Majority
Headnote
L Contract—Breach—Damages—Liability or Surety.Price & Garrison contracted with plaintiff to furnish it certain, granite at specified prices for the construction of the tower and anchorage foundations of the Brooklyn end of the new East River bridge, which plaintiff was under contract with the city to build. The defendant guarantied to plaintiff the performance by Price & Garrison of their contract. Price & Garrison failed to perform. Plaintiff procured the granite elsewhere, and now brings an action against defendant on its bond to recover the difference between what it actually paid for the granite and what it would have been required to pay to Price & Garrison under their contract if they had performed. Plaintiff had a verdict, and a question of law was reserved as to whether interest should be added to the amount found due by the verdict from the date of demand. Defendant claims that, as the damages were unliquidated, and as the granite had no market value, interest is only recoverable from the time of the judgment. It seems to be the settled rule in this state that in an action to recover unliquidated damages for a breach of a contract interest is not allowable unless there is an established market value of the property, or means accessible to the party sought to be charged of ascertaining by computation or otherwise the amount to which the plaintiff is entitled. Sloan v. Baird, 162 N. Y. 327 , 56 N. E. 752 ; Gray v. Central R. R. Co. of N. J., 157 N. Y. 483 , 52 N. E. 555 . I have examined the cases cited on defendant’s brief in support of the claim that, applying this rule to the case at bar, interest is not recoverable. There is a marked difference in the facts. In each of those cases there was a breach of an executory contract, and the damages sought to be recovered were really unliquidated and unascertained. They were in the nature of loss of prospective profits. In the case at bar a clause of the original contract between Price & Garrison and plaintiff provided:
“Should the parties of the second part (Price & Garrison) fail to promptly deliver granite stone as needed by the party of the first part, and as required hereunder, the party of .the first part may procure any required stone elsewhere, and, in the event that the cost of the stone procured shall exceed the price herein named, the excess so paid shall be paid by the parties of the second part.”
When Price & Garrison failed to deliver, and when they notified plaintiff that they would not and could not perform, plaintiff obtained bids from a number of granite dealers, notified defendant of Price & Garrison’s default, asked it if it desired to furnish the stone, submitted the bids it had received, offered any information required, and then accepted the lowest bid offered, and now seeks to recover
“When the defendant refused to perform its contract, the plaintiffs could have brought an action against it to recover the contract price of the vessel, in which case a recovery by them would carry interest. Or they could have sold the vessel for the account of the defendant, and have brought an action to recover the difference between the amount realized upon the sale and the contract price, in which case a recovery would also carry interest.”
If, under such circumstances, a breach and a sale for defendant’s account would carry interest, certainly a purchase for defendant’s account must. This is not an action for loss of prospective profits, but to recover the actual loss of the difference between the contract price and the cost of supplying the deficiency. The verdict has established the damage at the amount sued for, and that the price paid was fair and reasonable, and that plaintiff used all' the efforts that a reasonably prudent man would to get the stone at the lowest price he could to make the loss as small as possible. Defendant had due notice and full opportunity to ascertain the amount. Plaintiff is entitled to the interest from the time of demand, to be added to the verdict. Settle the amount and order upon notice. Extra allowance 3per cent.
■ Judgment accordingly.
Cases cited
- Sloan v. Baird 162 N. Y. 327 p. 945
- Gray v. Central Railroad 157 N. Y. 483 p. 945, p. 946