Grading Street—Extra Cost—Errors of Surveyor.On the 13th of November, 1889, the defendant entered into a contract with one Carr for the regulating and grading of Claremont avenue from 122d to 127th streets, in the city of New York. At the completion of the work a final certificate was made by
In considering the question presented upon this appeal, we must assume that every fact necessary to be established by the plaintiff to ■ entitle her to a verdict was found in her favor, in so far as there was evidence to sustain the finding. As to the $325 “repairing security,” it is not questioned but that the plaintiff is entitled to recover that sum. Therefore so much of the appeal as relates to that item may be dismissed without further consideration. The three remaining items will be considered together.
It is not' disputed but that the defendant paid $2,044 to an inspector, and that such payment was caused by reason of the contractor’s failure to complete the work under the contract within the time- specified therein. Neither is there any contest between the parties that the engineer did not include in the final certificate the amount of the second item, nor that it cost the contractor the amount claimed in the third item to do the additional work. But it is claimed by the appellant that it is not liable to the respondent for these items, or any of them, for the reason that the delay which resulted in the payment of the $2,044 to the inspector, as well as the cost of the additional work not included in the final certificate, and the increased cost of doing the work, was the fault of the contractor, and not the fault of the defend
“A city surveyor will be employed by the party of the first part [the city] to see that the work is completed in conformity with the profile, and to ascertain and certify to the quantity of .work done. Said surveyor, at the request of the contractor, will be directed to designate and fix the grades for his guidance during the progress of the work, without charge: provided, the said party of the first part shall not be liable for any delay or for any errors of said surveyor in giving such grades, and said surveyor shall be considered as the agent of the contractor, so far as the giving of such grades is concerned, and not the agent of the city of New York.”
By the contract the contractor agreed that he would regulate and grade the street in accordance with the plans and specifications, and the map and profile on file; and, for the purpose of determining whether he was° performing his work in accordance with his contract, he had the right to employ a surveyor, at his own expense, or he could, without expense, if he saw fit, obtain the services of the city surveyor, but if he relied upon the latter, he expressly agreed that the city should “not be liable for any delay or for any error of said surveyor in giving such grades,” and that, in case services were rendered by the city surveyor, he should be considered the agent of the contractor, and not the agent of the city. When the contractor commenced work, according to his own testimony, he found certain stakes set,- indicating, as he supposed, the center line of the street, and, assuming that they were correctly set, he prosecuted his work for several days according to them, when one Grassnock appeared, who informed him that he was an-assistant to one Slater, the city surveyor, who had charge of the grading of that street. That Grassnock changed the stakes which he found set when he commenced work, and he thereafter worked according to the stakes set by Grassnock. That he subsequently employed a surveyor, at his own expense,—just when, .the record fails to disclose,—who informed’him some time in July, 1890, that the stakes set by Grassnock did not correctly indicate the center or grade line of the street, and he thereupon conveyed such information to the superintendent of public improvements, who, in turn, directed him to proceed with the work in accordance with the grade
As we .have said, it is not disputed that the amount retained for the inspector’s fees was actually paid by the city on account of the delay in not completing the contract within the time specified in the contract; nor does it seem to be disputed that the amount paid by the contractor for excavating a quantity of rock and earth sought to be recovered in this action was not included in the final certificate given, and that the additional expense was occasioned by reason of the contractor’s assuming that the center line of the street had been correctly designated by the stakes which he found set when he commenced work, or the erroneous designation of them by Grassnock. But under the contract the city cannot be held liable for this error. To hold otherwise is to render nugatory the provisions of the contract by which the contractor agreed to assume responsibility and liability in this respect. This the contractor knew, and what he did unmistakably evidences that fact. In the first place, he had no right to assume that the stakes which he found upon the ground, indicating, as he supposed, the center line of the street, bound the city. There is nothing to show that the city put them there, or that they were intended to be used by him in prosecuting his work under the contract, or in fulfillment of its provisions. And, in the second place, there is nothing to indicate that the contractor supposed that he had a right to, or in fact did, rely, as binding the city, upon the work done by Grassnock. He, of course, knew that the contract required him to perform the work in accordance with the plans and specifications, and the map and profile on file, referred to in the contract. But it is said that the city is liable because the contractor did not request Grassnock to indicate the center or grade lines, and, not having requested him to do this work, he is not bound by what he did; that, not having made a request to have the center and grade lines designated, he had a right to assume (Grassnock being in the employ of the defendant) that his work was correct. There is no force in this contention, for the reason already indicated, viz. that by the provisions of the contract the city had expressly provided that the contractor could have a city surveyor if he wanted to designate these lines, but in that case the surveyor was the agent of the contractor, and not the agent of the city. Nor is it true that the contractor acted upon the assumption that the work done by Grassnock was correct. On the contrary, he ridiculed and criticised his work. He knew it was of a most primitive character and that no reliance could be placed upon it, and, as evidence of this fact, he employed a surveyor at his own expense,—just when does not appear, —who informed him, several months after the commencement of the work, that a mistake had been made in the center and grade lines; and the contractor then requested Slater, the city surveyor, to personally designate such lines, which Slater did. Therefore, if we give to the testimony of the contractor the most favorable consideration possible, it appears that he not only had no right to, but in fact did not. rely upon the work done by Grassnock. If the defendant is to be pro
Concurrence
For the foregoing reasons, we are of the opinion that the judgment should be reversed, and a new trial ordered, with costs to the appellant to abide the event, unless the plaintiff will stipulate to reduce it to the sum of $325 and interest thereon; and, if such stipulation be made, then the judgment should be modified to that extent, and as so modified affirmed, without costs to either party.
VAN BRUNT, P. J., concurs.
For reasons given by Judge STOVER, at trial term, I dissent.
I concur with Mr. Justice McLAUGHUN in a reversal of this judgment. It is quite true that Thomas Slater was on the 13th day of August, 1889, designated by the defendant to act as the city surveyor under the contract between the plaintiff and the defendant. That designation, however, did not make the surveyor the general agent of the city. As between the parties to this action, whatever authority he got under his designation was that given to him by the contract. The city would be liable for all acts of the surveyor within the scope of his employment, when acting for or on behalf of the city. What the plaintiff’s assignor agreed to do under the contract was to furnish “and provide all the materials and labor for the purpose, and regulate and grade Claremont avenue from One Hundred and Twenty-Second to One Hundred and Twenty-Seventh street, and set curbstones and flag sidewalks therein. * * * All the work and labor done under this contract shall and will be done at the times, in the manner, and under the conditions set forth and specified in this contract and said specifications.” And the plaintiff agreed
Assuming, however, that the city would be responsible for any grades given by Slater which were erroneous, there is no evidence that Slater ever gave a grade that was erroneous. Slater was the surveyor designated. The city relied upon his capacity and integrity to act for it under the contract. The plaintiff testified that when he commenced this work, on or about the 23d of November, 1889, he found certain stakes there, which he assumed to indicate the proper grades; that he worked several days at this stake, when a Mr. Gfrassnock came upon the work with an instrument, accompanied by a boy, and informed the plaintiff’s assignor that he was Slater’s assistant, and had been sent there to give to the plaintiff grade stakes. In the first place, this statement that he was Slater’s assistant, sent there for this purpose, was no evidence, against the city, that he occupied that relation to Slater, or that Slater had sent him there to fix these grades. Nor would the city be liable for Grassnoek’s errors, assuming him to have been Slater’s assistant, because the city had appointed Slater, and not Grassnock, and Slater had no authority to substitute another surveyor in his place to perform the important duties that the city had em
HATCH, J., concurs.