Majority
Headnote
1. Indemnity Bonds—Construction—Breach—Notice to Surety.This suit is brought against the defendant, as surety, upon a bond executed by Edward Egenberger, as principal, conditioned for his faithful performance of a written contract with the plaintiff for completing the construction of four unfinished houses in the borough of Brooklyn. These houses had belonged to the plaintiff. They were subject to four first mortgages
The case turned upon the proper answer to be given to two questions : (1) Whether the plaintiff notified the defendant, as he was required to do by the terms of the bond, of the first act on the part of Mr. Egenberger which involved a loss for which the defendant was responsible thereunder, immediately after acquiring knowledge of the occurrence of such act; and, (2) whether the action was brought in time, in view of the provision in the bond to the effect that any suit at law to recover any claim thereunder must be instituted within six months after the first breach of the building contract. The learned trial court answered both these questions in the negative, and directed a dismissal of the complaint on the merits.
1. As to the first question, the provision of the bond, necessary to be considered reads as follows:
“Provided that said surety shall be notified in writing of any act on the part of the said principal, or his agent or employés, which shall involve a loss for which the said surety is responsible hereunder, immediately after the occurrence of.such act shall have come to the knowledge of the duly authorized representative or representatives of the obligee, who shall have the supervision of the completion of the said contract *' *
The contract between Mr. Egenberger and Mr. Burr for the completion of the houses was dated November 11 and acknowledged November 13, 1901. The property was conveyed to Mr. Egenberger by a deed acknowledged on the latter date, and it is not disputed that he then entered into possession of the premises. 'The contract required him within one week from the execution and delivery thereof “to enter upon and thereafter proceed with the
“If at any time the party of the first part [Edward Egenberger] shall fail to push the work on the said buildings vigorously, of which fact the party of the second part [Joseph A. Burr] shall be the sole judge, and such default and neglect shall continue for ten days after the service of a notice on the party of the first part to that effect, the said bonds and mortgages shall at once become due for the whole amount advanced thereon.”
Mr. Egenberger never did any work whatever upon the buildings. The proof does not show clearly when the plaintiff became aware that nothing was being done toward the execution of the contract, but the testimony of his representative, Mr. John T. Bladen, an attorney in his office, indicates that he was chargeable with knowledge of the fact by the 14th of December, 1901. On the 20th he notified Mr. Egenberger that he considered him in default, and that, if such default continued for 10 days, he should and did elect that the bonds and mortgages should become due. On the same day notice to the same effect was sent by the plaintiff to the defendant.
In the opinion of the learned trial judge, which appears in the appeal book in the form of a letter addressed to the attorney for the plaintiff, the first ground stated for the dismissal of the complaint is:
“That the evidence does not show the giving of a notice of the failure of Egenberger to enter upon the erection of the building immediately after the same came to the knowledge of the duly authorized representative of the plaintiff.”
This ground was sufficient, if the bond entitled the defendant to immediate notice of the contractor’s omission to begin work within a week after the execution and delivery of the building contract. It seems to me, however, that the bond cannot fairly be construed so strictly. The fair and natural import of the language employed was to require Mr. Burr immediately to notify the surety whenever such a condition of things arose as to show that the contractor had violated his covenant to complete the erection and construction of the building with diligence and without unreasonable delay. There is no suggestion anywhere of bad faith on the part of the plaintiff or of collusion with the contractor, and it cannot be held as matter of law, upon the proof in this record, that the delay was unreasonable up to the time when Mr. Burr addressed his letter to Mr. Egenberger announcing his election to deem the mortgages presently due in case the contractor’s default continued more than 10 days longer. Mere delay did not entitle the surety to notice. It was only when such delay became unreasonable, and therefore violative of the builder’s contract with the plaintiff, that the surety was entitled to be notified, to the end that it might take means, if so advised, to protect itself against further inaction by the principal which would render it liable upon its bond. In my opinion, the trial court erred in holding that the plaintiff was precluded from a recovery by reason of having waited too long to inform the defendant of Mr. Egenberger’s failure to go to work.
. For the foregoing reasons, I think the plaintiff is entitled to a reversal of this judgment.
Judgment reversed, and new trial granted; costs to abide the event. All concur.
Cases cited
- Gilbert v. Wiman 1 N. Y. 550 at 561, 49 p. 118
- National Bank of Newburgh v. Bigler 83 N. Y. 51 at 61, 62 p. 118