Majority
Headnote
1. Building Contracts—Partial Performance.This action was brought to foreclose a mechanic’s lien for work performed and materials furnished in erecting for defendants a building in the city of New York. The complaint alleged that the parties entered into a contract by Which the plaintiff agreed to do certain work and furni^Ji certain materials for the erection of a building for the defendants m the city of New York, and for which it was to receive the sum of $6,600; that the plaintiff duly performed all the terms and conditions of the contract upon its part, together with certain additions thereto authorized in writing, by which it was entitled to receive the further sum of $I55> and also that it performed extra work and furnished extra materials not specified in the contract or authorized in writing, by which it became entitled to receive the further sum of $1,100, making a total of $7,855, for which judgment was demanded. The answer admitted the making of
I think the judgment should be modified in so far as the defendants have appealed from it. The plaintiff sought to recover $7,855 and interest. It recovered only $4,755. In other words, the trial court held that the claim which it made against the defendants was invalid in upwards of 39 per cent. The claim of $1,100 for extra work was disallowed upon the merits, and, in addition thereto, the court found that the defendants were entitled to offset against the plaintiff’s claim the sum of $2,000 by reason of the defective way in which it performed the work specified in the contract and inexcusable delays in completing the same. The contract "price, it will be remembered, was $6,600, and the plaintiff predicated its right to recover upon full performance. The trial court found, and the evidence sustains the finding, that it did not fully perform; on the contrary, that nearly one-third of the value of the contract remained unperformed at the time the notice of lien was filed and the action commenced, and by reason thereof the defendants had been damaged to the extent of $2,000, which amount they could set off in reduction of plaintiff’s claim. Upon this state of facts the plaintiff was not entitled to recover. Mitchell v. Williams, 80 App. Div. 527 , 80 N. Y. Supp. 864 . In the case cited the contractor failed to perform one-seventh of the work specified in his contract. The trial court, after deducting such amount from the contract price by reason of defective materials furnished and delays in completing the work, gave judgment for the balance. On appeal the judgment was reversed, this court holding that, where there had been such a material part of the contract unperformed, a party could not recover upon an allegation of full performance. In the case now before us the trial court found that nearly one-third of the contract remained unperformed, and, had it followed the rule laid down in the case cited, the complaint would have been dismissed. This, however, was not done, and, inasmuch as there has been no appeal from any portion of the judgment except that allowing interest, the same must be affirmed, except so far as appealed from, and in that respect the judgment must be modified.
The plaintiff was not entitled to recover interest for another reason. The claim made by it was unliquidated, and was subject to a reduction, as the trial court found, of $3,100. This being the situation, the case fell directly within the rule laid down in Delafield v. Village of Westfield, 41 App. Div. 24 , 58 N. Y. Supp. 277 , affirmed 169 N. Y 582 , 62 N.
“In Delafield v. Village of Westfield, 41 App. Div. 24 [ 58 N. Y. Supp. 277 ], affirmed without opinion hy this court 169 N. Y. 582 [ 62 N. E. 1095 ], the plaintiff’s claim was on a quantum meruit for labor and materials furnished under a contract which had been broken by each party. The claim was subject to reduction for the damages caused the defendant by the plaintiff’s breach of contract and improper performance of his work. Defendant’s set-off was unliquidated, and the plaintiff’s recovery was necessarily dependent upon the amount of that set-off. Interest was therefore allowed to neither party.”
Here the plaintiff’s claim was subject to reduction for damages caused by its breach of contract. The amount of the set-off was unliquidated, and what the plaintiff was entitled to could not be ascertained until the amount of the set-off had been determined. Such amount was determined upon the trial to be $2,000, and in addition the claim made by the plaintiff was subject to a further reduction of $1,100 for extra work. It cannot be that one can be subjected to a liability for interest which depends upon a proper demand because he does not accede to an improper demand. The demand made by the plaintiff prior to the commencement of the action upon which the claim for interest has been allowed not only exceeded by $2,000 the amount due upon the contract, but it was also coupled with an illegal demand for $1,100 for extra work which had never been done, and for which, as already indicated, the court expressly found it was not entitled to recover anything. The contract did not in express terms provide for interest, and a demand was therefore necessary to set interest running, and it is well settled that when such demand is necessary it must be for the amount due, and, if it includes any item' not recoverable, the demand is illegal, and interest cannot be allowed.
The plaintiff was not entitled to recover for another reason, and that is because it did not produce the architect’s certificate entitling; it to payment. The contract provided that the payments were to be made upon the certificate of the architect. It is true the complaint alleges that the architect wrongfull)r withheld the certificate, but the findings made by the trial court show that this is not the fact. Plaintiff had not performed his part of the contract, and therefore was not entitled to be paid. Under a clause in a contract of this character the _ obtaining of the certificate is indispensable to a recovery. Weeks v. O’Brien, 141 N. Y. 199 , 36 N. E. 185 ; O’Brien v. Mayor, 139 N. Y. 543 , 35 N. E. 323 . Discussion is unnecessary to demonstrate that the architect was not unreasonable in refusing a certificate where the court finds, after an investigation, that the plaintiff had not performed its contract, and by reason thereof defendants-were entitled to an allowance by way of damages in nearly one-third of the entire contract price.
The judgment, so far as appealed from, therefore, must be modified by striking out the allowance for interest, and, as thus modified, by deducting the amount of interest allowed, but on appeal affirmed^ with costs to the appellants. All concur.
Cases cited
- Delafield v. Village of Westfield 41 App. Div. 24 at 58 p. 733, p. 734
- Sweeny v. City of New York 173 N. Y. 414 p. 734
- Cutter v. Mayor of New York 92 N. Y. 166 p. 735
- Weeks v. O'Brien 141 N. Y. 199 p. 735
- O'Brien v. Mayor of New York 139 N. Y. 543 p. 735