Headnote
1. Mechanic’s Lien—Evidence—Substantial Performance.The plaintiff claims a lien for the balance of the contract price upon completion of the building, less the value of certain minor items concededly omitted, and, in addition, for the value of extra work. As the action is framed, the recovery must depend upon the plaintiff’s substantial performance of his contract; and, while the other points in dispute may, perhaps, be deemed insufficient to oppose a finding that the contract was substantially performed, it is impossible to escape the conclusion that there has been a material and substantial omission in the construction of the foundation walls of the building; an omission which the plaintiff failed to supply after notice and an ample opportunity,
What the cost of carrying the foundations to the proper depth might be is not proven, and, of necessity, that cost cannot but be substantial in view of the nature of the defect to be supplied. As the case stands, therefore, there has been a material omission of performance, and the plaintiff has not discharged the burden of showing substantial performance, so far as the omission might be made the subject of deduction from the contract price. Furthermore, the required course of flat stones was omitted, and the plaintiff has not controverted the defendant’s testimony that this requirement was modified only on condition that concrete of a certain thickness be substituted, which condition was not performed.
Of the two items of extra work claimed, I find that the “saddle” supplied should be allowed for, in the sum of $41.23, and the further
Judgment for plaintiff, without costs.