Majority
Headnote
1. Contracts—Payment—Pleadings—Admission.The action is brought to recover the sum of $4,100, being the balance of the contract price for the removal of snow and ice from certain streets of the city of New York, which was deducted by the city from the final payment upon the ground of a violation of the contract by the plaintiff, and pursuant to a liquidated damage clause contained therein. The referee found that on the 4th day of February, 1901, three inches of snow fell in the city, and before 3 o’clock in the afternoon the snow inspector, by direction of the commissioner of street cleaning, served notice in writing upon the plaintiff for the removal of the snow from about 4,100 city blocks covered by his contract; that the plaintiff failed to commence the work of removing the snow in part of the district within the time specified and required by the contract, and that it failed to employ at any time as many men on any of the gangs in one of the districts as it was its duty to do under the contract; that, although it was the duty of the plaintiff to commence the work by 7 o’clock that evening, and to prosecute the same with diligence, it failed to commence part of such work before the following afternoon, and practically abandoned the work in part of the district on the morning of February 5th; that the plaintiff only removed a small quantity of the snow that fell on 102 blocks during that storm, and, although it commenced the work in part of the territory, it failed to prosecute the same with the diligence required by the contract, or to employ in the performance of the work the number of men directed by the commissioner of street cleaning, as provided in the contract. Although there is no special contention on the part of the appellant that it was not guilty of a violation of its contract, a careful review of the evidence leads to the conclusion that the referee was justified inc finding the appellant guilty of breaches of the contract as specified.
The city pleaded as a defense to the action a general release alleged to have been executed and delivered by the plaintiff at the time of receiving the last installment as a final payment; and also that it was warranted in deducting the amount for which suit is brought by virtue of a liquidated damage clause contained in the contract for the breaches of the contract on the part of the plaintiff. The learned counsel for the appellant concedes that, if the release was executed, and the seal attached thereto in the regular way, it would bar a recovery; but he contends, in brief, .that the instrument presented as a release does not bar a recovery for two reasons : First, that it was executed by mutual mistake; and, second, that the certificate of acknowledgment, which was prima facie evidence of the due execution of the release by authority of the plaintiff, was rebutted by evidence showing that the seal was not affixed by authority of the company, and that the release, therefore, became merely a receipt for-the amount of money actually paid at the time, and recited therein, which it is claimed was concededly due. The claim that the final payment actually made was concededly due is based upon an admission contained in the answer of the defendant, which we think should not be so construed. The answer admits that between the 31st day of January and the 6th day of February,
The learned referee held that the liquidated damage clause of the contract was void upon the ground that by other provisions of the contract the city was fully indemnified against all actual damages, and that, therefore, the liquidated damage clause, instead of providing for damages which were difficult of ascertainment, in fact provided for an arbitrary penalty. We think the learned referee overlooked one important element of damages which was not covered by the other provisions of the contract, and which, in its very nature, would have been most difficult of ascertainment. This contract related to the removal of snow and ice from many of the principal thoroughfares in the portion of-the city where travel is great and congested. If the snow and ice, after being collected in piles for removal, should be allowed to remain for even a comparatively brief period of time, the city might be held liable for personal injuries upon the theory of negligence by those traveling in vehicles. It is quite likely that the city could not readily employ others prepared to promptly remove the snow and ice in case of the failure of the plaintiff to perform its contract. The liquidated damages authorized by the contract are startlingly large, and, in the view we take of the case, it is unnecessary to decide whether or not that provision of the contract could be sustained. „We make these observations, not with a view to expressing an opinion that the liquidated damage clause of the contract was valid and enforceable, but
The final payment made on the contract was $2,259.60, and it was made to the president of the company on the 10th day of May, .1901. Evidently, pursuant to a custom in such cases, the comptroller caused a notice to be sent by a postal card to the plaintiff that the voucher was ready for payment. Pursuant to this notice, R. T. Rokeby, the president of the company, called at the comptroller’s office on the 10th day of May, 1901, and applied to Timothy W. Crowley, the acting disbursing officer, who was known to Rokeby, and from whom Rokeby had on other occasions received warrants. The conversation between Crowley and Rokeby is in dispute. The evidence shows that Crowley handed to Rokeby a bundle of papers for signature or execution. One of these was a voucher showing the amount due the plaintiff on this contract, containing separate certificates by the inspector, the deputy commissioner, the chief clerk, the commissioner of street cleaning, and the deputy auditor, following which was a form of receipt reciting the receipt of the comptroller’s warrant for $2,259.60 “in full payment of above account.” This Rokeby signed in the name of the company, by him as president. Either attached to this voucher, or as a separate paper referring to it—the evidence does not clearly show which-— was an affidavit for execution by Rokeby, showing that the account was correct; that the services for which the charge was made had been duly authorized and rendered, and were reasonable and just, and had not been paid; that the account had. not been assigned, and that no perquisites or commissions had been paid therefor. This affidavit Rokeby signed and swore to before Crowley as a commissioner of deeds. Another of the papers consisted of a receipt which Rokeby executed in like manner as the former. It recited more fully that the plaintiff had received from the comptroller warrant No. 10,267A, for the sum of $2,259.60, “in full of the within contract, No. 3,221, for the removal of snow and ice.” With the other papers delivered to Rokeby was the. comptroller’s warrant, which he retained for the plaintiff. Another of the papers was a general release reciting-that the plaintiff, in consideration of the payment of said sum, among other. things, released the defendant from all liability under the contract for the removal of snow and ice to which reference was specifically made, and that the plaintiff had caused its corporate seal to be affixed thereto, and its corporate name to be signed thereto, by its president. This release Rokeby also signed as follows: “Uvalde Asphalt Paving Company, by R. T. Rokeby, Prest.” Attached to the release is the genuine seal of the company, and it purports to have been attached in the presence of Crowley on the same day, and to it is attached a certificate of acknowledgment by Rokeby as president, in the usual form of corporate acknowledgments, before Crowley, as commissioner of deeds, on the same day. Rokeby testified that he did not acknowledge this release, and that he signed it without reading it, or knowing that it was a release; and further testified, in substance, that he had received payments upon other con
The learned referee was justified in discrediting the testimony of Rokeby tending to impeach the certificate of acknowledgment. He would not admit the genuineness of the seal, saying that it might have been purchased for $2. His testimony was in other respects contradictory, unreliable, and improbable. Rokeby knew that there was a controversy between him and the city with reference to this contract, and particularly with respect to a deduction for liquidated damages. . It is utterly improbable that in these circumstances he executed these various papers, as he testified, without noticing what they were. Moreover, with respect to an interview that subsequently took place between him and Crowley, he is directly contradicted by Crowley, whose testimony appears to be entirely fair and honest. We therefore agree with the learned referee that the presumption of the due execution of the release raised by the certificate of acknowledgment- is not overcome.
It therefore follows that the judgment should be affirmed, with costs. All concur.