Majority
Headnote
1. Mechanics’ Liens—Right to Lien—Performance of Contract.The claim of the plaintiff, the Otis Elevator Company, for the balance of the contract price for installing an elevator upon the premises in suit is resisted upon the ground that there was such a defect in the performance of the contract that the lien may not be established upon the basis of substantial performance; the ground of the defense being that the plaintiff wholly departed from the plans furnished with regard to the position of the doors giving entrance to the elevator at the different floors of the building. The contract provided for the installation of an elevator and apparatus of a certain size and with certain details of construction, which contract was sufficiently specific in all matters other than the position of the elevator in the building, and, if deemed important by the parties, the position of the entrance doors in relation to the elevator shaft. So far as to supply omitted details necessary for an understanding of the intention of the parties, the architect’s plans, which were furnished to the plaintiff, may probably, as contended by the defendant, be resorted to as illustrative of the agreement, although not specifically referred to by the writing.
It is true that the plaintiff, when so constructing the elevator that the swing door upon the first floor necessarily was hinged from the left, did depart from the architect’s plans as to that particular floor so far as the plans showed the proposed position of the door, but, in view of the necessity for uniformity in the position of all doors opening upon the shaft, and of the fact that the plans as to the majority of other floors shown upon them provided for a reverse method of opening of the doors, it is impossible to say that the plans controlled, because of their total lack of definiteness in their relation to the work covered by the contract. The plaintiff - was justified in interpreting the plans as it did, and that its interpretation was sufficiently reasonable is also shown by the fact that the blue print prepared by it as a basis for the actual work done was never objected to when submitted to the defendant’s architect for approval.
. The claim of the lienor Hodkinson arises out of a contract for the installation of a steam-heating plant in the building, the items of the claim being $621.17, the balance of the contract price, together with $115 for extra work. It is contended by the owner that there were defects in the steam-heating apparatus, in that there was a lack of uniformity in the distribution of heat as between the radiators in the front of the house and the radiators in the rear, which defects, it is claimed, render the plant useless, and are due to some latent infirmity in the system. Upon the question of fact presented by the evidence as to thi.s, I am inclined to hold that such inequality of distribution of heat as may have been found was due, not to defects in the system, but rather to the manner of its maintenance, and the lienor is therefore entitled to judgment establishing the lien for the balance of the contract price, as upon substantial performance, lessened by the amount of three items of work omitted or not strictly performed, which will be allowed to the owner as deductions as follows: blow-off pipe, $5; check valve, $4; lowering return pipe, $25.
As to the claim for extra work, I do not find that the preponderance of the evidence is with the lienor upon his claim for work in connection with installing the boiler; this work being apparently covered by the contract. But as to the item of $40 for installing an extra radiator, I find that the work so far was extraneous to the contract, and was performed at the request of the owner. This item of $40, therefore, will be allowed.
I find no sufficient ground for holding that there was any deliberate falsification upon this lienor’s part for the purpose of enhancing the amount of his lien, as contended by the owner, and judgment is therefore to be rendered in favor of this lienor for the sum of $587.77, the amount due upon the contract, together with $40 for extra work—in all, the sum of $627.77.
Judgment accordingly.