Majority
Headnote
Municipal Corporations—Obstruction of Streets—Negligence.This litigation arises out of the construction of the so-called “subway” in this city, which work was undertaken under the provisions of the various acts of the Legislature of this state, passed during the years 1892, 1893, 1894, 1895, and 1896. As provided for by this legislation, a rapid transit commission was organized, a route was determined upon, and the contract for the construction of the road was made with John B. McDonald, who was the successful bidder in the competition between contractors; all working and figuring upon the invitation of the commission upon the basis of “a form of contract” annexed to the request made of them to offer bids. The proposed construction was to be underground in the main, and to traverse Manhattan Island from the Battery northward. It was to be built in sections, and the section which began at Great Jones street and ran northward to a point on Fourth avenue between Thirty-Third and Thirty-Fourth' streets, was known as section three. From Fourteenth street to Seventeenth, street, extending from Fourth avenue on the east to Broadway on the west, is an open park space know as “Union Square,” and that part of Fourth avenue between Fourteenth; street and Seventeenth street has come to be designated as “Union Square East.” The construction of section 3 was sublet by the contractor, McDonald, to the firm of Holbrook, Cabot & Daly, and by them in turn assigned to the Holbrook, Cabot & Daly
The plaintiff complains of the erection of said superstructure immediately in front of its place of business during a period from May 1, 1901, to August 1, 1902, and seeks to restrain said defendant from maintaining said structure in front of its place of business, and to recover damages for its deprivation of the easement of access during the period it was maintained, and for the impairment of the rental value of its premises and for the partial destruction of its carriage and soda water fountain trade. The structure complained of was removed before the trial of this action and the plaintiff now seeks to recover damages as aforesaid. The plaintiff contends that neither the statutes nor the contract for the building of the subway authorized the performance • of the acts of the defendant, and that the defendant’s method of construction, and particularly of disposing of the Metropolitan Company’s roadway, was improper and unskillful, and that the damages which the construction caused are not a necessary consequence of a public work, and were occasioned by the unskillful and improper manner of its performance, while, the. defendants contend that they are not liable in damages to the plaintiff for the erection of the structure complained of because it was engaged in the performance of a work of a public nature, authorized by law, and that, therefore, they are not liable for consequential damages occasioned by them to others unless caused by their misconduct, negligence, or unskillfulness.
“The doctrine, however,' is well established in this state that public officers lawfully employed in making public improvements, and corporations engaged in performance of work of a public nature authorized by law, are not liable for consequential damages occasioned by it to others unless occasioned by misconduct, negligence or unskillfulness.”
In this case the court distinguishes between damages caused by the erection of a public improvement and damages occasioned by a trespass or a permanent encroachment. In the case of Fries v. New York & H. R. R. Co., 169 N. Y. 376 , 63 N. E. 359 , the court states:
“The law is well settled in this state that where the property of an abutting owner is damaged, or even his easements interfered with in consequence of the work of an improvement in a public street conducted under a lawful authority, he is without remedy or redress, even though no provision for compensation is made in the statute. Whatever detriment the improvement may he to the abutter in such cases, is held to be damnum absque injuria.”
The case of Lewis v. New York & H. R. R Co., 162 N. Y. 202 , 56 N. E. 540 , which cites with approval Taylor v. New York & H. R. R. Co., 37 App. Div. 190 , 50 N. Y. Supp. 697 , seems to be in com flict with the cases above cited, but in this case the court used the following language:
“We have decided the case before us and have not tried to decide other cases, which, although arising .in the same section, rest upon different facts, and may be controlled by different principles of law.”
And the same court, in a later case, namely, Fries v. New York & H. R. R. Co., supra, two of the judges who wrote opinions admitted th'at its decision was in conflict with the Lewis Case, one of the judges who wrote a concurring opinion using the following language, viz.:
“While I agree generally with the views expressed by Judge O’Brien, I still think that the decision about to be made can be said to be in conflict with the Lewis Case, and to such extent as it is, the Lewis Case should be regarded as limited.”
In the case of Bates v. Holbrook, 171 N. Y. 468 , 64 N. E. 183 the court concedes the following propositions to be correct: First, that the law is settled in this state that acts which are authorized by express enactments of the Legislature and performed in good faith upon a work of a public character do not render the persons performing them liable for consequential damages, unless there is an absence of due care and skill in the execution of the work; second, that in authorizing the construction of a railroad under the streets of New York the Legislature may be deemed to have authorized the performance by the rapid transit commission and by the contractors of such acts as are necessary to the execution of the work. It is true that in the Bates Case the court held that the plaintiff was entitled to recover for damages, but it was so held upon the specific ground that
There is no contention that the work performed by the defendant was defective or unskillful from the standpoint of technical engineering; but it is contended by the plaintiff that the work could have been performed quite as well by the defendant without constructing the superstructure complained of and maintaining it to the detriment of the plaintiff from the 1st day of May, 1901, to the 1st day of August, 190.3. Plaintiff conceded that during the time when it was necessary to dig the trench immediately in front of his premises, to wit, on the east side of the roadway, he would be obliged to suffer the inconvenience and injury consequent upon the performance of a work of a public character for the benefit of the community; but that it was not necessary to build the superstructure immediately in front of his premises for the purpose of excavating that portion of the tunnel which was located in the center of the street under the car tracks of the Metropolitan Railway. The evidence on this question is conflicting; the experts for the plaintiff contending that the superstructure could have been avoided had the excavating been started from the east side of the street instead of the west side, or by building a temporary structure over the trench, which was originally dug out on the west side of the street, or by building temporary, tracks west of the said trench originally built on the west side of the road. The defendant’s experts, however, contend that while the methods suggested by thei plaintiff’s experts were possible, they were not feasible, for the reason that they would occasion undue delay, which would postpone the completion of the entire subway, and that they would cause unnecessary damage to abutting property on the east, and that they would be unworkmanlike, and that to place temporary tracks west of the westerly trench would be to invade Union Square Park and would cause great delay by reason of the location of the Everett House hotel, which would be directly in front of said temporary tracks and would occasion the construction of said temporary loop at great expense and delay.
It appears from the evidence that the defendant, after the.completion of the trench on the westerly side of the'street, did attempt to take away the rock from under the car tracks in the center of the street without removing the tracks; but it became dangerous to do so, because
It also appears from the testimony- of the defendant’s experts, and from the testimony of the officer of the defendant, Holbrook, that it would have been unworkmanlike and dangerous to blast from the east side of the street, instead of the west, by reason of the fact that the easterly side of the street was abutted by numerous buildings, while the westerly side was abutted by the park, and that the whole section of this particular location was of solid rock and had to be blasted by numerous heavy charges of explosives. It also appears from the testimony of defendant’s officer, Holbrook, and the defendant’s experts, that it would not have been feasible to lay the temporary tracks of the Metropolitan Railway on the easterly side of the street level with the surface of the. street, because of the location of pipes and mains under the street at that 'point which would have to be lowered several feet, which Avould have necessitated the blasting of the rock at least a couple of feet in order to make sufficient room for placing the yokes of the car tracks on a level with the street. The evidence of the plaintiff’s experts in no way, in my opinion, contradicts the evidence of the defendant’s in these particulars in substance: At most they prove that it would have been possible to have adopted some other method than the one adopted by the defendant, but that such methods would have been attendant with considerable delay, which would have tied up the completion of the whole subway for a considerable time and with considerable danger to the property abutting on the easterly side of the roadway.
I am therefore of the opinion that the. defendant exercised proper judgment, skill, caution, and diligence in completing its contract,- and is entitled to a judgment herein in its favor.
Cases cited
- Lewis v. New York & Harlem Railroad 162 N. Y. 202 p. 678