← Cases

Signell v. Wallace

72 N.Y.S. 348 Court N.Y. Sup. Ct. English

Delivered by O’GORMAN, J.

Contents

Majority

p. 348
(38 Misc. Rep. 656.)
SIGNELL v. WALLACE, Commissioner of Buildings (five cases).
(Supreme Court, Special Term, New York County.
August, 1901.)

Headnote

1. Constitutional Law—Police Power—Tenement House Act.
Laws 1901, c. 334, § 4, known as the “New Tenement House Act,” as-amended by Laws 1901, c. 555, providing that in cities of the first class an incomplete tenement house, which was constructed under plans complying with the law existing at the time the plans had been filed with the city department of buildings, and which plans had been filed before April 10, 1901, and for which excavations had been begun before June-1, 1901, after such plans had been approved, and which was built in accordance with the law existing at the time such plans were filed, should be subject to such provisions only of the new statute as affected tenement houses existing at the time of its passage, is constitutional, as a valid exercise of the police power.
2. Same—Unreasonable Provisions. •
The provision in the Tenement House Act (Laws 1601, c. 334) § 4, as-amended, requiring that the first tier of beams of a tenement house built on plans approved on or before April 10, 1901, must have been set on. or before August 1, 1901, is unreasonable and invalid.
Action by John V'. Signell against James G. Wallace, commissioner of buildings, to continue temporary injunctions restraining defendant from interfering with the construction of certain buildings by plaintiff.
Motions granted.
Wechsler & Burstein, for plaintiff.
John Whalen, Corp. Counsel (Samuel J. Parmenter and Charles J. McCafferty, of counsel), for defendant.

Section 4 of the new tenement house act (Laws 1901, c. 334), which became a law on April 12, 1901, declared that tenement houses upon which work had been actually commenced after approval of the plans by the department of buildings should be subject only to the provisions affecting existing tenement houses. It will be noticed that this section offered no protection to persons who had already filed plans which were awaiting examination and approval on the day the new law went into effect. In an at

p. 349
tempt to remedy this omission it is claimed the legislature exceeded its powers in passing on April 125, 1901, an amendment (chapter 555, Laws 1901) to section 4 so that the same reads as follows:
“Buildings in Process o£ Erection.—Section 4.—A tenement house not now completed, but the excavation for which shall have been commenced in good faith on or before the 1st day of June, 1901, after approval of the plans therefor by the department of buildings, and the first tier of beams of which shall have been set on or before the 1st day of August, 1901, shall be subject only to the provisions of this act affecting now existing tenement houses: provided that the plans for the said houses were filed in said department on or before the 10th day of April, 1901, and were in accordance with the laws in force at the time of filing, and that the building is built in accordance with such laws.”

In the five cases before the court it is conceded that the work was commenced in good faith before June 1, 1901. In none of the cases, however, was the first tier of beams completely set by August 1, 1901, and this situation was due to strikes and other causes beyond the control of the builders. The plaintiffs insist that this requirement touching the setting of the first tier of beams before August 1, 1901, was an oppressive and unreasonable enactment, and therefore invalid. This provision must be upheld, if at all, as an exercise of the police powers of the state; but these powers have certain limitations, and cannot be used arbitrarily without regard to private rights. Enactments made in the exercise of this power must be reasonable, and tend in some plain and appreciable manner towards the accomplishment of the objects which the legislature has the right to protect under the exercise of this power. Where the exaction is excessive, unfair, oppressive, and unreasonable, and under the forms of law confiscates private property, the constitutional rights of the citizen are invaded, and the act will be condemned by the courts. The requirement in the amended act that work be commenced in good faith before June 1, 1901, in order to secure for the builders the benefits of the act relating to existing tenements is a valid exercise of the police power, but the provision arbitrarily requiring that the first tier of beams be set by August 1, 1901, must be pronounced invalid. It was certainly as unreasonable as it was an" unnecessary means of attaining the main object of the act. It had no direct tendency towards the accomplishment of the main purpose of the legislation. If the work was begun in good faith by June 1, 1901,—and that it was is conceded,—the public welfare was sufficiently safeguarded, and there is no reason for the imposition of penalties for not progressing with the work by arbitrary stages. It is claimed, and not disputed, that these plaintiffs will lose large sums of money if they should now be required to make the changes necessary to conform to the laws now in force. The new tenement house act makes radical changes in the nature, method, style, and class of materials, and in the Signell building it is averred, and not denied, that, if compelled to change the building to conform to the laws now in force, upwards of $70,000 worth of work actually done and materials furnished will be rendered absolutely useless, to say nothing of the liability incurred by the owner in other contracts. The same is sub

p. 350
stantially true of all the plaintiffs. If the legislature had the right to impose such a restriction upon the builders, it might, with equal propriety, declare that the second or third tier should be completed by a specified date. The Signell case offers a good illustration of the unreasonable features of this provision. Signell’s plans were actually approved and permit granted under the old law on April 8, 1901, four days before the new act became a law. He is building a row of houses on Central Park West, from Ninetieth to Ninety-First street. The first tier of beams has been laid to the extent of about one-half of the block, but, owing to the nondelivery of iron material, the setting of the other half of the first tier was not completed by August 1, 1901. Although delayed in this respect, he has made other progress in the work, so that the walls were up to almost the second tier, and the entire job much further advanced than if the first tier had been completely set. To enforce such a law under such circumstances, with such disastrous consequences to the citizen, would be an act of spoliation under judicial sanction. Motions to continue the temporary injunctions pendente lite are granted. •

Motions granted.