Majority
Headnote
1. Bill of Particulars—Repetition—Unnecessary Detail.The action was brought to foreclose a mechanic’s lien upon the defendants’ premises for which the plaintiff had furnished terra cotta work. The answer denied that he had', properly performed the contract, and, by way of counterclaim, averred that much of the terra cotta work was not of the proper kind, or quality, to the defendants’ damage $1,500; that it was not supplied within the time required, and the building was therefore delayed until after the renting season, the resulting loss to the defendants being $15,000; that by reason of such delay they were obliged to cancel contracts with masons, and themselves complete the work, at an extra cost of $1,800; and that they were obliged to retain superintendents, watchmen, and other employes, and “were otherwise further damaged in the sum of $1,900.” The plaintiff asked for a bill of particulars of the counterclaim, and the court, with some slight modifications, granted it as requested, and from the order so entered the defendants appeal.
The first paragraph of the bill of particulars refers to the al
The two following paragraphs of the bill of particulars refer to alleged loss of rents arising from delay on the part of the plaintiff. The claim of $15,000 is large, and is over twice the amount for which the action is brought, and the plaintiff is entitled to ample information, the subject being more peculiarly within the defendants’ knowledge. These paragraphs, therefore, should stand, with the exception that subdivisions “e” and “f” of the paragraph numbered 5, requiring the dates of applications for apartments and the items claimed as loss of rents should be stricken out; for the subject is sufficiently covered by the subdivisions “a,” “b,” and “c” of this paragraph.
With respect to the paragraph numbered 6, which relates to the alleged loss because of the cancellation of contracts with masons, we think it is not necessary that the names and addresses of the masons referred to be given; it being sufficient if instead the defendants specify what contracts they were obliged to cancel. So, too, in paragraph 7, with regard to the names and addresses of the persons alleged to have been paid for extra work owing to the delay in the work, we think it is sufficient that the defendants state the number of superintendents, watchmen, and other employes, tfte length of the aggregate employment, and the aggregate amount of compensation paid.
Finally, we think that the paragraph numbered 9, calling for items making up the alleged loss of $1,900, should be omitted, as it is covered by paragraphs 7 and 8.
As modified in the respects indicated, the order allowing the bill of particulars should be affirmed, without costs.