Majority
Headnote
Municipal Contracts—Board of Estimate—Finding—Interest.Between June 22, 1888, and December 22, 1889, the plaintiff’s intestate, under a contract between him and Long Island City, cleaned the streets and sewers of, and removed the ashes and garbage from, the First ward of Long Island City. The amount due the contractor for the said services ($3,862.50) was audited and allowed by the common council of that municipality, but no payment was made for said services. In 1900 the legislature passed an act (Laws 1900, c. 678) providing for the payment of the said claim. The statute authorized the board of estimate and apportionment of the city of New York, in its discretion, to inquire into the facts relative to the justness of the contractor’s claim, as a matter of fact, against the city of New York for the performance of the aforesaid services, and if it should appear to said board that the services were actually performed, and were actually ordered, directed, or contracted for by the common council of Long Island
The question, therefore, is from what date the plaintiff is entitled to interest on the sum certified by the board of estimate and apportionment, and the answer depends upon the intent of the legislature as manifested in the statute referred to. Prom a careful reading of the statute, it would seem that the legislature intended that, in the event of the board of estimate and apportionment certifying for the payment of any sum for services performed by the contractor, such sum should represent what the fair and reasonable value of said services was at the time they were performed, and-that the comptroller should pay the same, “together with interest on the aggregate sum so certified.” The statute uses the word “was” in connection with the value of the services, and the fact that the board certifies that such rmlue “is” $3,862.50 is scarcely sufficient to show that the board disregarded the legislative mandate, and certified a sum which was the reasonable value of the contractor’s services when the said board acted in the matter, instead of the value of such services at the time they were performed. It must be assumed that the board complied with the directions of the statute, and certified what the services were worth at the time of their performance. It cannot be that the board allowed interest-on the demand; for, by the legislative enactment, it had nothing whatever to do with the subject of interest. The board was merely
It follows that the demurrer to the defendant’s answer must be sustained, but instead of calculating interest from an average date, as the plaintiff has assumed to do, it must be computed from December 22, 1889, when the contractor’s services, as certified by the board of estimate and apportionment, amounted to $3,862.50.
Cases cited
- De Lavallette v. Wendt 75 N. Y. 579 p. 93
- Wilson v. City of Troy 135 N. Y. 96 at 104, 32 p. 93
- Fifth Avenue Bank v. Colgate 120 N. Y. 381 at 394, 24 p. 93