Majority
Headnote
1. Wrongfully Flooding Land — Measure of Damage.So far as concerns the question whether the defendants had just reason for ceasing to fill the lot according to their contract, and were justified in backing up the water upon the plaintiff’s lot in the manner in which they did, the verdict of the jury is in the plaintiff’s favor. Upon the evidence in this case I conclude that their decision should not be disturbed.
But the serious question is, was the measure of damages upon which the plaintiff was allowed to recover the proper one to be adopted in this action? He was allowed to prove the difference in value between his lot as it then was and as it would have been had the defendants filled it in the manner required by their contract; and the jury were substantially instructed by the .court that such was the amount to which, if any, he was entitled. If the action is to be considered one for a trespass on the plaintiff’s lot by unlawfully flooding it with water, such would be the proper measure of his damages, unless the reasonable cost of repairing the injuries caused thereby was less than the diminution in the market value of the land. If it was less, then such cost of repairing would furnish the proper measure. Hartshorn v. Chaddock, 135 N. Y. 116 , 31 N. E. 997 , 17 L. R. A. 426 . And in this connection it appears that the trial judge permitted the defendants to show, if they desired, that the lot could have been filled at a less cost than the difference in its value appeared to be. He evidently adopted the theory that, under the peculiar features of this case, if filled as required by the contract, the injuries to the lot would be fully repaired, and in that respect I think he was correct. The defendants did not avail themselves of this offer; but, having been given the option of doing so, the proper measure of damages, assuming that the cause of action was for a trespass, was adopted by the court.
It is urged, however, by the defendants, that the action is for a breach of contract to fill up the lot; that the measure of damages for the breach of an agreement to perform certain specified work is the amount which it would reasonably cost to complete the work; and that such is the rule that should have been applied to this case. But it seems to me that the facts upon which the cause of action in this case is based is not upon the breach of any provision on the defendants’ part, but rather upon their unlawful act in flooding the plaintiff’s lot. The so-called “contract” amounts to no more than a permission on the plaintiff’s part that the defendants may flood his lot, provided they will so fill it up that whatever water they set back upon it shall not work any injury to him. The defendants do not promise to fill at all events. They are to fill only so far as is necessary to protect against the flooding; and manifestly they acquire no right to flood until the filling has been done. Their flooding before they had protected against it by filling was as much a trespass as if the agreement had never been made. The plaintiff had given them no right to flood him until his lot was so protected, and so he need not and did not rely upon any promise on their part for his
No specific objection was taken that the opinion of a witness cannot be given upon a speculative state of facts; and no exception was taken to the charge of the court when the rule of damages was submitted to the jury.
I conclude that the judgment should be affirmed, with costs. All concur.
Cases cited
- Hartshorn v. Chaddock 135 N. Y. 116 p. 612