Majority
Headnote
1. Rapid Transit Commission — Equipment—Liability op Contractor.This is an application for a writ .of mandamus requiring the comptroller of the city of New York to pay a voucher for $400,000 issued by the rapid transit commission to the contractor for extra work for placing ducts in the tunnel. Under the contract for the construction of the underground rapid transit railway, the city is to bear the cost of construction, and the contractor is to take a lease of the road at a stipulated rental, and bear the cost of its equipment and maintenance. The contract provides that the motive power shall be electricity or compressed air, which shall be so used as to involve no combustion in the tunnels, or any injury to the purity of the air in the tunnels. It further provides that the contractor’s plans and methods of equipment are subject to the approval of the board of rapid transit commissioners. In compliance with this latter provision, the contractor proposed to the rapid transit commissioners that electricity, and not compressed air, be adopted as the motive power; that the power be delivered to the trains through a third rail, or equivalent conductor; “and that the current should be carried in conduits placed in suitable chambers in the side walls of the subway.” The board approved this plan by the following resolution:
“Resolved, that the adoption by John B. McDonald, contractor, of electricity for the motive power for the rapid transit railroad in the boroughs of Manhattan and the Bronx, now under construction, be, and the same hereby is, approved; that the conduits for such electricity may be placed in ducts in the side walls of the tunnel, subject, however, to the approval of the plans therefor by the chief engineer; and that the electrical conduits may be installed in such ducts, but subject to plans to be approved by the chief engineer: but provided, however, that the cost of such conduits and installation be borne by the contractor, as part of the cost of construction under the contract between him and the city.”
The contractor protested against the final part of this resolution, and renewed his request previously made that the “additional cost made necessary by the construction of the vitrified ducts or conduits in the tunnel walls, and the expense of additional excavation required by such change,” should be paid for as extra work. Thereafter the board, by a majority vote, determined that the additional portion of the tunnel constructed for electrical cables, and including the mason-work chambers in which the cables are laid, is part of the road, and not part of the equipment, and should be regarded as extra work in the construction. This action of the rapid transit commissioners cannot be upheld. While acting within the authority delegated to them, their action will not be interfered with; but, where it is claimed they have gone beyond the scope of their authority, their conduct will be reviewed by the courts. Concededly, under the statute, the commissioners have no right or power to designate as work of construction what the legislature has declared to be equipment. The counsel for the petitioner upon the argument
Application for a mandamus denied.
Cases cited
- In re Board of Rapid Transit Railroad Com'rs. 5 App. Div. 290 p. 760