Majority
Headnote
1. Contract—Supplying Electric Power—Action foe Breach—Complaint —Allegations of Performance—Sufficiency.The plaintiff having demurred to four separate counts of the defendant’s answer for insufficiency, the defendant, as it may properly do, challenges the sufficiency of the complaint. And such demurrer brings before the court the whole record, and judgment goes against the party having the first insufficient pleading. Baxter v. McDonnell, 154 N. Y. 432 , 48 N. E. 816 . And this rule applies with equal force whether the demurrer is to an alleged defense or an alleged counterclaim. Village of Little Falls v. Cobb, 80 Hun, 20 , 29 N. Y. Supp. 855 . In determining the sufficiency of the complaint and of the answer the pleading must be liberally construed, and every allegation, whether expressly or only impliedly or argumentatively averred, is admitted. Nat. Contracting Co. v. Hudson R. W. P. Co., 170 N. Y. 439 , 63 N. E. 450 ; Atkins v. Judson, 33 App. Div. 42 , 53 N. Y. Supp. 504 .
First, at to the complaint. It seeks to recover payment for furnishing the electrical energy under the written contract which it states is “ready to be produced when and "where this court may direct,” and then purports to give the pleader’s conclusion as to what the contract is, reciting that the plaintiff was to furnish to the defendant electrical energy beginning July 1, 1902, and continuing 10 years, id agreed amounts monthly, and for August, energy equal to 2,750 electrical horse power, for which it was to receive $4,670.84. All of the payments, less certain deductions, if any, were to be made prior to the 10th day of the next ensuing calendar month, and the deficiencies in the amount of energy supplied were to be compensated for at a fixed rate. That during the month of August the energy was furnished, as agreed, of the value of $4,670.84, “less certain small deficiencies, which, as measured and computed by the defendant, entitled the latter to the deductions at the rate specified in the said contract,” aggregating the sum of $210.26, leaving due to the plaintiff a balance of $4,460.58 for the month of August, and" alleges nonpayment, and seeks to recover $350,000 prospective profits. The demurrer admits that a copy of the contract is attached to the answer, and the reference to the contract in the complaint as “ready to be produced when and where the court may direct” makes that contract when produced and identified a part of the complaint itself. The contract itself therefore takes the place in the complaint of the conclusions of the pleader as to its terms. In the fourth paragraph of the contract it is provided that if by reason of accident, lack of water, or other matter beyond its control,.the power company shall at any time be unable to furnish the electrical, energy fixed in accordance with the terms of this agreement, the traction company shall have the right to deduct a certain price per horse power for such deficiency, which is fixed as the liquidated damages “for failure to furnish said electrical energy as herein provided.” . Section 13 of said agreement provides: “This agreement is an entire contract, each stipulation thereto being a part of the consideration for every other and by the sixth provision of said contract it is provided that the
As to the counterclaims, the plaintiff contends that the matters alleged are not proper subjects of counterclaim, for the reason that they do not coexist with the plaintiff’s claim, but, if true, destroy it, and are therefore matters of defense, and not counterclaims; that the plaintiff alleges it has performed and the defendant defaulted on a certain contract, and it is not legitimate for the defendant by way of counterclaim to allege that it has performed and the plaintiff has defaulted, and seek an affirmative recovery. It seems to be the policy of the law to settle one dispute in a single action, and not drive litigants to cross-actions. If plaintiff claims damages growing out of the contract or transaction, the defendant may deny its liability or default, and as a counterclaim allege and establish the liability and default of the plaintiff and recpver its damages. Our Appellate Division has given this rule a wide application in holding that a defendant sued for an assault and battery may deny that he was the aggressor, and as a counterclaim allege that the plaintiff was the aggressor, and recover his damages therefor. Deagan v. Weeks, 67 App. Div. 410 , 73 N. Y. Supp. 641 . It is true that matter purely defensive, and not containing the elements of a cause of action, cannot become a counterclaim by calling it so. Walker v. American C. Ins. Co., 143 N. Y. 167 , 38 N. E. 106 . In this last case, where the defendant claimed that its answer was admitted by failure to reply, the court held the answering matter was purely defensive, and that although the defendant demanded a reformation of the policy, the subject-matter of the policy being destroyed, the facts did not constitute a cause of action, but practically concedes that, if the property to be insured still existed, so that a cause of action was alleged for reformation, it would be a counterclaim, although it was also matter constituting a defense. I therefore hold that the matters alleged in the various answers as counterclaims are proper, if sufficiently alleged.
As to the ninth answer, the alleged counterclaim alleges the contract-; that by its terms the plaintiff was to furnish and the defendant take all the excess of electrical energy above that mentioned in the first item of the contract that the plaintiff’s water-power plant was capable of producing, and that it did produce a large amount of excess of energy, but in violation of said contract the plaintiff wrongfully failed and refused to deliver the same to the defendant, but sold it to others, against the defendant’s protest, and in violation of the contract, and that by reason of said breach the defendant had sustained damages $1,073.20. To the criticism that this answer does not allege a request to deliver the energy,, it is an answer that it was utterly useless for the defendant to request the delivery if the plaintiff had already refused it, and delivered it to others, against its protest. Shaw v. Republic Life Ins. Co., 69 N. Y. 286 ; Robinson v. Frank, 107 N. Y. 655 , 14 N. E. 413 . And the plaintiff’s agreement was an independent one to deliver the energy before payment was required, and its performance was to precede any act of the defendant. 9 Cyc. 719. I therefore hold this answer sufficient.
The tenth answer alleges the contract and its performance by the
The eleventh answer the plaintiff treats as a counterclaim, but it is alleged only as a further answer and defense, both in law and equity. No affirmative judgment is asked, and it should be treated as a defense, rather than a counterclaim. It alleges the contract; the plaintiff’s failure to furnish the full amount of energy required by subdivision 1 of the contract, such deficiency amounting to $216.65; the failure to deliver the surplus energy provided for by section 6 of the contract; that plaintiff did produce such surplus, and could have delivered it, but refused to do so, and sold it elsewhere, in violation of the contract, to the defendant’s damage of $1,073.20. It then alleges that a course of dealing had grown up between the parties whereby the plaintiff presented no bills, but the engineers of the parties got together some time during the month-after the energy was supplied, determined the amount of energy used, and any deficiencies to lie deducted and arrived at the result due; that at the meeting so held the defendant claimed credit for both of said items, and the plaintiff’s representative consented to allow the first item, but objected to the second, and requested time and opportunity to refer it to the other officers of the plaintiff, saying he would report after such determination. Defendant assented to such time, and, relying upon such negotiation, and the request of the plaintiff for time, the payment was not made by the 10th of September, the law day, and the amount had not then been ascertained; that defendant was ready and willing to pay, and at the time of the meeting offered to pay if said items were deducted, or whatever amount was determined to be due; that defendant did not then or now want to rescind said contract, but the same was valuable, and it was desirous and is now desirous to pay whatever is due, and to continue the same; that its omission to pay arose from such negotiation,, and that the plaintiff had seized that pretext to declare the contract forfeited, and at midnight on the 10th of September repudiated the contract, and refused to perform the same, to the defendant's damage of $1,369,-444.44. These matters must certainly be a defense to the cause of action alleged in the complaint, or to some part of it. If true, it is certainly a defense to the claim of $350,000 prospective profits sought to be recovered. And, even though plaintiff has not properly alleged a cause of action as to such profits, it cannot defeat the answer aimed at it by claiming that its own pleading does not sufficiently. state a cause of action in that respect.
The twelfth answer repeats the allegations of the eleventh answer, and alleges that the plaintiff, after making the contract, sold itself to the Hudson River Electric Company, and thereafter the said electric company sold itself to the Hudson River Water Power Company,
Perhaps it was not necessary to, set out all these matters in the various answers, and there may be unnecessary repetitions, but that question is not before the court. It is only the question as to whether the matters alleged in each answer are a defense or counterclaim. The demurrer to the several answers ■ is therefore "overruled, and interlocutory judgment is directed accordingly, with leave to the plaintiff, upon paying $35 costs, to withdraw said demurrer, to amend its complaint if so advised, or to reply. The form of judgment may be submitted, and, if not agreed upon, will be settled on five days’ notice.
Judgment accordingly.
Cases cited
- Baxter v. McDonnell 154 N. Y. 432 p. 450
- National Contracting Co. v. Hudson River Water Power Co. 170 N. Y. 439 p. 450
- Atkins v. Judson 33 App. Div. 42 at 53 p. 450
- Spence v. Ham 163 N. Y. 220 p. 451
- Van Clief v. Van Vechten 130 N. Y. 571 p. 451
- William Wharton, Jr., & Co. v. Winch 140 N. Y. 287 p. 452
- Walker v. American Central Insurance 143 N. Y. 167 p. 452
- Shaw v. Republic Life Insurance 69 N. Y. 286 p. 452
- Robinson v. Frank 107 N. Y. 655 p. 452