Majority
Headnote
1. Liquidated Damages or Penalty—Contracts—Construction.The learned referee before whom this case was tried has well stated in his opinion the rule of law prevailing in the state of New York as to stipulations in contracts being for liquidated damages or for penalties. So much has been written upon the general subject of liquidated damages that it is unnecessary to multiply words concerning it. The leading cases in the state of New York are referred to by the referee in his opinion, namely, Cotheal v. Talmage, 9 N. Y. 554 , 61 Am. Dec. 716 ; Clement v. Cash, 21 N. Y. 258 ; Kemp v. Ice Co., 69 N. Y. 57 ; Ward v. Building Co., 125 N. Y. 235 , 26 N. E. 256 ; Curtis v. Van Bergh, 161 N. Y. 52 , 55 N. E. 398 ; Little v. Banks, 85 N. Y. 265 . The rule deducible from all the cases is that, where it is ascertainable from the terms of an agreement, construed in the light of the surrounding circumstances under which it was made, that a sum of money is agreed upon by the parties as the measure of damage which will be sustained by the nonperformance of that agreement, and the sum thus agreed upon under the circumstances is not so excessive as to shock the moral sense, courts will hold the parties to their agreement, and keep them bound by their contract. “Liquidated damages” is in one sense a mere phrase, but in another it has a very substantial meaning. When damages that may arise, but are incapable of legal proof, are agreed upon, the parties themselves come into accord as to compensation to be paid for a breach. Of course, if no damage is sustained, the provision of a contract for liquidated damages will be regarded as a penalty. That damage or injury must result from the breach is a necessary factor in the problem. In the case before us it is evident that time was of the essence of the contract. The testimony is very direct to the effect that, if the rock had been removed from the defendant’s property in accordance with the terms of the contract, that property would have been marketable, and might have been sold to the great profit of the defendant. By reason of the neglect or delay of the plaintiff in completing the work of removing the rock, the defendant lost his market; at least, that is the fair inference from the whole testimony. That time was an important factor in this contract is
The judgment should be modified so that it shall provide that the plaintiff recover of the defendant the sum of $6,050.54, less the defendant’s adjusted costs, to which he is entitled by reason of his offer to allow the plaintiff to take judgment for a larger sum than that now found to be due him, and, as thus modified, the judgment ■should be affirmed, without costs in this court. All concur.