Majority
Headnote
1. Contracts—Breach of Guaranty—Measure of Damages.Prior to May 15, 1902, the plaintiff and defendants had some negotiations looking to the installation of a hot-water heating apparatus in plaintiff’s residence in the city of Rochester, N. Y. One of the defendants inspected the house, measured the rooms to be heated, and as a result, on said 15th day of May, submitted to the plaintiff a proposal, with specifications attached, for installing the plant. Such offer, which was accepted by the plaintiff, was, in effect, that the defendants would properly install a heating system, which would heat the rooms mentioned in the specifications to a temperature of 70° in zero weather, for the sum of $250. The defendants claimed to have completed the work in accordance with the terms of the contract,, early in September, 1902, and the plaintiff paid the full contract price, together with $10 additional for “extras.” At the time such payment was made, the condition of the weather was such as to render it impossible to make a practical test of the heating qualities of the plant, or to know whether or not in zero weather it was capable of heating the house to 70°, as warranted to do.
During the latter part of November, however, the plaintiff attempted to heat his house, and found that the plant could not be made to accomplish the results guarantied, and so notified the defendants. They made several attempts to adjust the apparatus, sought to improve the draft, and did various other things in the endeavor to comply with the terms of the contract. The plaintiff claimed that such efforts were wholly unavailing, and he thereupon notified the defendants, in effect, that the plant was not as required by the contract, that it was impossible to heat the house in such manner as the defendants expressly warranted could be done, and asked them, in effect, to remove the plant installed by them, and notified them that if they did not, it would be removed by the plaintiff, and kept or stored subject to their order. The defendants made no further efforts to remedy the alleged defects, but claimed that they had fully performed their contract.
Under the contract in question, the plaintiff, assuming that the heating apparatus was not capable of doing the work which the defendants warranted it would do, had either one of two remedies: he might have required the defendant to remove the same, or, if they failed to do so,
Judgment modified, by directing a new trial in Municipal Court, and, as so modified, affirmed, without costs of this appeal to either party.
All concur.