Majority
Headnote
4. Contracts—Terms—Compliance—Supervisor’s Decision—Concj.usiveness.The plaintiffs are co-partners, doing business as contractors in the city of New York. On the 20th of December, 1898, they made a contract with the board of education of that city, by which they agreed to build a school house at the corner of Hubert and Collister streets for $193,93.1. The plaintiffs allege that they proceeded with the work in accordance with the contract, and were ready to complete the building at the time specified, but that on the 6th of June, while the work was in progress, they were served by the board of education with a written notice that the board elected to rescind the contract. They allege that they called at various times upon the board for permission to go on with the work, but were not allowed to do so. They allege that the delay in proceeding with the work was due to some extent to the failure of the board to lost the samples of the materials to be used in the building, and that by the action of the board they were forced to withdraw from the work and abandon it, and that thereby they were injured in the loss of their profits to the amount of $30,000, and that their credit and business were injured to the amount of $70,000, and they demand judgment for $100,000.
The defense was that by the contract it was agreed that if the plaintiffs at any time refused or neglected to furnish the proper materials, or to proceed with the work and furnish a sufficiency, of workmen, or should fail to prosecute the work in a prompt or diligent manner, after three days’ notice in writing given by the committee on buildings to the plaintiffs, the party of the second part, the contract should be avoided and forfeited, and the board should thereupon have the right to employ other persons to perform the work, and for any increase in the price necessary therefor the plaintiffs and their surety should be liable. It is alleged that it was further provided in the contract that, to prevent all disputes and litigation, it was agreed that the superintendent of school buildings should decide any question that might arise concerning the execution of the contract, or the work to be done or the materials to be furnished, and that his conclusion should be final and conclusive upon the contractors. It is further alleged that in May, 1899', the plaintiffs failed to supply a sufficiency of workmen and materials, and failed to prosecute the work as required by the contract, and in consequence a resolution was passed by the committee on buildings of the board of education on the 29th of May, 1899, that the three-days notice be given to the plaintiffs to the effect that, if they did not make satisfactory progress and provide sufficient workmen and materials to prosecute, the work with promptness and diligence, in pursuance with the contract, then the board would declare the contract void, and would .enter upon the premises. This notice was served upon the plaintiffs in the manner provided in the contract, and it is alleged that they did not comply with it, and that thereupon they were advised that the contract was at an end. It is further alleged that, after the three-days notice had been given to
It is not denied that on the 29th of May, 1899, the board passed the resolution to give the three-days notice as provided for in the contract, and that that notice was given to O’Connor, one of the plaintiffs, on the 2d day of June. He was thereby advised that if he did not make satisfactory progress, and furnish the materials to com: píete the work, the board would enter upon the premises, and declaré the contract void and forfeited because of their noncompliance with its terms. It is conceded that on the 6th of June, four days after the notice was given to O’Connor, the board took possession of the work in pursuance of the authority which they had after the service of-the three-days notice. It is claimed by the plaintiffs that this notice was not justified, because the conditions warranting it did not then exist. It is not denied that the superintendent of school buildings determined that the contractors were not proceeding with the work in a proper manner, and that they were not employing sufficient men, and were not furnishing sufficient material, so that the work could be completed in accordance with the contract, and on the 29th of May so reported to- the committee on buildings. It might be enough to say with respect to this matter that by the terms of the contract the superintendent was made the final arbiter as to the proper execution of it, and, when he decided that the plaintiffs were not proceeding with its execution in the manner prescribed, his decision, in the absence of fraud or plain and palpable mistake, is conclusive, and no further question can be made about it. It is not claimed that there is any fraud on the part of the superintendent, although some testimony was given by reason of which the plaintiffs claim that as a matter of fact the superintendent was mistaken in his conclusion that the plaintiffs were not proceeding with the work properly, in time incomplete it within the time prescribed. But this evidence does not warrant any such conclusion. By the terms of the contract, it waa expressly required that the plaintiffs should begin the work forthwith upon its execution. It was in fact executed on the 20th of December,, 1898, and it is conceded that they began work on the 24th of January, 1899. No point seems to have been made by the defendants that the work was not begun immediately after the 20th of December, but they seem to have been willing that the time for the completion of the contract should run from the 24th of January, instead of from the
It is said that the defendants had no right to rely upon this determination, because Mr. Snyder, the superintendent, had delegated the duty of inspection and determination to someone else. But that is not true. It is quite true that he himself, as he admits, did not per-" sonally inspect the work from day to day, but he had been kept informed by his inspectors as to the condition of the work, and there is no dispute that the inspectors told him all about it; so, although he did not get his information first hand, he did have accurate knowledge, which enabled him to decide correctly as to the matters submitted to him. It is to be assumed that there was no mistake in the conclusion reached by Mr. Snyder, and that, as his determination was made by the contract concltisive upon the plaintiffs, they were bound by it. The sureties also were bound by that determination. They were parties to the contract. It was expressly provided by the clause in question that the three-days notice should be given to the parties of the second part, who were Jones and O’Connor, the contractors, and it is conceded that the notice was actually given to O’Connor in the manner prescribed in the contract. The express agreement of the sureties was that, whenever that notice should be given, the contract should be void, as to themselves as well as to the contractors. So, as to all these matters, they occupied no better position than did the contractors themselves, and the contract was void as to them, as it was to the contractors.
The only question, then, remaining, is whether the offer by the board of education to the contractors that they might go on and com
We have examined the exceptions taken to the rulings upon the admission of testimony, and only one of them requires particular mention. The new contractor was asked whether, in his judgment, it was possible for the plaintiffs to have completed the contract in what remained of their 300 days allowed to them for it. That evidence was admitted over the plaintiffs’ objection. We agree with the plaintiffs that it was not competent testimony, but it was not of the slightest importance. The .only question was what conclusion had been reached by Mr. Snyder upon that" matter, and what were the facts upon which he based his conclusion. The judgment of any other person Was not material, because the parties had agreed to be bound by the decision of Mr. Snyder.
We find no other point requiring consideration, and upon the whole case we are clear that the judgment was correct, and it should be affirmed, with costs. All concur.