Majority
Headnote
1; Sale — Contract—Construction—Amount Seller may Deliver.The judgment and order should be affirmed, with costs.
The action was to recover the purchase price of stone delivered, and damages for refusal to accept other stone under a contract between the parties. The defendant, having entered into an agreement with other parties to construct the abutments and piers of the bridges, and to do other stone work upon the Terminal Railway of Buffalo, made the contract in question with the plaintiff August 2, 1897, wherein it was provided, among other things, as follows:
“Mr. Ready agrees to furnish and the J. L. Fulton Company agrees to buy not less than 5,000 and no more than 8,000 cubic yards of stone from Ready’s-quarries at Oil City at a price of §3.40 per cubic yard, f. o. b. cars Buffalo-W. N. Y. & P. R. R. delivery; and the stone to include all such stone as may be required for face stone, bridge seats, coping and backing. If more than-5.000 cubic yards are required three weeks’ notice is to be given for the extra amount. * * * The specifications for this work permit the use of stone from twelve to thirty inch courses and, it is agreed that stone is to be gotten out in as thick courses as possible under these specifications, as it is-the essence of this contract to gain this point. Stone is to be well quarried, squared as practicable and all face stone to have beds of at least one and one quarter times their rise. All stone to be acceptable to the engineer, and 4.000 pounds railroad weight shall constitute a cubic yard of stone and be the basis of payment”
Under this contract 2,668 cubic yards of stone were shipped, and then the defendant refused to receive any further stone, and stopped
The findings of the jury upon these two questions of fact were such" as to relieve the plaintiff from the claim that he had failed to comply with the terms of the contract, and to entitle him to recover the balance unpaid upon the stone delivered, and his damages for the refusal of the defendant to receive the remaining stone contracted for. They defeated defendant’s claim for dámages upon the stone delivered and undelivered, and its right to refuse the balance of the stone. The question remained, how many stone had the plaintiff a right to deliver under the contract, 8,000 cubic yards as claimed by him, or only 5,000 cubic yards as claimed by the defendant ? The court seemed in doubt as to the proper construction of the contract in this respect when the
The parol evidence given as bearing upon the construction to be given to the contract cannot be considered here, because it was disregarded by the trial court, and nothing was left to the jury upon this subject. The construction was based upon the language of the contract alone. We are of the opinion that the trial court correctly construed the contract. It evidently was intended to provide for the furnishing and purchase of all the stone required, that is, necessary, for the work to be done, the only limit being from 5,000 to 8,000 cubic yards. See Miller v. Leo, 35 App. Div. 589 , 55 N. Y. Supp. 165 , affirmed in 165 N. Y. 619 , 59 N. E. 1126 ; Brawley v. U. S., 96 U. S. 171 , 24 L. Ed. 622 . The plaintiff had a right to deliver, and the defendant to require delivery of, all the stone necessary within the limit specified. The notice required, if more than 5,000 cubic yards were required, was for the protection of the plaintiff. Defendant would know better than plaintiff what the requirements of the work would be as it progressed, and, having to deliver 5 to 10 car loads per day, the plaintiff required the notice so as to know how long he must provide for the continuous supply of stone. If the notice was not given, the defendant could not complain if the stone were not promptly delivered after the 5,000 cubic yards were shipped. The plaintiff had the right to deliver the stone required beyond the 5,000 cubic yards if the notice was not given, but could not be held to as strict delivery as if the notice were so given. We are unable to tell upon what theory the verdict of the jury was rendered. The amount claimed by the plaintiff for the balance unpaid upon the stone actually delivered, 2,668 cubic yards, was $3,840.56. The verdict was $5,977.40. The difference, $2,136.84, must have been allowed for damages for refusal to receive other stone. The plaintiff claimed such damage was $1 per cubic yard. At this rate the allowance of damages would have been upon 2,136.84 cubic yards of stone. This, added to the 2,668 cubic yards actually delivered, would make 4,804.84 cubic yards, or less than 5,000 cubic yards, the lower limit specified in the contract. The verdict in any event seems to have been a reasonable one, and much less than the plaintiff claimed, to wit, $9,172.76.
We conclude the judgment and order should be affirmed, with costs. All concur.
Cases cited
- Miller v. Leo 35 App. Div. 589 p. 629
- Brawley v. United States 24 L. Ed. 622 p. 629