Majority
Headnote
1. Contracts—Installment of Elevator—Time as Essence—Waiver—Effect on Counterclaim.The plaintiff contracted with the defendant Varick Realty Company to furnish and install, in a building owned by said defendant, two electric elevators. One of the elevators was to be in operation by February 2, 1903; the installation of the other to be completed as quickly as possible after the installation of ,the first-; 10 days, being mentioned as the probable time. It is made clear by the evidence that much stress was laid by defendant upon the necessity of having at least one elevator in running order by February 2d, and that plaintiff was distinctly notified that no contract would be made which did not definitely state the daté for the complete installation of at least one of the elevators. There can be no doubt that it was thoroughly understood by both parties that the timely- installation of at least one elevator was an important and essential element of the agreement. The reason for this insistence on the part of the defendant was that it had already negotiated and was about to execute a lease of the premises from February 1st, under which the tenant was to pay no rent until at least one elevator had been installed and was in running order. It was shown that plaintiff at the time of making its contract with defendant, or very shortly thereafter, had lcnowledge^of the making of such -a lease, and that its agent in the transaction between plaintiff and defendant had knowledge of the special clause respecting the payment of the rent. At all events, from the character and size of the building, the plaintiff might well be held bound to know that its value for rental purposes would be much affected by the existence or nonexistence of proper ele
The judgment must be reversed and a new trial granted, with costs to the appellants to abide the event. All concur.
Cases cited
- Dunn v. Strubing 120 N. Y. 232 p. 413