Majority
Headnote
1. Building Contract—Construction—Delay—Damages—Excuse.In the year 1895 the defendant was the owner of a large building, extending from Broadway to New street, in the borough of Manhattan. This building was known as 26 Broadway and 71 New street, and measured about 87 feet on Broadway and New street, by about 200 feet deep, and was 10 stories high. The defendant decided to put up 5 additional stories on the top of said building, and erect an extension on the north side thereof, about 27 by 60 feet deep, fronting on Broadway, 15 stories high, and a similar extension fronting on New street. It thus became necessary to build up the extensions from the ground to the level of the top of the old building, and then continue the construction for 5 stories more of the extension and old building together. The foundation of the old building rested upon piles, and, while there was a sufficient number of piles in the entire foundation of the old building to bear the weight of the additional stories, yet these piles were not so placed that the weight of the additional structure would be equally distributed upon them. In order to procure equality of sustaining power, and thus carry the additional weight, equalizing girders were placed upon the top of the old building, and the weight thus distributed over the whole foundation. It appeared upon the trial that the plaintiff on or about the 31st day of January, 1896, entered into a contract with the defendant for the construction of all the iron and steel work required in the building, and to furnish all the material necessary therefor. By the terms of this contract the plaintiff agreed that the work should be finished on or before the 15th day of June, 1896; and the contract contained a clause that for every day’s delay caused by the plaintiff in completing the work after the 15th day of June, 1896, he should forfeit $50 a day to July 1st following, and $100 a day for each day’s delay thereafter. A reciprocal clause was also provided, by which for every day’s delay caused by the defendant the plaintiff should be given an additional day in which to complete the contract, and that the plaintiff should not be liable for any delays caused by independent contractors under contract with, the defendant for the performance of other parts of the work. It was further provided in the contract that, in case there was any delay caused by the plaintiff in finishing his -\york, the defendant might deduct from the amount agreed to be paid'as the contract price, and as liquidated damages, any sum which might be due or owing to the plaintiff at the time of the completion of the work. The entire contract price of performing the work—not, however, including the extra work—was $234,000. It was admitted upon the trial that the contract was fully completed in every particular as required by its
In the disposition which we make of the case, it is not necessary that we enter upon a discussion of the evidence respecting particular delays as to particular parts of the work, the causes thereof, or who was to blame therefor. The contract was an entire contract for the performance of all of the structural iron work upon this building. Such being its character, it is evident that the plaintiff could not be chargeable for any delays, no matter from what reasons such delay arose, if he was prevented in finally completing his contract as to any particular part of the work, if such delay was occasioned by the acts of the defend
The construction, in accordance with the plans and specifications, required that there should be placed upon the front of the New street side of the building a particular kind of iron front, called “mullion.” This was the last work done under the plaintiff’s contract, and, when finished, substantially completed the same. It therefore became important under the rule which we have announced to determine the time when this mullion was set, and whether there was any interference by the defendant or its other contractors which prevented its setting at an earlier date. Upon this subject it appeared that a bridge had been constructed along this side of the building, principally for the masons engaged in the performance of work upon the building; its purpose being to protect passers-by upon the street, and also to serve as a runway for the various contractors in carrying material into the building. The runway was used for such purpose by all of the contractórs, including the plaintiff. The testimony, however, on the part of the plaintiff, authorized the jury to find that the plaintiff did not construct the bridge, nor was he responsible for its construction, and he was under no obligation to remove it; nor could it be removed, with safety to pedestrians upon the street, until work upon the building had been completed. It was recognized that it was no part of the plaintiff’s duty to remove this bridge, and it was subsequently removed by other contractors. The testimony showed that this removal did not take place until some time in January, 1898, and that within a few days after its removal the plaintiff set the mullion and completed his contract. It appeared without dispute that the mullion had been on hand, stored in the yard of the plaintiff, for over a year, awaiting an opportunity to put it in place. Whatever delay there was in respect to its setting, it cannot be said but that the jury allowed for such delay in finding the number of days’ delay for which the plaintiff was responsible. Giving force and effect to this testimony, it is evident that the jury were authorized to find that the plaintiff was prevented by the acts of independent contractors from completely performing his contract until some time in January, 1898. Therefore the jury were.
“We used the runway at both ends—we used the Broadway end and the New street end—until we got to the fourth or fifth tier, and then, when we got to the fourth tier, we used our boom derrick, and took things out from the street. Q. You didn’t require the runway after that? A. No. sir; we hoisted everything-. We took them direct ofE the trucks. Q. When did you get up to the fourth or fifth tier? A. It was in the summer of 1896.”
Other testimony is to the same effect. Longacre testified:
“There was an elevator on the east end of the New street section, which was inclosed with timbers from the bottom to the top, and it was used for hoisting up material. The engine that ran it just stood inside the building in this opening where we afterwards put in the mullion in front. That was used for carrying up the masons’ materials. Q. Used by whom? A. By the masons, plasterers, etc.; not by us. Q. How long did it remain there, if you know ? A. I cannot tell. Q. Well, you tell up to any time? A. Some time in the winter of 1897-1898.”
Other testimony shows that this obstruction was not removed until 1898, and that as soon as these obstacles were removed the plaintiff commenced setting the mullion, and finished it in a day or two after the obstacles were cleared away. It is clear, therefore, that the contention of the defendant in this respect cannot be upheld. The most that can be said in favor of the argument is that it presented a question of fact, but the testimony was abundant which authorized the jury to find that the contention which the defendant now makes was not supported by the facts as developed upon the trial. If we are right in our conclusion that the plaintiff could not be charged with any delays except such as arose after the time when he was permitted to set this mullion, it necessarily follows that the verdict-of the jury was fairly supported by the testimony, and that the learned court should have directed a verdict in favor of the plaintiff, in accordance with the finding.
A single exception and ruling upon the evidence is called to our attention. It consisted in the introduction of the timebook kept by the plaintiff and his agents. In view of the construction which we have placed upon the contract, the introduction of this book in evidence becomes of little importance, for the reason that upon practically undisputed proof, and quite independent of the book, the plaintiff established approximately the date of the final completion of the contract, and such date corresponds with that claimed by the defendant as to when the contract was completed. If, therefore, the admission of the book was technical error, it is not prejudicial, in the view we have taken of this case; but, in addition to this, we think the ruling which admitted the
Upon practically undisputed proof, we think the plaintiff became entitled to a judgment in accordance with the verdict of the jury, and that it was therefore error for the court to set the verdict aside. The order vacating and setting aside the special verdict rendered by the jury should therefore be reversed, and judgment should be directed to be entered upon the verdict in favor of the plaintiff, with interest and costs. All concur.