Majority
Headnote
1. Mechanics’ Liens — Filing—Validity.This is an action to foreclose a mechanic’s lien for work, labor, and services performed on premises known as No. 337 East Fifty-Seventh street, owned by the defendant. The lien is based upon a contract in paroi, by which the owner employed the plaintiff to make changes and alterations in the building then on the premises upon a io per cent, basis; that is, the plaintiff was to purchase the materials and procure the labor, and the defendant was to advance the necessary money therefor to pay the plaintiff for his services in supervising the work and paying the bills an amount equal to io per cent, of the aggregate cost of materials and labor. The court evidently dismissed the complaint upon the theory that the lien was not filed within the time prescribed by the statute. The lien was filed on the 16th day of November, 1900. The last item of work performed by the plaintiff was on the 8th day of September, iqoo, and consisted in oiling the concrete on the top floor, the cost of which for labor and material was $8.86. The last work done prior to that time was on the 4th day of August, which was more than 90 days prior to filing the lien. The plaintiff gave evidence from which the trial court was justified in finding that his contract work was complete on the 4th day of August, and that the oiling of the floor was not part of the original contract work, but was work done at the suggestion of the defendant’s.wife. The court therefore was justified in finding that the lien was invalid, but this does not warrant the dismissal of the complaint.
In addition to demanding a foreclosure of the lien, the plaintiff, in his complaint, demanded personal judgment against the defendant for any deficiency. The Legislature, by section 3412 of the Code of Civil Procedure, has commanded that, even though the lien be invalid, the right to a personal judgment in such case shall be determined in the action; and we have held that this provision of law does not impair the defendant’s right to a jury trial. Hawkins v. Mapes-Reeves Construction Co., 82 App. Div. 72 , 81 N. Y. Supp. 794 . The defendant will now, of course, be entitled to a jury trial, if he desires it. In Hawkins v. Mapes-Reeves Construction Co., supra, we suggested two methods by which this may be secured: (1) By having the issues settled and tried by a jury in advance of the trial at Special Term; or (2) by trying the issue as to the validity of the lien at Special Term first, with the understanding that, if the lien be declared invalid, an interlocutory judgment to that effect will be granted, and sending the issues upon which the personal judgment depends to the Trial Term. Unless the defendant in such case secures or preserves his right to a jury trial in one of these methods, he will be
It follows, therefore,'that the judgment, should be reversed, and a new trial granted, with costs to appellant to abide the event. All concur, except VAN BRUNT, P. J., who dissents.
Cases cited
- Hawkins v. Mapes-Reeves Const. Co. 82 App. Div. 72 at 81 p. 397