Majority
Headnote
1. Municipal Corporations — Street Cleaning — Contracts — Offer and Acceptance.This action was to recover from the city of New York the amount due under a special contract for cleaning certain streets in the city of New York of snow during the winter of 1902. There are 10 separate causes of action, by each of which the plaintiff seeks to recover for services rendered under a special order by the commissioner of street cleaning of the alleged aggregate value of $5,317.95, of which there has been paid $2,245.78, leaving a balance of $3,072.17. The allegation as to the employment of the plaintiff in each of the causes of action is substantially the same, and is as follows: “That, pursuant to the power and authority vested in the said commissioner of street cleaning pursuant to the terms of the charter of the city of New York [Laws 1897, c. 378], he did hire, employ, and engage this plaintiff, its machines, horses, carts, and workmen, to remove the snow and ice from the said Astor Place and Eighth street, east side of Bowery, and on Fourth avenue south of Ninth street, and west side of Bowery, north of Fourth street, borough of Manhattan, city of New York”; that “reasonable value and the agreed price of the services so rendered by this plaintiff, as aforesaid, to this defendant and to the said commissioner of street cleaning of the city of New York on said 25th day of February, 1902, and the fair and reasonable value of the use of said machines, horses, carts, and workmen, was the sum” specified. The answer admits the employment, and denies the allegation that the reasonable "value and agreed price of the services rendered by the plaintiff was the amount named, or that the defendant agreed to pay to the plaintiff the • fair and reasonable value for the use of the machines, horses, carts, and workmen, or to pay for the same in any manner except as more specifically alleged; and then alleges as a defense to the several causes of action that the commissioner of street cleaning hired, engaged, and employed the plaintiff to remove the snow which lay in the streets of the city of New York referred to in the complaint, and that it was agreed between the parties that the area from which the snow was to be removed should be determined by actual measurement; that the snow fall as reported by the United States Weather Bureau, taken in connection with the area, less 70 per cent, to be deducted for shrinkage, should be the basis of the computation by which the amount of
The action was referred. The referee reported that the plaintiff was entitled to the sum of $2,924.68, with interest; that the commissioner of street cleaning employed the plaintiff to remove the snow and ice from certain public streets in the city of New York at the price of 36% cents per cubic yard, and pursuant to said employment the plaintiff removed 14,072 cubic yards of snow and ice from certain public streets and highways in said city of New York, which, at the agreed price of 36^4 cents per cubic yard, amounted to the sum of $5,170.46, on account of which the defendant has paid the plaintiff the sum of $2,245.78, leaving due the sum of $2,924.68; for which sum judgment was awarded against the defendant.
The employment of the plaintiff and the price being conceded, the only question at issue was as to the number of cubic yards of snow and ice that the plaintiff removed and for which it was entitled to be paid. The plaintiff based its right to recover upon the number of square yards of the street cleaned, multiplied by the depth of snow that fell, as testified by the officer from the weather bureau, making an allowance for shrinkage, based upon the testimony of Mr. Emory, an officer of the weather bureau. The allowance for shrinkage was the difference in the amount of snow on the ground on the day that the snow fell and that remaining on the night of the day following. Mr. Emory testified that it started to snow at 11 ¡45 p. m. on the night of February 16th, and it stopped falling at 8:59 p. m. of the 17th; that 9.3 inches of snow fell; that that was the amount of snow on the ground when the snow stopped; that he made an observation on the 18th of February at 8 p. m., as to how much snow there remained of what had fallen; that there was remaining on the 18th of February at 8 p. m. 8 inches; and the calculation of the plaintiff was based upon the amount of snow that remained at 8 p. m. on the 18th of February, multiplied by the number of square yards of street cleaned. The position taken by the defendant was that these, orders were given in- pursuance of an offer made by the plaintiff to the defendant to remove the snow upon certain terms- contained in a letter written to the street cleaning department on the 6th day of February, 1901. This letter, introduced in evidence by the defendant, was addressed to the commissioner of street cleaning, and was as follows:
' “We desire to undertake a contract to remove snow from suck section on the long-haul districts as might he designated by the street cleaning department at 36% per cu. yd. Quantity removed to be estimated by the snow fall as given by U. S. Weather Bureau, and taken in connection with the area cleaned. The allowance of shrinkage to be decided by your department. We are prepared to undertake this work following any snowfall that may occur during this year. [Signed] Snow Melting Co. F. H. Cowles.”
The referee held that this letter in question was not intended to be a binding contract, but merely a tender to be put in proper shape and form, if agreeable to the commissioner, as the basis of a general contract for the removal of snow for a term in a large section of the city; and that the determination by the commissioner was arbitrary and unfair, and not based upon proper facts. We are not able to agree with the learned referee as to either proposition. It is not disputed by the plaintiff but that Cowles, the writer of this letter, had charge of this matter on behalf of his company, and that on behalf of the company, with the authority of its officers, he entered into negotiations with the commissioner. It was said that he was not authorized to make a contract; but he was a vice president of the company, authorized to negotiate with the commissioner, and certainly he had authority to make a proposition to them upon which a contract should be based. He was informed that the amount of shrinkage based upon the records of the department was 70 or 75 per cent, of the amount of snow that fell, and with that knowledge he wrote and delivered a letter which expressly authorized the commissioner to determine the amount of shrinkage. That the commissioner required that such a letter should be written as a prerequisite to any order given is testified to by him, and is not disputed. That letter was certainly an offer of the plaintiff to remove the snow upon the terms mentioned. It was never withdrawn, and the commissioner certainly had a right to consider it an offer upon which he could base a contract with the plaintiff. It was an offer to remove the snow from such a section on the long-haul districts as might be designated by the department, and not from the whole city, as stated by the referee. It is established beyond question that the commissioner did give the order based upon this letter, and thát it was considered and understood by the department that when that order was given the department was accepting the offer contained in that letter, and the work was to be done under that offer. The president of the plaintiff, who received the offer, testified that when he asked what price they were to receive he was informed that it was the contract price, 36% cents. This contract could certainly be no other contract than one that was proposed by the representative of the plaintiff, and which the department accepted. The plaintiff certainly cannot be absolved from its offer because the vice president of the company had failed to communicate the offer that he had made on behalf of the plaintiff to the president, when the commissioner based the order to do the work upon the offer received. The amount, therefore, that the plaintiff was entitled to recover depended upon the contract made between the plaintiff and the depart
The referee, in his opinion, states that Cowles, the plaintiff’s vice president, who wrote the letter, contradicted the evidence offered by the defendant that prior to the letter of February 6th 70 per cent, was mentioned to him as the amount of shrinkage according to the experience of the department; but on turning to Cowles’ testimony it appeared that, instead of denying he expressly admits it, for Cowles testified: “I saw Mr. Clarke, I believe, a few days prior to the writing of this letter, defendant’s Exhibit 1. I never had any discussion with him whatever on the question of shrinkage. I remember Mr. Clarke told me that the department would deduct 70 per cent, as a gross shrinkage in the amount of snow removed. He did not make that statement to me regarding any deduction. He said that they had made deductions in figuring it out.” And the commissioner testifies that Cowles was informed before the letter was written that this deduction, 70 per cent., would be made. Under the contract which was accepted by the department the amount of shrinkage was to be determined by the commissioner. Seventy per cent, had been mentioned to- the party writing the letter on behalf of the plaintiff as the probable deduction that would be made. The commissioner, under the power which was granted to him by the offer made on behalf of the plaintiff, determined that 70 per cent, was a proper deduction. The question, then, was whether there was a fair and honest determination, reasonable in itself, and which bound the plaintiff. The referee seems to have considered that the method adopted by the department would be fair in arriving at a just conclusion as affecting the entire city, as he says:
“It seems clear and reasonable that such method should be adopted in making a contract for a large area and for a specified term; but it does not seem fair or reasonable to employ a party to remove snow in a certain limited area after a single storm, and then apply that rule, without regard to actual conditions of the location and the state of the weather.”
It is a little difficult to see the reasoning upon which this' conclusion is based. If it would be a fair rule to adopt in applying to the whole city, I do not see why it was not a fair rule to adopt as applying to a particular order. The portions of the city cleaned by the plaintiff were a part of the most thickly settled in the city of New York, and certainly the shrinkage would be as much there as anywhere; and it seems to me that the rule that the referee adopted, basing the shrinkage solely upon the report of the weather bureau and upon the shrinkage in the snow level in a park was quite unjust to the city, where the conditions were very different, and where, by the Use of the streets, the shrinkage would certainly be much greater. I do not think, therefore, that we can affirm the conclusion of the referee.