Majority
Headnote
1. Railroads — Crossings—Commissioners—Temporary Crossing — Statutes.This proceeding was commenced on the 27th day of June, 1902, by the service of respondent’s petition for the purpose of having appointed commissioners pursuant tp section 12 of the railroad law, to determine the amount of compensation to be paid by the respondent to the appellants for a crossing of their railroad in the town of Portville, in the county of Cattaraugus, and to determine the line or lines, grade or grades, and point or manner of intersection of one railroad by the other. The appellants duly filed an answer to the petition, putting in issue the material allegations thereof, and such issues were, by order of the court, duly referred to a referee for trial and determination, and are as yet undetermined by such referee. Thereafter, and on the 10th day of July, 1902, the respondent applied to the special term for an order permitting it temporarily to lay its tracks across the tracks of the appellants’ railroad at a highway in the town of Portville, in the county of Cattaraugus, which application was based upon chapter 239 of the Laws of 1893. The respondent’s application was granted, and the order appealed from made, which permitted such temporary crossing. There can be no question but that the order, so far as it involved the discretion of the court below, fully protected the risrhts of the appellants and of the public. The onlv
It is insisted that chapter 754 of the Laws of 1897, as amended by chapter 739 of the Laws of 19.00, repealed chapter 239 of the Laws of 1893, which is the only authority for making the order in question. Chapter 754 of the Laws of 1897, as amended, provides:
“All steam railroads hereafter constructed across the tracks of any other railroad, and any street surface railroad hereafter constructed across a steam railroad, shall be above, below or at grade of such existing railroad as the board of railroad commissioners shall determine, and such board shall in such determination fix the proportion of expense of such crossing to be paid by each railroad.”
The contention of the respondent is that this section ousted the supreme court of jurisdiction to provide for even a temporary crossing by one railroad of another under section 1 of chapter 239 of the Laws of 1893. In other words, that all questions relating to the physical crossing of one road by another were placed wholly within the power and jurisdiction of the railroad commissioners. It is apparent that section 12 of the railroad law was not wholly repealed by the section quoted, because under that section the commissioners appointed as therein provided are to determine the amount of compensation to be paid by the railroad company seeking the crossing, and they are also to determine the point of crossing. By the express provisions of chapter 754 of the Laws of 1897, as amended, the board of railroad commissioners has no power or authority to determine those questions. It would seem quite plain that it was not the intention of the legislature to repeal section 1 of chapter 239 of the Laws of 1893. That provision was enacted for the purpose of avoiding the inconvenience, and often hardship, which would frequently result from long delays incident to the final determination by the commissioners of the issues submitted to them under section 12 of the railroad law; and chapter 754 of the Laws of 1897,' as amended, would in no manner tend to prevent such delays, and thus avoid the necessity of the statute. Even if the manner of crossing, whether above, below, or at grade, should be finally determined by the board of railroad commissioners to the satisfaction of both railroads, the company seeking to acquire the right to cross the railroad of another company would not necessarily have any right so to do, because the question of compensation might yet be undetermined, and the only manner in which that question could be determined is pursuant to the provisions of section 12 of the railroad law, and the final determination of that question might easily involve quite as great delay as the question of the manner of crossing. As we have seen, chapter 239 of the Laws of 1893 was apparently enacted for the very purpose of avoiding such delays. Chapter 754 of the Laws of 1897, as amended by chapter 739 of the Laws of 1900, clearly has reference to a permanent crossing of one railroad by another, and the commissioners appointed by the supreme court under section 12 of the railroad law have now no jurisdiction over that question, but they still have jurisdiction and are the only tribunal which has the power to determine the
The board of railroad commissioners have the exclusive power and authority to determine the manner in which the permanent crossing of one railroad by another shall be made or constructed. The point at which such crossing shall be made, and the compensation which shall be paid by the company seeking such crossing, is still, as before, to be determined by commissioners appointed by the supreme court; and pending the determination of such commissioners the supreme court still has the power to authorize, under proper conditions, a temporary crossing. When such commissioners shall have determined the point of crossing and the compensation which must be paid by the company seeking the right, then it must be constructed in accordance with the determination of the board of railroad commissioners, and without reference to the method of constructing the temporary crossing under the direction and in accordance with the permission granted by the supreme court. It seems to us that the orderly and natural course of procedure in a case of this kind is to apply for the appointment of commissioners to determine the location of the proposed crossing, and the compensation to be paid therefor, pursuant to the provisions of section 12 of the railroad law, and then to make application to the board of railroad commissioners, under chapter 754 of the Laws of 1897, as amended, for their determination as to the character of the crossing to be constructed; for manifestly the location, lines, or angles of approaching the point of proposed crossing would materially affect, if not be controlling in, the proper decision of the question as to whether the crossing should be above, below, or at grade. Pending the determination of either or both of these proceedings, and to avoid the delay incident thereto, an application may properly be made to the special term of the supreme court for permission to lay and construct a temporary, crossing, pursuant
Order affirmed, with $10 costs and disbursements. All concur.