Majority
Headnote
1. Contract—Rescission—Failure oe Other Party to Perform,The defendant, the owner of about 32,000 acres of land in the Adirondacks, with about 424,000 cords of pulp wood thereon, agreed to sell and deliver to the plaintiff at Water-town, N. Y., or an equivalent place, rossed pulp wood at $9 per cord, the delivery, from 11,000 to 12,000 cords per year, to begin the 1st day of June, 1900, and to continue for 10 years at the rate of about 1,200 cords per month for 10 months of each year, with the right to the plaintiff to continue said contract for 10 years more at $12 per cord. It was provided further that the defendant need not deliver more pulp wood than could be obtained from said lands, and it is excused in case it could not deliver on account of fire or condemnation by the state, and it was not to sell the land or wood to jeopardize or prevent its performance of said contract; and, further:
“Party of the second part [plaintiff] shall make such advance of money to the party of the first part [defendant] as it may request during the progress of the work, but party of the second part need not advance more than approximately the cost of work done. * * * It is further agreed that the said party of the second part shall be deemed to have an equitable interest in said pulp wood for advances made by them as hereinbefore provided.”
The defendant entered upon and continued in the performance of the contract until April 12, .1900, when it claimed to rescind the same on account of the plaintiff’s failure to make advances as agreed. Thereupon the plaintiff brings this action, alleging its performance and defendant’s refusal to perform, and that it had sold a part of the lands to the Brooklyn Cooperage Company, and asks specific performance, and that the defendant be enjoined from selling the land or the wood elsewhere. The Appellate Division ( 55 App. Div. 225 , 67 N. Y. Supp. 149 ) dissolved the injunction granted in this action upon three grounds: (1) That it was not probable that a court of equity would enforce a specific performance of the contract, as it was practically a sale of personal property. (2) That upon the papers it was doubtful if the plaintiff could recover at all, as' it must show that it was performing its contract fully, and, if there had been a substantial breach by it in making the advances as alleged by the defendant, that might furnish a good ground for rescission. (3) On account of the difficulty and danger of enforcing such and so indefinite covenants by injunction. The Court of Appeals ( 173 N. Y. 149 , 65 N. E. 967 ) reversed the decision of the lower courts, dismissing the complaint at the trial upon the first ground stated above,
The fair meaning of this contract with reference to the advances is that the defendant shall cut and handle this wood in a reasonable and proper manner, and that the actual cost of so doing shall be advanced from time to time by the plaintiff upon the defendant’s
The contract was practically agreed to in July, 1899, was dated August 29th, fixes about August 15th as the time to begin cutting for the next June delivery, was signed by the plaintiff September 28th, and was signed by the defendant and mailed to the plaintiff October 7th, at which time defendant requested an advance of $2,500 on account of the work theretofore done, which was paid. The defendant had in fact been cutting and skidding wood on this contract since about August 1st, as plaintiff knew, and the contract when signed related back to that time and embraced the wood so cut, and such was the intention of both the parties. The complaint alleges that
As a matter of fact, the plaintiff did not at any time advance the cost of the work as required by the defendant, or any fair approximation of the cost. October 7th, defendant properly requested an advance of $2,500 on account of the work therefor done, and suggested that it would make its requests about the 1st and 15th of each month. Receiving no reply, it repeated the request on the 17th, reported the amount of wood skidded, and that the advance asked was on account of the logs cut some time ago. The advance was paid October 18th. October 26th, defendant reported as skidded as of October 21st 4,482. cords, and that the weekly rate is about 600 cords, and requested an advance of $5,000 by November 1st. October 28th the plaintiff suggested that it would send its Mr. Smith to inspect and measure the wood, and would send a check when he reported. November 1st the defendant expressed satisfaction at Mr. Smith’s coming, but the delay in the advance was- causing it disappointment and great inconvenience, and trusted it would not be compelled to wait longer. November 8th the plaintiff reports that Mr. Smith finds 5,300 cords of wood put up, but it has not been in the habit of paying more than a dollar per cord; still it will hear what the defendant has to say; and then suggests that there is another matter which they desire to talk about, and asks the defendant to come to Watertown. November 9th the defendant repeats its request, and gives notice that it shall require an additional sum by November 15th. November 17th the defendant notifies plaintiff it is suffering for funds, and must have full payment if the contract is to continue, and urges the payment at once of the $5,000 asked for October 26th. December 4th the plaintiff remits $7,500, saying it had hoped before being obliged to make such advances to be able to settle some claim it had on account of some previous sale of timber land, and that it understands the defendant claims it has skidded 7,000 cords of pulp wood at a cost of $2 per cord; that it does not say that it has not cost that amount, but it knows the defendant will be willing to let it make an investigation. Defendant, December nth, acknowledges the check, repudiates the alleged claim on account of the timber lands, and says it will be glad to have the plaintiff send a proper person to investigate the work done. The plaintiff, December 18th, repeats that it is customary to advance only a dollar a cord, and that it will do no good to send a man to look the ground over, and, if the defendant is entitled to the advance, asks it to send an itemized statement showing the expenses, etc. The defendant, December 19th, reports 10,250 cords skidded, and requests $10,000. The plaintiff replies, December 20th, asking the defendant to show upon what ground further advances are claimed. The defendant, January 3d, submits a statement of the number of men and horses, the-wages paid, the product per week, and refers to the incidental expenses..
It is unnecessary to follow through the correspondence. After the contract, all the matters between the parties are in writing, and appear in the exhibits. The defendant was repeatedly asking for money, the plaintiff continually neglecting to pay the same, and offering the same excuses. There is no dispute as to the meaning of the contract, as its terms are not ambiguous, and the correspondence shows that the plaintiff did not question that the defendant was entitled to advances approximately to the cost of the work done; and, as we have seen, after the return of Mr. Smith from the woods upon his first visit, there was no honest misunderstanding on the part of the plaintiff as to the cost of the work done. When it proposed an arbitration it suggested that the arbitrators settle the matter upon the correspondence and contract at an intermediate point, showing that it was not desired that the arbitrators should examine the books or determine the amounts skidded, or the cost. It will not do to say that the plaintiff would not, for technical reasons, or to annoy the defendant, or to compel it to make an adjustment of outside matters, or to pay the interest upon moneys which it was legally entitled to without such payment, imperil a contract of the great value represented here. The acts of the parties must be viewed by the situation as it then was. The plaintiff was building a large pulp mill in which it intended to use this wood, but was delayed so that, instead of being ready for business in June, 1900, as expected, it was not ready until July, 1901, and pulp wood would suffer detriment if kept over, unless it remained in the water. In June, 1900, at Watertown, rossed pulp wood was worth only from $9 to $9.50 per cord, and this wood, the plaintiff advancing the cost during the progress of the work, would approximate the latter figure. So that at the time this correspondence was going on it is not easy to say that either party had the advantage over the other on account of the value of pulp wood at Watertown. But since the alleged rescission pulp wood has very rapidly increased in value, and each June has seen a very material advance in its price, so that the contract now, if in force, is of very great value.
We therefore find that the plaintiff did not make the advances as requested, approximately with the cost of the work, but with a
Two items entering into the above aggregate of cost of work done require further consideration: (1) The defendant has a New York office and a Tupper Lake office, and has charged to this job the salaries and expenses of this Tupper Lake office, amounting to $1,-635.03, for the eight months during which the contract was being performed. For four months of that time the defendant was performing some other work carried on through said office which practically occupied one-third of the time of the office force while in progress, allowing for which one-third, $272.96 should be deducted from the above aggregate. (2) The defendant also has charged to this job the bedding and certain tools and implements which were in camp from the year before, of the value of $2,197.98. While the property was worth the sum charged, it is claimed that at the most only the use of said property can be charged against this job. This may be so, but we must remember that the defendant was entering upon a contract for 10 years, and at plaintiff’s option for 20 years, and that the whole of this perishable property would be used up long before the 10 years, and much of it during the first year, and probably some of it at least was rendered valueless before the recission. It must also be' remembered that the camps and the roads which had been built the year before were turned into this job without price, and perhaps the advantage from these sou'rces may make .up any difference in value which the plaintiff
After the plaintiff had unreasonably neglected or refused the several proper requests of the defendant for advances, and the defendant had repeatedly, directly, and impliedly threatened to cease performing the contract for that reason, the plaintiff, with knowledge of the approximate cost of the work done, and with an understanding of the terms of the contract, suggested an arbitration. The defendant, through its attorney, Mr. Badger, consented, and, as a speedy means of arriving at a result, suggested that each party take its foreman and they select a third arbitrator, to which the plaintiff replied that it had named an arbitrator in a sealed envelope inclosed, requesting- the defendant to do the same, and that the arbitrators meet at an intermediate point and arbitrate the difference between the companies upon the contract and correspondence. The contents of the sealed envelope was “Gifford Penchot, or any one designated by him.” As he resided in Washington, D. C., it is not apparent what the plaintiff meant by an intermediate point. The defendant interprets the plaintiff’s consent to arbitrate as intending to bring in the old dispute about the timber land upon another contract referred to in some of the correspondence. The defendant had not the right to suggest an arbitrator for the plaintiff, and the plaintiff had not the right to suggest that the arbitrators proceed solely upon the letters and correspondence, and that they meet at an intermediate point, or that Mr. Penchot should select an arbitrator, or to leave the proposition so indefinite that it might fairly be construed as including other disputes, or that the arbitrators be agreed upon in sealed envelopes. Mr. Pursell and Mr. Badger, the counsel of .the respective parties, met and had some conference, the purport of which does not appear. But after the defendant had made new demands for money, the plaintiff again referred to the matter of arbitration, and Mr. Badger informed it that he supposed the conversation between Mr. Purcell and himself had avoided further discussion. Both Mr. Badger and the defendant thereafter demanded further advances. ' The plaintiff at different times, when requests were made for advances, referred to the matter of arbitration. Aside from these facts, there was no real attempt to arrive at an arbitration, and the attempt made by either party had no tendency to arrive at such a result. In fact there was no actual misunderstanding or dispute. The plaintiff was intending by discussing' the' matter of arbitration only to make further delay, or to bring in the other contract as a dispute for consideration, or to obtain some advantage other than the known rights of the parties under the agreement. The plaintiff, March 12th, writes that the proposed arbitration was as to the construction of the contract, and, April 13th, that it was as to the cost and the value of the work done. While a contract may provide for an arbitration for the ascertainment of- amounts
The plaintiff’s action proceeds entirely upon an allegation of full performance by it and a breach by the defendant. It seeks no relief from its own default, but is clearly in default'itself. Upon receiving the notice of rescission, the plaintiff offered to excuse the defendant for sending it, but did not offer to change its method of making advances, claimed it had made the advances .promptly as requested, and proposed to continue in the same way. It thus placed itself in a position of standing upon its full performance and the defendant’s default. It has taken the same position in the complaint in this action. The defendant entered upon the performance of the contract, and at all times was ready, able, willing, and desirous to carry out the same according to its terms, but was delayed and suffered great inconvenience and put to great expense on account of the default of the plaintiff in making the advances as agreed, and at the time of the last demand for payment and of the notice of rescission the defendant was able and ready to perform and carry out its contract with the plaintiff if the plaintiff had complied with its provisions, and the defendant was justified in electing to rescind the said contract, and did legally rescind it, having offered to return the money advanced, with the interest thereon, with its notice of rescission.
The contract having been recorded as affecting the title to real' estate, as it might do, according to the decision of the Court of Appeals in this case, if the defendant were in default, it is proper
Judgment for defendant, with costs.
Cases cited
- St. Regis Paper Co. v. Santa Clara Lumber Co. 173 N. Y. 149 p. 1035
- Miller v. Benjamin 142 N. Y. 613 p. 1036
- William Wharton, Jr., & Co. v. Winch 140 N. Y. 287 p. 1036
- Norrington v. Wright 115 U. S. 188 p. 1036
- Haggart v. Morgan 5 N. Y. 422 p. 1043
- National Contracting Co. v. Hudson River Water Power Co. 170 N. Y. 439 p. 1043
- Hamilton v. Liverpool, London & Globe Insurance 34 L. Ed. 419 p. 1043