Majority
Headnote
Reference—Contempt Proceedings—Admitted Facts.This proceeding was to punish one Luke Healy for contempt in having executed and justified upon a bond given to procure the discharge of a mechanic’s lien, filed by the petitioners upon certain premises in the city of New York. The petition upon which the application was based alleges that the petitioners had filed a mechanic’s lien for $489 against Thomas McKeone, as owner and contractor, upon premises No. 16 East Seventeenth street, city of New York; that thereafter a proposed bond executed by the said Thomas McKeone as principal, and by Luke Healy and William W. Vaughan as sureties, to discharge the said lien, was served upon the plaintiffs, with a notice that the said sureties would justify before one of the justices of the supreme court at a time and place named; that the sureties justified before the justice, the justification of Healy being annexed to the petition, and that upon such justification the bond was approved by the justice, and an order entered canceling the lien; that thereafter an action was brought to foreclose the lien, and to obtain judgment against the principal and the sureties upon the bond given to discharge the same for the amount due thereon, which action resulted in a recovery of a judgment for $381.28, the amount due upon the said lien, with interest and costs, on the 7th day of March, 1901; that an execution against Healy was issued, which was subsequently returned wholly unsatisfied; that the said Healy and his wife were thereupon examined in supplementary proceedings under the said judgment, such examination having been reduced to writing and annexed to the petition; and it was upon this petition and these examinations that the motion to punish Healy was based. In answer to the motion, the affidavits of Healy and his wife were submitted to the court, but these affidavits do not contradict any material fact upon which the application was made.
There does not seem, therefore, to be a serious dispute as to the facts, and the question for the court to determine was whether or not Healy was guilty of contempt in executing the undertaking and justifying as a surety thereon. The court, instead of determining
It follows that the order appealed from must be reversed, with $10 costs and disbursements, and the motion remitted to the special term for decision. All concur.
Cases cited
- Bucholtz v. Florida East Coast Railway Co. 59 App. Div. 566 p. 434
- Wienberger v. Metropolitan Traction Co. 63 App. Div. 240 p. 434