Majority
Headnote
1. Brokers—Sales of Real Estate—Action for Commission—Authority to Act—Statutory Provisions—Sufficiency of Written Authority.The only agreement in writing between the plaintiff and the defendant is the one dated August 4, 1904, by which the, plaintiff agreed to take payment of commission for selling the southwest corner of 100th street and Madison avenue for $60,-000, for William Lane, to John E. Olson, as,follows: “One-half when second payment of building loan is due and payable, and balance immediately after inclosure payment is due and made.” This agreement appears to have been signed the day the defendant delivered to the purchaser a deed of said property. The case does not show that the' plaintiff, the broker, had the written authority of the owner of the property to make a sale, and want of such authority was alleged in the answer. It does not appear whether the paper of August 4th was or was not signed before the deed conveying the property to said Olson was signed. It if were signed before such deed, we are of the opinion that it would be a sufficient compliance with section 640d of the Penal Code. But the burden was on the plaintiff of establishing that at the time he made the sale, he had the written authority required by the statute and decisions to make the sale, and, not having established that fact, it is well settled, at least in this department, that he cannot recover. Borgio v. Gange (Sup.) 87 N. Y. Supp. 538 ; Cohen v. Boccuzzi (Sup.) 86 N. Y. Supp. 187 ; Whiteley v. Terry, 83 App. Div. 197 , 82 N. Y. Supp. 89 .
But, irrespective of the point above stated, there is another reason for reversing the judgment. If the paper of August 4th be treated as a compliance with the statute, then plaintiff was to be paid one half of the amount due when the second payment of the building loan was due and payable, and was to be paid the other half immediately after the inclosure payment was due and paid. The evidence shows that neither one of these events has happened, and that the reason they did not happen was because of the failure of the purchaser to comply with the terms of the building loan agreement. There is no allegation on the part of the plaintiff that the contingency or contingencies contemplated by the agreement of August 4th had ever happened, nor was any excuse for there not having happened pleaded.
The judgment is reversed, and a new trial ordered, with costs to the appellant to abide the event. All concur.
Cases cited
- Whiteley v. Terry 83 App. Div. 197 p. 1084
- Tooker v. Arnoux 76 N. Y. 397 p. 1085