Majority
Headnote
1. Building Contract—Extension of Time.This action was brought to foreclose a mechanic’s lien, amounting to $8,054.17, for work done and materials furnished in the construction, for the defendants, of a building at the corner of Riverside drive and Eighty-Fourth street, in the city of New York. A portion of the work done and materials furnished (amounting to the sum of $6,506) was alleged to have been done under a written contract, and the balance for extra work done and materials furnished for the same building. The defendants, by their answer, denied that the plaintiff had performed his contract, in that he had not completed his work upon the building within the time specified, and by reason thereof they had sustained damage to the extent of $12,000, which .sum they asked to counterclaim against the plaintiff. Upon the trial it was conceded that “the plaintiff duly performed for the defendants the work in accordance with the plans and specifications,” and that “notice of the mechanic’s lien set forth in the complaint was duly filed, and a copy served upon the defendants, and that after the commencement of this action this lien was bonded.” The defendants also conceded that there was due to the plaintiff under the original contract the amount claimed by him. After these concessions had been made, the only questions which remained to be determined were those arising under the plaintiff’s claim for extra work done and materials furnished, and the damages which the defendants alleged they had sustained, and which they sought to counterclaim against the plaintiff, and all of the
We are, however, unable to agree with the trial court that the plaintiff is entitled to recover all of his claim for extra materials furnished and work done. The items for extra work objected to by the defendants are included in Schedules A, B, and 0 of plaintiff’s Exhibit A, set out in the record. We do not think that the plaintiff was entitled to recover the claim there made. It is true that at the end of the exhibit the architect certified as follows: “Items A, B, and C I certify as being for materials purchased under letter of June 6, 1899. George Keister.” Keister, it will be remembered, was conceded to be the architect and agent. of the "defendants. : The letter referred to by him in this certificate is dated June 7, 1899 (not 6th), and reads as follows:
“Mr. O. F. Bond—Dear Sir: Please proceed with the work at Riverside drive and '84th street without delay. Substitute, at your own discretion, for the balance of the floor beams. Deliver as quickly as possible.
“George Keister.”
In relation to the materials for which a substitution was thus permitted, it appears from the testimony of the plaintiff himself, as well as that of Keister and other witnesses, that, owing to the condition of the iron market, it was impossible for the plaintiff to pro
It follows that the items included in Schedules A, B, and C, amounting to $65-7.60, should not have been allowed to the plaintiff, and for the error thus committed the judgment must be reversed, and a new trial ordered,- with costs to the appellants- to abide the event, unless the plaintiff will stipulate to deduct this sum from the amount of the judgment, together with interest thereon from the date of its entry, and, if such stipulation be made, then the judgment is affirmed as thus modified, without costs to either party. All concur.