Majority
Headnote
1. Master and Servant—Injuries to Servant—Fall of Building—Negligence.The defendant is a domestic corporation engaged in the brewing business in the borough of Brooklyn, New York City. The plaintiff, in September, 1901, was in the employ of a contractor who had engaged to fill certain coal pockets on the defendant’s premises, and while he was at work under the pockets the entire structure fell, inflicting the injuries of which he complains. I do not find reversible error in any of the rulings of the trial court, and the verdict cannot be regarded as excessive. If there is, therefore, sufficient evidence to justify the submission to the jury of the question of the defendant’s negligence, the plaintiff is entitled to retain his judgment.
The coal pockets in question had just been built at or shortly before the time of the accident, and were being filled with coal for the first
In claiming immunity for their client for the consequences of the accident; the learned counsel for the appellant rely upon the proposition established in Burke v. Ireland, 166 N. Y. 305 , 59 N. E. 914 , that the owner of a building in process of erection is not responsible for the defective execution by a contractor of a competent plan of construction. The case has no controlling application. The measure of liability is different in the case of an unfinished building from one which has been completed, accepted, and in use. This was pointed out by Mr. Justice Cullen in Murphy v. Altman, 28 App. Div. 472 , 474, 51 N. Y. Supp. 106 , in the following words: “The case of a building in the course of. construction is very different from that of a completed structure, which is used and occupied for. business purposes, which persons are invited to enter, and which such, persons have a right to assume is reasonably safe.” Aside from this consideration, however, the evidence in this case tends to affirmatively establish negligence on the part of the defendant. It had received at least two warnings before the accident that there was some defect in either the plan or structure, which rendered it dangerous to load the pockets to their capacity, and the jury was entitled to' conclude that in such circumstances it was not reasonable care to proceed with the work and its attendant risks with no other safeguard than the temporary, and, as the event proved, inadequate, means adopted to secure the safety of the workmen. In addition to this, there is some evidence that a hoisting apparatus, which occasioned additional weight and strain, was attached by the defendant to the structure, and that the architect by whom the structure was planned had not been informed, when he designed it, that it would be subjected to this added burden..
It follows that the judgment and order should be affirmed.
Judgment and order affirmed, with costs. All concur.
Cases cited
- Burke v. Ireland 166 N. Y. 305 p. 960
- Murphy v. Altman 28 App. Div. 472 at 474, 51 p. 960