee’s report, and they are some 23 in number. Most of them are very substantial in their nature, and there is evidence to show that many of the departures from the modified contract and omissions of work must have been intentional; as, for instance, those relating to the thickness of the walls, the height of the partitions of the stalls, plumbing work, the shaft for fresh air, and the want of pillars or stones under posts supporting girders. Many of the defects for which the referee has held the plaintiffs responsible were omissions in the work required by the plans and specifications or departures therefrom after the 29th of June, 1891. The plans and specifications were never abandoned, but alterations and changes were
The judgment should be affirmed with costs. All concur.
Cases cited
- Glacius v. Black 50 N. Y. 145 p. 91
- Van Clief v. Van Vechten 130 N. Y. 571 p. 91
- Crane v. Knubel 61 N. Y. 645 p. 91